Universal Plant Services of Nashville, Inc. v. Boland Trane Services, Inc.

CourtDistrict Court, D. Maryland
DecidedAugust 6, 2024
Docket8:21-cv-01188
StatusUnknown

This text of Universal Plant Services of Nashville, Inc. v. Boland Trane Services, Inc. (Universal Plant Services of Nashville, Inc. v. Boland Trane Services, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Universal Plant Services of Nashville, Inc. v. Boland Trane Services, Inc., (D. Md. 2024).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

UNIVERSAL PLANT SERVICES OF * NASHVILLE, INC. * Civil No. TJS-21-1188 v. * BOLAND TRANE SERVICES, INC. *

* * * * * *

MEMORANDUM OPINION

When a party to a contract breaches its obligations, it must pay for damages proximately caused by its breach. It is not required to pay for other damages. In this case, Universal Plant Services of Nashville, Inc. (“Universal”) contracted with Defendant Boland Trane Services, Inc. (“Boland”) to remove, repair, and reinstall a machine. Universal breached the contract by failing to align the machine with other equipment. Because Universal breached, Boland is not required to pay for Universal’s work. At the same time, Universal does not have to pay for Boland’s damages because they were not caused by Universal’s breach. Instead, they were caused by Boland’s decision to run the machine out of alignment. And Boland cannot recover for negligence because Universal’s only duties to it were those written in the contract. For the reasons explained below, neither party recovers anything. I. Introduction By the stipulation of the parties, the Court conducted a three-day bench trial on February 26-28, 2024.1

1 This case is assigned to me for all proceedings, by the consent of the parties, pursuant to 28 U.S.C. § 636(c). ECF Nos. 31, 33 & 34. Under Rule 52 of the Federal Rules of Civil Procedure, the Court must make specific findings of fact and state conclusions of law separately in any action tried without a jury. In doing so, the Court must appraise the testimony and demeanor of the witnesses, assess and evaluate witness credibility of, weigh the evidence, and choose among conflicting inferences and conclusions. In doing so, and to comply with this rule, the Court “‘need only make brief, definite,

pertinent findings and conclusions upon the contested matters,’ as there is no need for ‘over- elaboration of detail or particularization of facts.’” Wooten v. Lightburn, 579 F. Supp. 2d 769, 772 (W.D. Va. 2008) (quoting Fed. R. Civ. P. 52(a) advisory committee’s note to 1946 amendment). Rule 52(a) “does not require the court to make findings on all facts presented or to make detailed evidentiary findings; if the findings are sufficient to support the ultimate conclusion of the court they are sufficient.” Darter v. Greenville Cmty. Hotel Corp., 301 F.2d 70, 75 (4th Cir. 1962) (quoting Carr v. Yokohama Specie Bank, Ltd., 200 F.2d 251, 255 (9th Cir. 1952)). Based on an evaluation of all of the evidence, including the parties’ exhibits, the testimony of the witnesses, the inferences to be drawn from the evidence, and the parties’ arguments, I make

the following findings of fact and conclusions of law: II. Findings of Fact 1. Some buildings on the campus of the University of Maryland, College Park are cooled by the University of Maryland Chiller System (“chiller”). In 2019, Engie-College Park Energy, LLC (“Engie”), the company that monitors and maintains certain cooling and energy systems for the University of Maryland, decided to overhaul the chiller. Engie is not a party to this case. 2. The chiller is composed of a Murray Model KD7 multi-stage steam-driven turbine and a York compressor. The two components are connected by a coupling, which allows the energy generated by the rotation of the turbine to power the compressor. When the compressor is powered, it compresses refrigerant from a lower pressure to a higher pressure. This allows chilled water to be supplied to fan coil units and air handlers, cooling the air in connected buildings. If the chiller fails, buildings relying on it for climate control will lose cooling capacity. In hot weather, buildings without air conditioning can be uncomfortable.

3. Boland is a sophisticated commercial HVAC contractor with expertise in large air conditioning equipment. Its customers include municipalities, school systems, government entities, hospitals, hotels, and other buildings with chillers or large air conditioning equipment. It has been in business since 1960. It hires steamfitters from the local steamfitters union, which requires that steamfitters undergo a five-year apprenticeship program. 4. Boland entered into a contract with Engie for the overhaul of the chiller at the University of Maryland. Under its contract, Boland agreed to overhaul the chiller’s turbine and compressor, and Engie agree to pay Boland for the work. Boland handled the work on the compressor itself and subcontracted the overhaul of the turbine to Universal.

