Unity School District v. Vaughn Associates, et al.

2017 DNH 013
District Court, D. New Hampshire·Decided January 20, 2017·No. 15-cv-155-SM·Published

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF NEW HAMPSHIRE

Unity School District, Plaintiff

v. Case No. 15-cv-155-SM Opinion No. 2017 DNH 013

Vaughn Associates, Inc., and Scott Vaughn, Defendants

v.

Excel Mechanical, Inc., and Superior Walls of Hudson Valley, Inc., Third-Party Defendants

O R D E R

In 2010, the Unity School District entered into two contracts with defendants, Vaughn Associates and Scott Vaughn (collectively, “Vaughn”), to design and oversee construction of a new elementary school in Unity, New Hampshire. What was originally supposed to be a $4.7 million project ballooned into one exceeding $9 million. The contracts between the parties were terminated in early 2014, and the School District eventually brought this action. The District advances four claims: professional negligence (i.e., architectural malpractice); breach of contract; negligent misrepresentation;

and unfair and deceptive trade practices in violation of New Hampshire’s Consumer Protection Act.

Pending before the court is Vaughn’s motion for summary judgment on all claims. The School District objects. For the reasons discussed, Vaughn’s motion is granted in part, and denied in part.

Standard of Review

When ruling on a motion for summary judgment, the court must “constru[e] the record in the light most favorable to the non-moving party and resolv[e] all reasonable inferences in that party=s favor.” Pierce v. Cotuit Fire Dist., 741 F.3d 295, 301 (1st Cir. 2014). Summary judgment is appropriate when the record reveals Ano genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.@ Fed. R. Civ. P. 56(a). In this context, “[a]n issue is ‘genuine’ if it can be resolved in favor of either party, and a fact is ‘material’ if it has the potential of affecting the outcome of the case.” Xiaoyan Tang v. Citizens Bank, N.A., 821 F.3d 206, 215 (1st Cir. 2016) (citations and internal punctuation omitted). Nevertheless, if the non-moving party=s “evidence is merely colorable, or is not significantly probative,” no genuine dispute as to a material fact has been proved, and “summary

judgment may be granted.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249-50 (1986) (citations omitted). In other words, “[a]s to issues on which the party opposing summary judgment would bear the burden of proof at trial, that party may not simply rely on the absence of evidence but, rather, must point to definite and competent evidence showing the existence of a genuine issue of material fact.” Perez v. Lorraine Enterprises, Inc., 769 F.3d 23, 29–30 (1st Cir. 2014).

The key, then, to defeating a properly supported motion for summary judgment is the non-movant=s ability to support his or her claims concerning disputed material facts with evidence that conflicts with that proffered by the moving party. See generally Fed. R. Civ. P. 56(c). It naturally follows that while a reviewing court must take into account all properly documented facts, it may ignore a party’s bald assertions, speculation, and unsupported conclusions. See Serapion v. Martinez, 119 F.3d 982, 987 (1st Cir. 1997). See also Scott v. Harris, 550 U.S. 372, 380 (2007) (“When opposing parties tell two different stories, one of which is blatantly contradicted by the record, so that no reasonable jury could believe it, a court should not adopt that version of the facts for purposes of ruling on a motion for summary judgment.”).

Background

In 2009-10, the School District faced a difficult decision, with serious financial consequences. It had to either renovate an existing elementary school that no longer complied with state building codes, fire safety codes, and educational requirements, or construct an entirely new school. In August of 2010, Scott Vaughn, a local architect, presented a proposal to a special meeting of the School District. He assured the District that he could both design and construct a 28,500 square foot elementary school in ten months, for less than $4.7 million. See Minutes of August 23 School District Meeting (document no. 48-9); Vaughn PowerPoint Presentation (August 23, 2010) (document no. 46-10). Relying upon those representations, district voters approved a special warrant article authorizing the District to raise and appropriate the necessary tax revenue to cover the $4.7 million cost. Three weeks later, the District retained the defendants, Scott Vaughn and Vaughn Associates, to act as both project architect and construction manager.

The “Architectural Services Contract” between the parties provided that, “[a]s approved on 23 August 2010, the maximum budget for the total project cost is 4.7 million.” Architectural Services Contract (document no. 48-10) at section 1.1.7. Under the contract’s terms, construction was to begin in

April of 2011, and be completed by May of 2012. Id. at section 1.2. But, construction did not begin until approximately eight months later than anticipated. The project encountered numerous delays from the start, including two stop-work orders issued by the State Fire Marshal (due to defendants’ failure to timely provide copies of constructions plans). By June of 2011, the final building design had been amended to include an additional 6,500 square feet (for a total of approximately 35,000 square feet), along with other substantive modifications to the original design. Nevertheless, Vaughn continued to tell the District that, “[b]ased upon meetings with vendors and contractors it appears that the construction cost target for the total Project of $4,700,000 is achievable.” Unity Elementary School - Progress Report from Vaughn Associates (Aug. 15, 2011) (document no. 48-16) at 3.

Eventually, due to the numerous delays in completing the project, the District had to send its elementary students to Claremont for the 2013-2014 school year. And, because the building was still not enclosed by January of 2013, it sustained damage from exposure to the elements. Similar problems were encountered the following winter when, in December of 2013, the building was not properly heated. Damage was sustained to the foundation, pipes, and drains. Apparently, the District had to

enlist volunteers from the town to properly secure the building against further damage. See, e.g., Exhibit Y to Plaintiff’s Memorandum, Minutes of Unity School Board of Education (January 14, 2014) (document no. 48-28), at 2.

In January of 2014, after construction had slowed significantly and costs had risen substantially, Vaughn Associates resigned as construction manager and terminated its architectural services contract with the District. The School District then hired Trumball-Nelson to act as the new construction project manager and, soon thereafter, the District retained Banwell Architects to provide architectural and design services necessary to complete the project. The project was not finished until two years after the original contract completion date, and the total project cost nearly doubled, to $9.18 million. This litigation ensued.

Discussion

Free access — add to your briefcase to read the full text and ask questions with AI

Unity School District v. Vaughn Associates, et al., 2017 DNH 013 (D.N.H. 2017).

2017 DNH 013 (Unity School District v. Vaughn Associates, et al.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Schaefer v. IndyMac Mortgage Services
731 F.3d 98 (First Circuit, 2013)
Kellogg v. Pizza Oven, Inc.
402 P.2d 633 (Supreme Court of Colorado, 1965)
Pierce v. Cotuit Fire District
741 F.3d 295 (First Circuit, 2014)
Solis v. Lorraine Enterprises, Inc.
769 F.3d 23 (First Circuit, 2014)
James Yager v. K. William Clauson & a.
139 A.3d 1127 (Supreme Court of New Hampshire, 2016)
Xiaoyan Tang v. Citizens Bank, N.A.
821 F.3d 206 (First Circuit, 2016)
Sherman v. John Brown Insurance Agency
38 F. Supp. 3d 658 (W.D. Pennsylvania, 2014)
Barrows v. Boles
687 A.2d 979 (Supreme Court of New Hampshire, 1996)
Bruzga v. PMR Architects, P.C.
693 A.2d 401 (Supreme Court of New Hampshire, 1997)
Wong v. Ekberg
807 A.2d 1266 (Supreme Court of New Hampshire, 2002)