Universal Eng. & B., Inc. v. Lafayette Steel Erec. Corp.

235 So. 2d 612
CourtLouisiana Court of Appeal
DecidedMay 14, 1970
Docket3073
StatusPublished
Cited by15 cases

This text of 235 So. 2d 612 (Universal Eng. & B., Inc. v. Lafayette Steel Erec. Corp.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Universal Eng. & B., Inc. v. Lafayette Steel Erec. Corp., 235 So. 2d 612 (La. Ct. App. 1970).

Opinion

235 So.2d 612 (1970)

UNIVERSAL ENGINEERS & BUILDERS, INC., Plaintiff-Appellee,
v.
LAFAYETTE STEEL ERECTOR CORPORATION et al., Defendants-Appellants.

No. 3073.

Court of Appeal of Louisiana, Third Circuit.

May 14, 1970.
Rehearings Denied June 16, 1970.

*613 Garrett, Ryland & Downs, by B. Dexter Ryland, Alexandria, and Edwards, Edwards & Broadhurst, by Nolan J. Edwards, Crowley, for defendants-appellants.

Davidson, Meaux, Onebane & Donohoe, by Edward C. Abell, Jr., Lafayette, for intervenor-appellant.

Smith & Stansbury, by J. Nathan Stansbury, Lafayette, for plaintiff-appellee.

Before TATE, SAVOY and MILLER, JJ.

SAVOY, Judge.

This is a suit by plaintiff for damages to a large piece of oilfield equipment caused by an accident on February 26, 1968, which occurred at the premises of Hub City Iron Works in Lafayette, Louisiana. Plaintiff was the designer and builder of the specialty oilfield equipment described as a "pipe break-out and lay-down machine", which was about 40 feet in length and weighed approximately 16,500 pounds. Defendant was called upon to furnish a crane and an operator to move the specialty machine from a truck bed to a platform. In the process, the crane and the machine fell, with the boom of the crane falling upon and destroying the machine. The property damage insurer of defendant, Aetna Insurance Company, joined with defendant in a petition of intervention for the damages to defendant's crane in the amount of $5,979.36.

After trial on the merits, judgment was rendered for plaintiff for the value of the specialty machine, less salvage, in the amount of $47,911.13. The petition in intervention was dismissed. From this judgment, defendant and intervenor have appealed to this Court. Plaintiff did not appeal or file an answer to the appeal.

Plaintiff was the designer of the oilfield equipment described as a "pipe break-out and lay-down machine". This machine, an experimental unit in the final stages of development, was designed for use in the oil industry for breaking out and laying down drill pipe or other pipe in offshore drilling operations. The machine was constructed at Hub City Iron Works under the direction of plaintiff's employees. On one previous occasion, plaintiff had obtained a crane and operator from defendant to set the machine in an upright position so that certain tests could be run. In order to test the machine again, after certain changes and additions, it was to be removed from a truck bed and placed in an upright position on a platform. The machine was about 40 feet long, and measured about four feet by six feet at its base and about four feet by four feet at its top. It weighed approximately 16,500 pounds.

On the morning of February 26, 1968, plaintiff's project engineer, William J. "Bill" Ryan, contacted the employees of defendant for the purpose of obtaining a crane operator to perform this special job. He testified that plaintiff often rented trucks and heavy equipment to move machinery, and that there was usually a minimum charge, a minimum number of hours at a specified rate, on a special job as this one. The agreement was for a four hour minimum at $18.50 per hour.

Defendant owns and operates large moving equipment, including cranes and other type of erection equipment, and is in the business of moving equipment with cranes and erecting steel in various types of construction. After a phone conversation between the president of the defendant corporation and Bill Ryan, the defendant dispatched to the job site a truck-mounted 15 ton (or 30,000 pound capacity) hydraulic crane, with its employee, Robert M. "Bob" Miller, as the operator. The crane had a 30,000 pound capacity with a short boom, but with an extended 50 foot boom its capacity was reduced to about 21,000 pounds.

*614 Prior to beginning the work, Miller had Ryan sign a rental agreement stipulating a four hour minimum at $18.50 per hour. The agreement or work order provided that "Rentee shall take reasonable care of equipment. Rentee shall be liable for any and all damage to any persons or property while said equipment is in its possession". Ryan testified he was asked to sign the work order in advance to agree to the four hour minimum charge. Ryan also testified he told Miller to make a lift as he had done before, indicating the platform and where the machine was to be placed, but he did not give any instructions as to how the job was to be done. He stated he told Miller that the machine had an additional weight of 2,000 pounds.

