United States v. Virginia Electric & Power Co.

412 F. Supp. 165, 1976 U.S. Dist. LEXIS 15414
CourtDistrict Court, E.D. North Carolina
DecidedApril 26, 1976
Docket76-0006-CIV-2
StatusPublished
Cited by5 cases

This text of 412 F. Supp. 165 (United States v. Virginia Electric & Power Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Virginia Electric & Power Co., 412 F. Supp. 165, 1976 U.S. Dist. LEXIS 15414 (E.D.N.C. 1976).

Opinion

MEMORANDUM OPINION and ORDER

LARKINS, Chief Judge:

INTRODUCTION

On July 1, 1965, the Virginia Electric and Power Company (hereinafter “Vepco”) entered into a contract with the United States Coast Guard to deliver electrical power to the Coast Guard Air Base at Elizabeth City, North Carolina. In return for service, the Coast Guard agreed to pay a price to be determined by the rate schedule currently on file with the North Carolina Utilities Commission. Following formation of the contract, both parties apparently performed their respective obligations for some nine years before any substantial controversy arose between them.

On November 1, 1973, Vepco filed, and the Utilities Commission approved, a rate schedule calling for the assessment of “late payment charges” upon customers failing to pay their electrical bills within a prescribed period of time. During the period of May, 1974, to December, 1975, Vepco assessed late payment charges in the amount of $785.55 against the Coast Guard Air Base in Elizabeth City. It is Vepco’s position that these late payment charges are part of the rate approved by the Utilities Commission and that the Coast Guard is obligated to pay them under paragraph 3 of the General Provisions of their contract wherein the Coast Guard agreed to pay the rates on file with the Commission.

The Coast Guard, on the other hand, has refused to pay the late payment charges. *167 It takes the position that these charges amount to “penalty or interest” the payment of which is expressly prohibited by paragraph 1 of the General Provisions of the contract. Thus, the basic controversy here appears to be over interpretation of the contract.

Another issue which has been raised by the Government is whether the controversy between the parties is covered by the administrative disputes procedure set forth in paragraph 9 of the General Provisions of the contract. In substance, the Disputes Clause provides that the parties agree to submit all disputes involving questions of fact for final administrative determination, subject to limited judicial review, but that administrative decisions on questions of law will not be considered final. The Government maintains that interpretation of a contract involves mixed questions of law and fact, and it would have this Court remand the dispute for administrative findings on all questions of fact. Vepco, on the other hand, argues that interpretation of a contract is a “pure question of law” and that it is not obligated to submit this dispute for administrative disposition.

In any event, the Government treated the controversy over late payment charges as if it were covered by the Disputes Clause. On January 5, 1976, the Coast Guard’s Contracting Officer formally advised Vepco that he had made an administrative decision that the Government was not obligated to pay the late payment charges because those charges constituted “penalty or interest” for which the Coast Guard was not liable under paragraph 1 of the General Provisions of the contract. On February 4, 1976, Vepco responded to the Contracting Officer’s decision stating that the controversy over the late payment charges was an entirely legal dispute not covered by the contract. Vepco also advised that it intended to refer the matter of the Coast Guard’s non-payment of these charges to the North Carolina Utilities Commission.

Therefore, Vepco, did refer the matter to the Commission by a complaint filed on February 13,1976. The company requested on order directing the Government to pay the late payment charges in issue and any future late payment charges. In its complaint before the Commission, Vepco also stated that other federal installations in North Carolina, particularly the Air Force and U. S. Information Service, had agreed to pay late payment charges, despite similar language in their service contracts.

On March 1, 1976, the Utilities Commission issued an order to the Commander of the Coast Guard Air Base at Elizabeth City directing the Coast Guard to pay the late payment charges then due. The order then went beyond Vepco’s request and provided that if such charges were not paid within 10 days after the order was served on the Commanding Officer of the Base, then Vepco was to discontinue electrical service. While the position of the Utilities Commission with regard to its authority for ordering discontinuance is unclear, it appears that the Commission is arguing that the Coast Guard consented to the imposition of such a remedy when it agreed under paragraph 3 that service would be subject to regulations by the Commission.

On March 12,1976, this action was initiated by a complaint filed by the Government against Vepco and the Utilities Commission. Alleging both breach of contract and anticipatory breach of contract, the Government seeks orders enjoining Vepco and the Commission from discontinuing electrical service to the Air Base and directing Vepco to submit all disputes concerning late payment charges for administrative determination under the Disputes Clause of the contract. Concurrently, the Government moved for a temporary restraining order and preliminary injunction restraining discontinuance of electrical service pendente lite. A temporary restraining order was issued pending a hearing on preliminary injunction.

On April 2, 1976, the defendant Vepco filed an answer containing a counterclaim against the Government for $785.55, representing the amount of late payment charges which the company asserts are due *168 and payable. The matter of plaintiff’s Motion for Preliminary Injunction was heard on April 13, 1976. As a result of that hearing, this Court continued the temporary restraining order and took plaintiff’s Motion under advisement. On April 14, 1976, the Utilities Commission voluntarily issued an order postponing the date for collection of the disputed electrical bill or discontinuance of electrical service until there has been a final adjudication on the merits of this case. In view of the Commission’s most recent order, this Court denied plaintiff’s Motion for Preliminary Injunction, without prejudice to reapply.

Whether the issues in this case are considered purely legal or mixed questions of law and fact, the merits are not yet before the Court. No party has moved for Summary Judgment, and the case is not yet ripe for trial. Nevertheless, certain of the matters raised by the parties in the preliminary stages of this litigation have prompted this Court to act ex mero motu.

I.

In support of its prayer for injunction, the Government has contended that discontinuance of electrical service to the Air Base would severely cripple essential governmental services and, thus, cause substantial and irreparable harm. In response, the defendants argue that discontinuance of service is a result which the Coast Guard can readily avoid' — that is, the Government can simply pay the late payment charges and then initiate an action to recover them. In turn, the Government has raised an issue which lies at the very heart of almost every aspect of this litigation: can the Coast Guard’s Certifying Officer pay the disputed late payment charges without violating federal appropriations statutes?

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mayor of Cambridge v. Secretary of the Commonwealth
436 Mass. 476 (Massachusetts Supreme Judicial Court, 2002)
Opinion No.
Texas Attorney General Reports, 1978
Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 1978
Crawford v. University of North Carolina
440 F. Supp. 1047 (M.D. North Carolina, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
412 F. Supp. 165, 1976 U.S. Dist. LEXIS 15414, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-virginia-electric-power-co-nced-1976.