United States v. Williams Building Co.

137 F. Supp. 3d 6, 2015 U.S. Dist. LEXIS 132914, 2015 WL 5737138
CourtDistrict Court, D. Massachusetts
DecidedSeptember 29, 2015
DocketC.A. No. 13-CV-11920-MLW
StatusPublished
Cited by2 cases

This text of 137 F. Supp. 3d 6 (United States v. Williams Building Co.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Williams Building Co., 137 F. Supp. 3d 6, 2015 U.S. Dist. LEXIS 132914, 2015 WL 5737138 (D. Mass. 2015).

Opinion

MEMORANDUM AND ORDER

WOLF, District Judge.

On August 9, 2013, Prime Steel Erecting, Inc.. (“Prime”) filed a complaint, against the Williams Building Company, Inc. (‘Williams”) and International Fidelity Insurance Company (“IFIC”). Prime alleged that Williams and IFIC owed Prime payment for work on a federal construction project. On October 4, 2013, Williams filed its first motion to stay the proceedings pending mediation and arbitration. Williams also filed a third-party complaint against two subcontractors, Va-[8]*8nasse Hangen Brustlin, Inc. (“VHB”) and Unistress Corporation (“Unistress”) related to the same construction project. The parties have since filed many counterclaims and crossclaims. On April 10, 2014, Prime stipulated to dismissal of its original complaint. However, Williams’s third-party complaint, the counterclaims and cross-claims coneérning it, and Unistress’s fourth-party complaint against IFIC remain pending.

On April 25, 2014, Williams moved either to dismiss for lack of subject matter jurisdiction or to stay the litigation pending arbitration. For the reasons explained below, Williams’s motion to stay pending arbitration is being allowed. Williams’s motion to dismiss for lack of subject matter jurisdiction is being denied without preju-. dice subject to 'possible refiling after arbitration.

1. BACKGROUND

A. Factual Allegations

The undisputed facts include the following. This case arises out of a federal construction project in the Jamaica Plain neighborhood of Boston, Massachusetts. In 2011, the federal government hired Williams as the prime contractor for the construction of a parking garage. Williams contracted with two relevant subcontractors, VHB and Unistress.. Unistress subcontracted with Prime. IFIC provided surety bonds on behalf of Williams as required by federal law. The project ran behind schedule and over budget, leading to disputes among the parties.

In its third-party ‘complaint, Williams alleged the following. Williams hired VHB to “perform layout services for the project,” but VHB “failed to properly perform its surveying duties, resulting in the foundation for the new garage being located closer to the existing garage” than had been specified in project plans. Docket No. 17 at ¶¶ 16-17. In its answer, VHB denied these allegations. Docket No. 24 at ¶¶ 16-17.

Williams further alleged that its contract with Unistress required Unistress to “perform measurements at the Project site before fabricating the precast concrete panels,” but Unistress did not perform these measurements. Docket No. 17 at ¶¶ 31-32. After learning that the, foundation had been laid closer to the old garage than planned, Unistress, failed to “modify the panels in its shop prior to transporting them to the Project site.” Id. at ¶¶ 33-35. As a result, Unistress “engaged Prime to perform additional services for which it, Unistress, has failed and refused to pay Prime.” Id. ¶ 36. In its answer, Unistress “admits that it was informed at some point that the foundation for the new garage was located closer to the existing garage” than planned, but denied the other allegations. Docket No. 34 at ¶¶ 31-36

In its complaint, Prime alleged the following. Prime, pursuant to its contract, installed concrete precast components and steel at the job site. Docket No. 1 at Prime also performed “Extra & Corrective Work” including “making job site adjustments to material and site preparations provided by Williams and/or Unistress,” as well as-“many other fixes, repairs, and field adjustments.” Id. at ¶ 10. This additional work was not in the original contract, ’but Williams and Unistress requested that Prime perform this work. Id. at ¶¶ 11-12. Prime was not compensated either for its contracted-for work or for the additional work, and its complaint sought $171,328.82 plus attorneys’ fees and costs. Id. at ¶¶ 9, 20, 22-24. In its answer, Williams denied these allegations to the extent that they “deviate from the terms of the written contract.” Docket No. 12 at ¶¶ 8-12.

[9]*9B. Procedural History

Williams’s contracts with both Unistress and Vanasse provided for mandatory mediation followed, if necessary, by arbitration. See Williams-Unistress Contract, Docket No. 46-1 at §§ 6.1-6.2; Williams-VHB Contract, Docket No. 46-2 at §§ 9.4-9.5. On February 20, 2018, Unistress demanded mediation. The parties attended mediation, but the claims remained unresolved.

On September 9, 2018, Prime initiated litigation against Williams and IFIC, seeking $171,328.82 plus attorneys’ 'fees'- and costs. This ’ litigation was brought under the Miller Act, which applies to -federal public works projects. See 40 U.S.C. § 3131. The Miller Act provides that federal public works contractors must furnish a payment bond for the “protection of,all persons supplying labor and material in carrying out the work provided for in the contract.” Id. § 3131(b)(2). The Miller Act authorizes “[ejvery person that has furnished labor or material in carrying out work provided for in a contract for which a payment bond is furnished under section 3131” to “bring a civil action on the payment bond for the amount unpaid at the time the civil action is brought.” Id. § 3133(b)(1); see also id. § 3133(b)(2) (authorizing'suits against a contractor by person having direct contractual relationship with only a subcontractor). ■ ■ -

On September 20, 2013, Williams filed an answer, asserting, among other affirmative defenses, that Prime had failed to pursue mediation prior to initiating litigation. Docket No. 12 at 5.

On October 4, 2013, Williams moved to stay the litigation pending mediation. Docket No. 14. Prime opposed the motion to stay. Docket No. 20 at' 1. Prime argued that it was not bound by the arbitration clause in Williams’s contract with U-nis-tress, id. at 2-5, and that its Miller Act bond claims could proceed prior to an arbitrator’s finding of fault, id. at 5-7.

On October 4, 2013, Williams moved to stay the litigation pending mediation. Docket .No. 14. Prime opposed the .motion to stay. Docket No. .20 at 1. Prime argued that it was not bound by the arbitration clause in Williams’s .contract with Unis-tress, id. at 2-5, and that its Miller Act bond claims could proceed prior to an arbitrator’s finding of fault, id at 5-7.

On November 26, 2013, the four parties participated in mediation. Docket. No. 45 at 5. During mediation, they settled some, but not all, of the claims. Id. Among other terms, the settlement provided for the dismissal of pending claims and the. resolution of outstanding claims in arbitration. Prime, Unistress, and Williams,, but not VHB, signed a memorandum of understanding on November 26, 2013, agreeing that the parties would execute a formal agreement by March 20, 2014. Docket No. 45 at 5.

On December 6, 2013, VHB answered Williams’s third-party complaint. Docket No. 24. VHB’s answer asserted crossclaims against Unistress and counterclaims against Williams. Id. On February,. 24, 2014, Williams replied to VHB’s counterclaims. Williams asserted, among other defenses, that the action should be dismissed pursuant to the arbitration clause in the parties’ contract. Docket No. 31 at 6. Unis-tress filed an answer to VHB’s crossclaims on March 20, 2014. Docket No. 35.

On March 20, 2014, Unistress answered Williams’s, third-party complaint. Docket No. 34.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
137 F. Supp. 3d 6, 2015 U.S. Dist. LEXIS 132914, 2015 WL 5737138, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-williams-building-co-mad-2015.