United States v. Witco Corp.

76 F. Supp. 2d 519, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20192, 1999 U.S. Dist. LEXIS 18179, 1999 WL 1054911
CourtDistrict Court, D. Delaware
DecidedNovember 16, 1999
DocketCiv.A. 91-022RRM
StatusPublished
Cited by14 cases

This text of 76 F. Supp. 2d 519 (United States v. Witco Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Witco Corp., 76 F. Supp. 2d 519, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20192, 1999 U.S. Dist. LEXIS 18179, 1999 WL 1054911 (D. Del. 1999).

Opinion

OPINION

McKELVIE, District Judge.

This is an environmental remediation case. Plaintiff is the United States, on behalf of the U.S. Environmental Protection Agency (EPA). Defendant is Witco Corporation, a Delaware corporation with its principal place of business in New York, New York.

Witco has owned a site in Delaware known as the New Castle Spill Site since 1969. On September 8, 1983, the EPA placed the site on the National Priorities List pursuant to the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA). The EPA named Witco as a potentially responsible party for cleanup costs. As a settlement of the EPA’s claim against Witco, the parties entered into a court-approved consent decree on April 19, 1991 whereby Witco agreed to remediate the contaminated site and to reimburse the EPA for the agency’s oversight costs. The decree provides that the EPA shall demand reimbursement payments from Witco on an annual basis. The decree also authorizes the EPA to impose penalties on Witco for delays in payment.

On August 12, 1993, the United States Court of Appeals for the Third Circuit decided United States v. Rohm and Haas Co., 2 F.3d 1265 (3d Cir.1993), and ruled that the constitutionally based non-delegation doctrine prohibits the EPA from recovering oversight costs under § 107 of CERCLA when private parties perform the remediation.

*522 On July 31, 1996, the EPA for the first time submitted a demand for oversight costs from- Witco. Witco advised the EPA that Rohm & Haas precludes the.agency from collecting such costs. The EPA responded that the consent decree has contractually bound Witco to pay the costs, Rohm & Haas notwithstanding.

On February 12, 1999, Witco filed a motion to preclude the EPA from collecting the oversight costs. Witco alleges that the EPA’s tardiness in demanding the costs constitutes a breach of the EPA’s obligations under the consent decree, relieving Witco of its duty to reimburse the EPA. Witco also asks the court to modify the consent decree in light of the Rohm & Haas decision pursuant to its authority under Rule 60(b) of the Federal Rules of Civil Procedure. In particular, Witco asks the court to delete from the consent decree Witco’s obligation to reimburse the EPA for oversight costs.

On August 26, 1999, Witco filed a petition to bar the EPA from collecting penalties that have accrued during the pendency of this dispute. Witco asserts that imposition of such penalties is inconsistent with the provisions of the consent decree and with basic principles of due process.

The parties have completed briefing on the motions. This is the court’s decision on Witco’s motions.

I. FACTUAL BACKGROUND

The site at issue comprises approximately six acres and is located approximately 0.5 miles west of the Delaware River on New Castle Avenue approximately 0.5 miles north of New Castle, Delaware. Witco, known until 1985 as Witco Chemical Corporation, purchased the site in 1969. Hazardous substances were allegedly released at the site during Witco’s ownership of the facility, and investigations have detected contamination in the site’s groundwater. One such contaminant is tris (2-chloropropyl)-phosphate.

On September 8, 1983, the EPA listed the site on the National Priority List, also known as the Superfund List. The EPA identified Witco as a potentially responsible party for the release of contaminants at the site. Witco denied responsibility for any release of contaminants. Nonetheless, it agreed to perform a Remedial Investigation/Feasibility Study, which it published on August 1,1989, to determine the nature and extent of any contamination at the site and to evaluate potential remedial alternatives. The EPA, in concurrence with the State of Delaware, issued a final Record of Decision on September 28, 1989 embodying a plan for remedial action. The EPA’s complaint, which was filed on January 14, 1991, sought relief under § 106 and § 107 of CERCLA to compel Witco to remediate the site and to reimburse the EPA for its costs associated with the cleanup.

A. The Consent Decree

Witco agreed to settle the dispute with the EPA. On October 1, 1990, after four months of negotiations, the parties executed a consent decree. Among its provisions, the decree specifies the remediation work to be performed by Witco, and requires that Witco reimburse the EPA for its “Oversight Response Costs” incurred in overseeing the remediation. The costs include all direct and indirect costs “incurred by the United States in overseeing the Work, including, but not limited to, the costs of reviewing or developing plans, reports and other items pursuant to [the] Consent Decree and verifying the proper performance of the Work.” Decree at 7. The consent decree provides that the “EPA shall send Witco a demand for payment of such costs on an annual basis, with each demand to be made as soon as practicable after the anniversary date of the entry of this Consent Decree.” Decree at 38.

The decree stipulates dispute resolution procedures. In particular, Witco ■ is obliged to notify the EPA in writing of its objections within ten working days of any *523 difference of opinion or of receipt of the notice or decision giving rise to a dispute. The EPA, in turn, is to reply to Witco within ten days. In the event that Witco contests the EPA’s ruling, the decree provides for a negotiation period, after which Witco may petition the court for redress.

The decree limits the extent to which Witco may challenge the costs demanded by the EPA, allowing Witco to invoke the dispute resolution procedures to contest the costs “solely on the grounds that the costs are not within the definition of Further Response Costs or Oversight Response Costs, that the costs were incurred inconsistently with the NCP [National Contingency Plan] or that the mathematical calculations used to determine costs were performed improperly.” Decree at 39.

The decree also stipulates that the EPA may impose penalties upon Witco for any failure to comply with any requirement set forth in the decree, unless excused by force majeure or by written agreement with the EPA. Under the terms of the decree, penalties begin to accrue on the first day of Witco’s non-compliance, and continue through the final day of correction of non-compliance. Separate penalties accrue for each separate violation. The decree stipulates that the following penalties shall be imposed for failure to comply with provisions such as the Oversight Response Costs requirements: 1) $2000 per violation per day for the 1st through 14th day; 2) $4,000 per violation per day for the 15th through 30th day; and 3) $12,000 per violation per day for the 31st day and beyond. In the event that Witco challenges its obligations and does not prevail, the decree provides that Witco must pay all penalties and interest that accrued prior to, during and after the dispute resolution period.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

USA v. City of Atlanta
N.D. Georgia, 2024
Smith v. Angelo
D. Delaware, 2020
United States v. General Electric Co.
986 F. Supp. 2d 79 (D. Massachusetts, 2013)
USA v. Volvo Powertrain Corporation
854 F. Supp. 2d 60 (District of Columbia, 2012)
Tobin v. Gordon
614 F. Supp. 2d 514 (D. Delaware, 2009)
United States v. Alshabkhoun
277 F.3d 930 (Seventh Circuit, 2002)
United States v. Shakeab Alshabkhoun and A&a Farms
277 F.3d 930 (Seventh Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
76 F. Supp. 2d 519, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20192, 1999 U.S. Dist. LEXIS 18179, 1999 WL 1054911, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-witco-corp-ded-1999.