Unity School District v. Vaughn, et al.

2016 DNH 062
CourtDistrict Court, D. New Hampshire
DecidedMarch 23, 2016
Docket15-cv-155-SM
StatusPublished

This text of 2016 DNH 062 (Unity School District v. Vaughn, et al.) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Unity School District v. Vaughn, et al., 2016 DNH 062 (D.N.H. 2016).

Opinion

UNITED STATES DISTRICT COURT

DISTRICT OF NEW HAMPSHIRE

Unity School District, Plaintiff

v. Case No. 15-cv-155-SM Opinion No. 2016 DNH 062 Vaughn Associates, Inc., and Scott Vaughn, Defendants

v.

School Administrative Unit #6, Excel Mechanical, Inc., Superior Walls of Hudson Valley, Inc., and Town of Unity, Third-Party Defendants

O R D E R

This case arises from two contracts between the Unity School

District and Vaughn Associates, Inc., pursuant to which Vaughn

Associates agreed to design and, subsequently, oversee

construction of a new elementary school in Unity, New Hampshire.

Those contracts were terminated in early 2014, and this

litigation ensued. Initially, the Unity School District filed a

four-count writ in state court against Vaughn Associates and its

principal, Scott Vaughn (collectively, “Vaughn”). Vaughn then

removed the action to this court, on grounds that the parties are

diverse. Subsequently, it filed a ten-count third-party

complaint against several entities, none of which was a party to

its contracts with the Unity School District. Two of those third-party defendants - the Town of Unity and

School Administrative Unit #6 - now move to dismiss all claims

advanced against them, asserting that none states a viable cause

of action. See generally Fed. R. Civ. P. 12(b)(6). Vaughn

objects. For the reasons discussed, those motions are granted.

Standard of Review

When ruling on a motion to dismiss under Rule 12(b)(6), the

court must “accept as true all well-pleaded facts set out in the

complaint and indulge all reasonable inferences in favor of the

pleader.” SEC v. Tambone, 597 F.3d 436, 441 (1st Cir. 2010).

Although the complaint need only contain “a short and plain

statement of the claim showing that the pleader is entitled to

relief,” Fed. R. Civ. P. 8(a)(2), it must allege each of the

essential elements of a viable cause of action and “contain

sufficient factual matter, accepted as true, to state a claim to

relief that is plausible on its face,” Ashcroft v. Iqbal, 556

U.S. 662, 678 (2009) (citation and internal punctuation omitted).

In other words, “a plaintiff’s obligation to provide the

‘grounds’ of his ‘entitlement to relief’ requires more than

labels and conclusions, and a formulaic recitation of the

elements of a cause of action will not do.” Bell Atl. Corp. v.

Twombly, 550 U.S. 544, 555 (2007). Instead, the facts alleged in

2 the complaint must, if credited as true, be sufficient to “nudge”

plaintiff’s claims “across the line from conceivable to

plausible.” Id. at 570. If, however, the “factual allegations

in the complaint are too meager, vague, or conclusory to remove

the possibility of relief from the realm of mere conjecture, the

complaint is open to dismissal.” Tambone, 597 F.3d at 442.

Background

Accepting the allegations of the third-party complaint as

true - as the court must at this juncture - the relevant facts

are as follows. In 2009, the New Hampshire Department of

Education voted to close the Town of Unity’s elementary school

because it failed to comply with state building, fire safety, and

educational requirements. In 2010, Scott Vaughn volunteered to

donate his design services to assist the Unity School District in

preparing a proposal to construct a new elementary school and to

secure voter approval of a bond to fund the project.

In August of 2010, that bond was approved by the voters of

the school district. Subsequently, the Unity School District

entered into an Architectural Services Contract with Vaughn

Associates, under which Vaughn Associates agreed to design the

new elementary school. Shortly thereafter, the Unity School

District entered into a second contract with Vaughn Associates,

3 pursuant to which Vaughn Associates would act as the project’s

construction manager. Once the project got underway, however, it

was plagued by difficulties and delays. Eventually, in January

of 2014, Vaughn Associates resigned as construction manager and,

approximately two months later, it sent notice to the Unity

School District terminating the Architectural Services Agreement.

In terminating that contract, Vaughn Associates cited

“impracticability, frustration of purpose, lack of good faith and

fair dealing, and non-payment.” Third-Party Complaint (document

no. 8) at para. 125.

In March of 2015, the Unity School District filed suit in

state court against Vaughn Associates, Inc. and Scott Vaughn,

advancing claims of negligence, breach of contract, negligent

misrepresentation, and violations of New Hampshire’s Consumer

Protection Act. Vaughn removed the action, invoking this court’s

diversity subject matter jurisdiction. See generally 28 U.S.C.

§ 1332. And, as noted above, Vaughn subsequently filed a ten-

count third-party complaint against School Administrative Unit #6

(“SAU #6”), Excel Mechanical, Inc., Superior Walls of the Hudson

Valley, and the Town of Unity, New Hampshire.

Pending before the court are motions filed by SAU #6 and the

Town of Unity, seeking dismissal of all claims asserted against

4 them. Counsel for the parties presented their arguments in legal

memoranda, as well as at a hearing before the court on December

1, 2015.

Discussion

Before addressing the specifics of the pending motions to

dismiss, it probably bears noting that, with the exception of its

claim against the Town of Unity for intentional interference with

contractual relations, Vaughn does not seek to recover damages

for actual losses or injuries it sustained. Instead, Vaughn

seeks contribution or, better still, complete indemnification

from both the Town and SAU #6 for harms sustained by the Unity

School District and any damages Vaughn may, in the future, owe to

the Unity School District. See, e.g., Third-Party Complaint at

paras. 138, 144, 205, and 212. Vaughn has clearly, repeatedly,

and unambiguously proclaimed that it is (with the one exception

noted above) pursuing claims for contribution and implied

indemnification. Accordingly, its claims must be treated as such

(despite allegations in the third-party complaint that might

suggest Vaughn is pursuing the third-party defendants for harm it

suffered as a consequence of their allegedly tortious conduct).

5 I. Claims Against SAU #6.

Vaughn advances two claims against SAU #6: one for statutory

contribution, pursuant to N.H. Rev. Stat. Ann. (“RSA”) 507:7-f

(count one); and one for common law indemnity (count two).

Third-Party Complaint at paras. 138 and 144. See also Vaughn’s

Memorandum in Opposition (document no. 30-1) at 2-3 (“[Vaughn’s]

Third-Party Complaint against SAU seeks contribution and/or

indemnity for the actions of SAU which caused or contributed to

the Project issues and delays.”). The New Hampshire Supreme

Court has explained the distinction between contribution and

indemnification as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Connors v. Suburban Propane Co.
916 F. Supp. 73 (D. New Hampshire, 1996)
Jaswell Drill Corp. v. General Motors Corp.
529 A.2d 875 (Supreme Court of New Hampshire, 1987)
Roberts v. General Motors Corp.
643 A.2d 956 (Supreme Court of New Hampshire, 1994)
Dunn v. CLD Paving, Inc.
663 A.2d 104 (Supreme Court of New Hampshire, 1995)
Hughes v. New Hampshire Division of Aeronautics
871 A.2d 18 (Supreme Court of New Hampshire, 2005)
Gray v. Leisure Life Industries
77 A.3d 1117 (Supreme Court of New Hampshire, 2013)
Securities & Exchange Commission v. Tambone
597 F.3d 436 (First Circuit, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
2016 DNH 062, Counsel Stack Legal Research, https://law.counselstack.com/opinion/unity-school-district-v-vaughn-et-al-nhd-2016.