Miller testified he was told some weight was added, but thought he was told the total weight was about 15,000 pounds. He backed his crane-truck to about eight feet from the platform which was about seven feet high, placed outrigger pads under the rear outriggers on his crane-truck, extended the boom to fifty feet, and otherwise prepared for the lift. Plaintiff's machine was brought to the location on a flat bed trailer about 4½ feet high. Miller told the truck driver where to position the truck and trailer for the lift on the left side and parallel to the crane-truck about four to six feet away, with both vehicles facing in the same direction away from the platform. He then decided on the method of hooking onto the lifting eye of the machine, deciding on using a wire cable and a shackle which was hooked through the eye. He testified it was his impression that the lifting eye was the balancing point. With the truck in a stopped position, he lifted the top of the machine, using the power of the crane to lift and swing the machine, and moved the machine along a rolling tail board on the truck, until he had its base touching the ground, with the machine almost standing up. His next move was to get the machine close to his crane before he swung it to the rear of the crane-truck to lift it onto the platform. To do this, he instructed the truck driver how he intended to use the truck to assist him so that the machine would move in closer to the crane without swinging too much. He lifted the machine and instructed the truck driver to move out slowly. As he lifted, he brought the machine near the crane, lifting it about eight inches to one foot off the ground. As he got the machine near the crane, he noticed the tower or machine was not hanging level, but at a 15 or 20 degree angle. The truck had moved away. At this point he wanted to set the machine down to straighten it out, and as he considered how to do this, with the truck driver standing on the crane with him, a few minutes past. Then the ground gave way under the outrigger to the left rear of the crane-truck, where the weight was suspended, the boom swung to the right as the machine fell away; he tried to stop the swing by putting pressure on the swinging level in the opposite direction, but there was too much weight and angle to equalize the swing. The machine fell to the ground, and the boom of the crane fell on top of it. Miller and the truck driver jumped clear as the crane-truck turned on its side with the falling of the boom.

It was stipulated at the trial that the construction cost of plaintiff's machine was $48,061.13, and that it was a total loss with a salvage value of $150.00. The record also shows that defendant's crane was damaged to the extent of $5,979.36, and that this loss was paid by the intervenor, Aetna Insurance Company, less a deductible of $450.00 absorbed by defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Alexander
406 So. 2d 1378 (Louisiana Court of Appeal, 1981)
LeJeune v. Allstate Ins. Co.
365 So. 2d 471 (Supreme Court of Louisiana, 1978)
LeJeune v. Allstate Ins. Co.
356 So. 2d 537 (Louisiana Court of Appeal, 1978)
Vincent v. Ryder Enterprises, Inc.
352 So. 2d 1061 (Louisiana Court of Appeal, 1977)
Highlands Insurance Co. v. LJ Denny and Son
328 So. 2d 779 (Louisiana Court of Appeal, 1976)
Berry Brothers General Contractors, Inc. v. Air Marine, Inc.
328 So. 2d 771 (Louisiana Court of Appeal, 1976)
Guilbeau v. Liberty Mut. Ins. Co.
324 So. 2d 571 (Louisiana Court of Appeal, 1976)
Nichols Const. Corp. v. Spell
315 So. 2d 801 (Louisiana Court of Appeal, 1975)
LeBlanc v. Roy Young, Inc.
308 So. 2d 443 (Louisiana Court of Appeal, 1975)
Cooley v. Slocum
313 So. 2d 606 (Louisiana Court of Appeal, 1975)
Pagitt Well Service, Inc. v. Sam Broussard, Inc.
293 So. 2d 631 (Louisiana Court of Appeal, 1974)
Kirkland v. Western Electric Company, Inc.
296 So. 2d 350 (Louisiana Court of Appeal, 1974)
Lambert v. James A. Teague Rental Equipment, Inc.
278 So. 2d 544 (Louisiana Court of Appeal, 1973)
Elston v. Shell Oil Company
376 F. Supp. 968 (E.D. Louisiana, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
235 So. 2d 612, Counsel Stack Legal Research, https://law.counselstack.com/opinion/universal-eng-b-inc-v-lafayette-steel-erec-corp-lactapp-1970.