Unity School District v. Vaughn Associates, et al.

2017 DNH 013
CourtDistrict Court, D. New Hampshire
DecidedJanuary 20, 2017
Docket15-cv-155-SM
StatusPublished

This text of 2017 DNH 013 (Unity School District v. Vaughn Associates, et al.) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Unity School District v. Vaughn Associates, et al., 2017 DNH 013 (D.N.H. 2017).

Opinion

UNITED STATES DISTRICT COURT

DISTRICT OF NEW HAMPSHIRE

Unity School District, Plaintiff

v. Case No. 15-cv-155-SM Opinion No. 2017 DNH 013 Vaughn Associates, Inc., and Scott Vaughn, Defendants

v.

Excel Mechanical, Inc., and Superior Walls of Hudson Valley, Inc., Third-Party Defendants

O R D E R

In 2010, the Unity School District entered into two

contracts with defendants, Vaughn Associates and Scott Vaughn

(collectively, “Vaughn”), to design and oversee construction of

a new elementary school in Unity, New Hampshire. What was

originally supposed to be a $4.7 million project ballooned into

one exceeding $9 million. The contracts between the parties

were terminated in early 2014, and the School District

eventually brought this action. The District advances four

claims: professional negligence (i.e., architectural

malpractice); breach of contract; negligent misrepresentation; and unfair and deceptive trade practices in violation of New

Hampshire’s Consumer Protection Act.

Pending before the court is Vaughn’s motion for summary

judgment on all claims. The School District objects. For the

reasons discussed, Vaughn’s motion is granted in part, and

denied in part.

Standard of Review

When ruling on a motion for summary judgment, the court

must “constru[e] the record in the light most favorable to the

non-moving party and resolv[e] all reasonable inferences in that

party=s favor.” Pierce v. Cotuit Fire Dist., 741 F.3d 295, 301

(1st Cir. 2014). Summary judgment is appropriate when the

record reveals Ano genuine dispute as to any material fact and

the movant is entitled to judgment as a matter of law.@ Fed. R.

Civ. P. 56(a). In this context, “[a]n issue is ‘genuine’ if it

can be resolved in favor of either party, and a fact is

‘material’ if it has the potential of affecting the outcome of

the case.” Xiaoyan Tang v. Citizens Bank, N.A., 821 F.3d 206,

215 (1st Cir. 2016) (citations and internal punctuation

omitted). Nevertheless, if the non-moving party=s “evidence is

merely colorable, or is not significantly probative,” no genuine

dispute as to a material fact has been proved, and “summary

2 judgment may be granted.” Anderson v. Liberty Lobby, Inc., 477

U.S. 242, 249-50 (1986) (citations omitted). In other words,

“[a]s to issues on which the party opposing summary judgment

would bear the burden of proof at trial, that party may not

simply rely on the absence of evidence but, rather, must point

to definite and competent evidence showing the existence of a

genuine issue of material fact.” Perez v. Lorraine Enterprises,

Inc., 769 F.3d 23, 29–30 (1st Cir. 2014).

The key, then, to defeating a properly supported motion for

summary judgment is the non-movant=s ability to support his or

her claims concerning disputed material facts with evidence that

conflicts with that proffered by the moving party. See

generally Fed. R. Civ. P. 56(c). It naturally follows that

while a reviewing court must take into account all properly

documented facts, it may ignore a party’s bald assertions,

speculation, and unsupported conclusions. See Serapion v.

Martinez, 119 F.3d 982, 987 (1st Cir. 1997). See also Scott v.

Harris, 550 U.S. 372, 380 (2007) (“When opposing parties tell

two different stories, one of which is blatantly contradicted by

the record, so that no reasonable jury could believe it, a court

should not adopt that version of the facts for purposes of

ruling on a motion for summary judgment.”).

3 Background

In 2009-10, the School District faced a difficult decision,

with serious financial consequences. It had to either renovate

an existing elementary school that no longer complied with state

building codes, fire safety codes, and educational requirements,

or construct an entirely new school. In August of 2010, Scott

Vaughn, a local architect, presented a proposal to a special

meeting of the School District. He assured the District that he

could both design and construct a 28,500 square foot elementary

school in ten months, for less than $4.7 million. See Minutes

of August 23 School District Meeting (document no. 48-9); Vaughn

PowerPoint Presentation (August 23, 2010) (document no. 46-10).

Relying upon those representations, district voters approved a

special warrant article authorizing the District to raise and

appropriate the necessary tax revenue to cover the $4.7 million

cost. Three weeks later, the District retained the defendants,

Scott Vaughn and Vaughn Associates, to act as both project

architect and construction manager.

The “Architectural Services Contract” between the parties

provided that, “[a]s approved on 23 August 2010, the maximum

budget for the total project cost is 4.7 million.”

Architectural Services Contract (document no. 48-10) at section

1.1.7. Under the contract’s terms, construction was to begin in

4 April of 2011, and be completed by May of 2012. Id. at section

1.2. But, construction did not begin until approximately eight

months later than anticipated. The project encountered numerous

delays from the start, including two stop-work orders issued by

the State Fire Marshal (due to defendants’ failure to timely

provide copies of constructions plans). By June of 2011, the

final building design had been amended to include an additional

6,500 square feet (for a total of approximately 35,000 square

feet), along with other substantive modifications to the

original design. Nevertheless, Vaughn continued to tell the

District that, “[b]ased upon meetings with vendors and

contractors it appears that the construction cost target for the

total Project of $4,700,000 is achievable.” Unity Elementary

School - Progress Report from Vaughn Associates (Aug. 15, 2011)

(document no. 48-16) at 3.

Eventually, due to the numerous delays in completing the

project, the District had to send its elementary students to

Claremont for the 2013-2014 school year. And, because the

building was still not enclosed by January of 2013, it sustained

damage from exposure to the elements. Similar problems were

encountered the following winter when, in December of 2013, the

building was not properly heated. Damage was sustained to the

foundation, pipes, and drains. Apparently, the District had to

5 enlist volunteers from the town to properly secure the building

against further damage. See, e.g., Exhibit Y to Plaintiff’s

Memorandum, Minutes of Unity School Board of Education (January

14, 2014) (document no. 48-28), at 2.

In January of 2014, after construction had slowed

significantly and costs had risen substantially, Vaughn

Associates resigned as construction manager and terminated its

architectural services contract with the District. The School

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Schaefer v. IndyMac Mortgage Services
731 F.3d 98 (First Circuit, 2013)
Kellogg v. Pizza Oven, Inc.
402 P.2d 633 (Supreme Court of Colorado, 1965)
Pierce v. Cotuit Fire District
741 F.3d 295 (First Circuit, 2014)
Solis v. Lorraine Enterprises, Inc.
769 F.3d 23 (First Circuit, 2014)
James Yager v. K. William Clauson & a.
139 A.3d 1127 (Supreme Court of New Hampshire, 2016)
Xiaoyan Tang v. Citizens Bank, N.A.
821 F.3d 206 (First Circuit, 2016)
Sherman v. John Brown Insurance Agency
38 F. Supp. 3d 658 (W.D. Pennsylvania, 2014)
Barrows v. Boles
687 A.2d 979 (Supreme Court of New Hampshire, 1996)
Bruzga v. PMR Architects, P.C.
693 A.2d 401 (Supreme Court of New Hampshire, 1997)
Wong v. Ekberg
807 A.2d 1266 (Supreme Court of New Hampshire, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
2017 DNH 013, Counsel Stack Legal Research, https://law.counselstack.com/opinion/unity-school-district-v-vaughn-associates-et-al-nhd-2017.