United States v. Valentine

856 F. Supp. 621, 38 ERC (BNA) 2086, 1994 U.S. Dist. LEXIS 8695, 1994 WL 288463
CourtDistrict Court, D. Wyoming
DecidedJune 1, 1994
Docket1:93-cv-01005
StatusPublished
Cited by4 cases

This text of 856 F. Supp. 621 (United States v. Valentine) is published on Counsel Stack Legal Research, covering District Court, D. Wyoming primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Valentine, 856 F. Supp. 621, 38 ERC (BNA) 2086, 1994 U.S. Dist. LEXIS 8695, 1994 WL 288463 (D. Wyo. 1994).

Opinion

ORDER AND DECISION ON MOTION FOR SUMMARY JUDGMENT

ALAN B. JOHNSON, Chief Judge.

This matter came before the Court on the United States of America’s March 7, 1994 Motion for Summary Judgment. Hearing was held on April 15,1994. Having carefully considered the pleadings on file and the arguments of counsel, being fully advised in the premises, and in accordance with the findings from the bench made at the time of hearing, the Court FINDS and ORDERS as follows:

Background

The United States in its complaint seeks enforcement of the administrative orders issued by the United States Environmental Protection Agency (“EPA”) under Section 7003 of the Resource Conservation and Recovery Act (“RCRA”), 42 U.S.C. § 6973 (1992) and civil penalties for defendants’ failure to comply with those orders. In a separate, independent claim, the United States seeks injunctive relief, pursuant to Section 7003, to address the continuing threat to the environment posed by present conditions at the Powder River Crude Processors Site (“Site”) outside of Glenrock, Wyoming.

In his May 20, 1993 Order on Initial Pretrial Conference, the United States Magistrate Judge bifurcated this action into two phases. 1

The Site was operated as an oil reclaiming facility during the 1970s and 1980s. When EPA issued the administrative orders, there were several open, unhned pits containing oily wastes at the Site. The twenty-three tanks at the Site, some of which were decaying and leaking, also contained oily wastes in varying quantities. Soils around the tanks and pits were stained and saturated with oily wastes. Samples of the soils in these areas indicated the presence of various toxins including benzene, toluene, ethylbenzene, and xylene.

At the time EPA issued the administrative orders, the evidence in EPA’s possession also indicated that there was the potential for off-site migration of contaminants through a shallow drainage ditch that led from the Site down-gradient toward the North Platte River. In addition, there was limited information about the migration of these oily wastes in the soil, subsurface, and groundwater. Further, Site records indicated that there had been a fire and/or an explosion at the Site.

The Site served, and continues to serve, as a habitat for various wildlife species. The U.S. Fish and Wildlife Service advised EPA that the Site may pose a threat to the bald eagle and the peregrine falcon, both of which are protected by federal law. At the time EPA issued the administrative orders, access to the Site was unrestricted except for a low barbed wire fence with no gate.

Scientific papers demonstrated that the toxins in the pits posed significant health risks to birds and other wildlife. The U.S. Fish and Wildlife Service informed EPA that pits such as the ones at the Site serve as a lure to wildlife because the oily shiny surfaces of the pits look like water. Once attracted to the Site, animals may become coated with oil and may become trapped, leading to death by suffocation or exposure. Even animals that escape the pits can die or become sick from eating oil while cleaning their fur or eating vegetation coated with oily *625 wastes. Therefore, there was, and continues to be, a risk that animals may come into contact with the oily wastes and be exposed to the physical and toxicological hazards posed by these wastes. In fact, inspectors had found dead animals mired in oil at the Site.

Based upon this information, EPA issued orders pursuant to RCRA Section 7003 that required the recipients to: 2

(1) address the known risks posed by these conditions by submitting a work plan for the removal and disposal of all materials from the pits and tanks;
(2) immediately and temporarily secure the Site by installing certain interim measures; and
(3) determine whether there were additional impacts of these conditions by conducting further investigations.

In response to these orders, some of the defendants not subject to the summary judgment motion installed a chain link fence, placed polypropylene netting over the pits, and conducted limited sampling and testing of the wastes and equipment at the Site. None of these measures, however, is sufficient to exclude wildlife from the Site or to prevent further leaks from the tanks and pits. For instance, in each of the nets there are holes large enough to permit access by birds and small mammals. Further, the equipment at the Site continues to deteriorate and leak. After the filing of this action, the United States discovered twelve more dead animals mired in oily wastes leaking from a tank at the Site.

Standard of Review

Pursuant to Fed.R.Civ.P. 56(c), summary judgment is appropriate “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits on file, if any, show that there is no genuine issue as to any material fact, and that the moving party is entitled to summary judgment as a matter of law.” The moving party has the burden of showing the absence of a genuine issue concerning any material fact. Adickes v. S.H. Kress & Co., 398 U.S. 144, 90 S.Ct. 1598, 26 L.Ed.2d 142 (1970). The moving party’s burden may be met by identifying those portions of the record demonstrating the absence of a genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). In determining whether these burdens have been met, the court is required to examine all evidence in the light most favorable to the non-moving party. Barber v. General Electric Co., 648 F.2d 1272 (10th Cir.1981).

Once the moving party has met its initial burden, the burden shifts to the party resisting the motion. That party must “make a showing sufficient to establish the existence of an element essential to the party’s case, and on which that party will bear the burden of proof at trial.” Manders v. Oklahoma ex rel. Dept. of Mental Health, 875 F.2d 263, 265 (10th Cir.1989) citing Celotex, 477 U.S. at 325, 106 S.Ct. at 2554.

Discussion

Under any standard or review, the undisputed facts demonstrate that (1) conditions at the Site may have presented an imminent and substantial endangerment at the time the administrative orders were issued and (2) present site conditions may present an imminent and substantial endangerment. 3 Therefore, the United States is entitled to summary judgment as a matter of law on all Phase I issues. 4

*626

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. EI Du Pont De Nemours & Co., Inc.
341 F. Supp. 2d 215 (W.D. New York, 2004)
Wilson v. Amoco Corp.
989 F. Supp. 1159 (D. Wyoming, 1998)
United States v. Valentine
885 F. Supp. 1506 (D. Wyoming, 1995)
Clorox Co. v. Chromium Corp.
158 F.R.D. 120 (N.D. Illinois, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
856 F. Supp. 621, 38 ERC (BNA) 2086, 1994 U.S. Dist. LEXIS 8695, 1994 WL 288463, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-valentine-wyd-1994.