5. Under its contract with Boland, Universal agreed to a scope of work that included: • performing an “as-found coupling alignment check” of the chiller’s turbine; • disassembling the turbine and removing its upper half for refurbishment; • reassembling the turbine after refurbishment; • reinstalling the refurbished turbine; • checking the alignment of the turbine and compressor after reinstallation; • aligning the turbine to the compressor after reinstallation; and • standing by to support Boland and Engie when the turbine was first started after

reinstallation. 6. Boland agreed to pay Universal for its work. The cost for Universal’s work was between $171,733 and $184,468.70. 7. At the end of each day of work, Universal summarized the work it performed in a daily field report. The daily field report is a simple, one-page report that would be displayed for and signed by a Boland representative on an iPad. In some instances, daily field reports identify

only the persons who performed work and do not describe the work performed. 8. At all relevant times, Brad Elkins was Universal’s foreman on the Boland job. He was responsible for preparing the daily field reports. Elkins has over 20 years of experience as a millwright. For Boland, steamfitter Casey Emory was the prime mechanic on the job site. Emory was the person generally tasked with making decisions for Boland. 9. While the chiller was being serviced, it was “locked out” and “tagged out.” In practical terms, this meant that Boland, Universal, and Engie each placed a lock on the chiller so that it could not be operated. The chiller could be started only if all three locks were removed. 10. On February 10, 2020, Universal personnel arrived onsite at the University of

Maryland to disassemble the turbine. Before disassembly, Universal performed an “as-found coupling alignment check” to determine the respective positions of the turbine and compressor. Universal found that the turbine and compressor were out of alignment on both the vertical and horizontal planes. It informed Boland that the turbine and compressor were misaligned. This misalignment was likely due to the internal components wearing down over time. 11. Universal disassembled the turbine, removed the upper half of the case, and left the lower half of the case undisturbed. It shipped the turbine to BWC, a machine shop in Pennsylvania, so that BWC could perform rotor repairs on the turbine. Universal rebuilt the turbine’s governor valve, which regulates the steam entering into the turbine. 12. BWC took longer than expected to complete its work on the turbine. On June 22, 2020, Universal delivered the refurbished turbine to the University of Maryland and reinstalled it over several days. 13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Munday v. Waste Management of North America, Inc.
997 F. Supp. 681 (D. Maryland, 1998)
Mesmer v. Maryland Automobile Insurance Fund
725 A.2d 1053 (Court of Appeals of Maryland, 1999)
Campfield v. Crowther
249 A.2d 168 (Court of Appeals of Maryland, 1969)
Valentine v. on Target, Inc.
727 A.2d 947 (Court of Appeals of Maryland, 1999)
Stone v. Chicago Title Insurance
624 A.2d 496 (Court of Appeals of Maryland, 1993)
Taylor v. NationsBank, N.A.
776 A.2d 645 (Court of Appeals of Maryland, 2001)
Minh-Vu Hoang v. Hewitt Avenue Associates, LLC
936 A.2d 915 (Court of Special Appeals of Maryland, 2007)
Hauch v. Connor
453 A.2d 1207 (Court of Appeals of Maryland, 1983)
Miller v. Michalek
281 A.2d 117 (Court of Special Appeals of Maryland, 1971)
Philip Morris Inc. v. Angeletti
752 A.2d 200 (Court of Appeals of Maryland, 2000)
Impala Platinum Ltd. v. Impala Sales (U.S.A.), Inc.
389 A.2d 887 (Court of Appeals of Maryland, 1978)
Beard v. S/E JOINT VENTURE
581 A.2d 1275 (Court of Appeals of Maryland, 1990)
Burdette v. ROCKVILLE CRANE RENTAL, CORP.
745 A.2d 457 (Court of Special Appeals of Maryland, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Universal Plant Services of Nashville, Inc. v. Boland Trane Services, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/universal-plant-services-of-nashville-inc-v-boland-trane-services-inc-mdd-2024.