United States v. United States Steel Corp.

16 F. Supp. 3d 944, 2014 WL 1577837, 2014 U.S. Dist. LEXIS 54671
CourtDistrict Court, N.D. Indiana
DecidedApril 18, 2014
DocketNo. 2:12-cv-00304
StatusPublished
Cited by2 cases

This text of 16 F. Supp. 3d 944 (United States v. United States Steel Corp.) is published on Counsel Stack Legal Research, covering District Court, N.D. Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. United States Steel Corp., 16 F. Supp. 3d 944, 2014 WL 1577837, 2014 U.S. Dist. LEXIS 54671 (N.D. Ind. 2014).

Opinion

OPINION AND ORDER

PHILIP P. SIMON, Chief Judge.

The Environmental Protection Agency and three similar state agencies from Indiana, Michigan and Illinois filed a complaint against U.S. Steel Corporation alleging violations of the Clean Air Act relating to plants U.S. Steel operates in those three states. In Count One of its complaint, the EPA sought both damages and an injunction for alleged violations of the Clean Air Act relating to construction work done at U.S. Steel’s Gary, Indiana plant in 1990. U.S. Steel moved to dismiss on the basis that the claims were initiated well past the five-year statute of limitations period that U.S. Steel says applies to the alleged violations. Shortly before I filed my opinion, the Seventh Circuit issued an opinion in United States v. Midwest Generation, LLC, 720 F.3d 644 (7th Cir.2013), dealing with some of the same issues I face in this case, and I applied that ruling as I interpreted it. In my original Opinion, I agreed with U.S. Steel that the statute of limitations barred any claim for damages relating to those long ago events. However, I agreed with the government that the statute of limitations didn’t bar injunctive claims. (Docket Entry 54.)

U.S. Steel now asks me to reconsider the latter ruling — the one relating to the request for an injunction — based on its interpretation of Midwest Generation. After closely reading Midwest Generation I am now persuaded that my earlier ruling was wrong, and that the request for an injunction based on a claimed permit violation from 24 years ago cannot stand under Midwest Generation. So for the following reasons I will GRANT the Motion to Reconsider and DISMISS the claim for in-junctive relief contained in Claim One.

BACKGROUND

I won’t rehash everything in my initial opinion on the motion to dismiss. I will include only the facts necessary to this opinion and the application of Midwest [946]*946Generation to the issue at hand — whether the government can obtain an injunction against U.S. Steel for commencing construction in 1990 on a major modification to its facility without first obtaining certain permits. The plaintiffs in this case are both federal and state environmental agencies, but for ease of reference I will refer to them collectively as the EPA.

In 1990, U.S. Steel performed a “reline” of its No. 4 furnace at its Gary Works facility in Gary, Indiana. A reline is the process whereby the furnace is completely shut down and the interior lining is updated. U.S. Steel didn’t get a construction permit for the reline — it argues a permit wasn’t necessary — and now more than twenty years later the EPA says it should have.

In order to understand the issues in this case, one must understand the permitting process under the regulatory scheme established by the Clean Air Act (the “CAA”). There are two types of permits: construction permits and operating permits. Midwest Generation, 720 F.3d at 645. Both types of permits are at issue in this case. But for present purposes, because U.S. Steel’s Motion to Dismiss is only attacking Count One (and a portion of Count Three) of the complaint, only the failure to obtain a construction permit is presently before the Court.1

The construction permitting program emerged from the 1977 amendments to the CAA which required all new sources of air pollution — factories, power plants, refineries, etc. — to undergo a “New Source Review” (“NSR”). Under the NSR process, all post-1977 sources are required to meet various emission limits for pollutants. One might ask how this applies to the century-old Gary Works plant. The answer is that it might not. This is because plants built prior to 1977 are grandfathered in, meaning they need not abide by the 1977 amendments. But if the owners of the plant make a “major modification” to it, then the 1977 amendments do kick in. Whether the 1990 reline of the No. 4 furnace was a “major modification” under the CAA is a bone of contention in this case: EPA says it was major, U.S. Steel disagrees. But that issue is not before me today. Instead, at this stage, I will accept as true the EPA’s allegation that the reline was a major modification.

NSR consists of two programs — prevention of significant deterioration in air quality (“PSD”) and non-attainment with air quality standards (“NA/NSR”). Both of those programs are at issue in this case. The EPA’s first claim in this case alleges construction permit violations under both 42 U.S.C. § 7475(a) (PSD violations) and 42 U.S.C. § 7503 (NA/NSR violations). See DE 1 at 21.

A bit of clarification is necessary at this point. In Midwest Generation, the Seventh Circuit only addressed § 7475, holding that the EPA couldn’t sue over precon-[947]*947struction PSD permitting failures a decade after construction was complete and thus a decade after the violation occurred. However, Midwest Generation didn’t address § 7503. The parties in this case don’t distinguish between PSD and NA/NSR in their briefing, or between § 7475 and § 7503. It’s not obvious that the two can be addressed together, so before I analyze the effect that Midwest Generation has on this case, that issue requires some discussion.

While § 7475 explicitly addresses only PSD preconstruction requirements and not operation of the facility, § 7503 addresses nonattainment plan permit requirements generally, addressing both construction and operation permits for areas with especially poor air quality that are designated as “nonattainment areas.” However, the allegations for each of § 7475 and § 7503 in the EPA’s Complaint against U.S. Steel in this case explicitly refer to U.S. Steel’s “commencing a major modification without undergoing” the respective PSD and NSR review and permitting processes. (Compl. at ¶¶ 86, 87.) That is, the Complaint alleges that U.S. Steel violated § 7475(a) “by commencing a major modification without undergoing PSD review for major modifications, obtaining a PSD permit, and installing and operating [Best Available Control Technology] for control of the relevant air pollutants.” (Compl. at ¶ 86.) It similarly alleges that U.S. Steel violated § 7503 “by commencing a major modification without undergoing NA NSR review for major modifications, obtaining an NA NSR permit, and installing and operating [Lowest Achievable Emission Rate] for control of such air pollutants.” (Compl. at ¶ 87.) In other words, the allegations under §§ 7475 and 7503 mirror one another, and both are based on preconstruction permitting violations (“commencing a major modification”), not operation violations. Therefore, the Seventh Circuit’s logic in Midwest Generation, which relies on the preconstruction nature of the allegations under § 7475, must also apply to the allegations under § 7503 as they are made in the EPA’s First Claim against U.S. Steel. I therefore view the differences between the two sections as immaterial to U.S. Steel’s motions to dismiss and to reconsider. So to simplify matters I’ll just refer to the whole construction permitting process as “NSR.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Ameren Missouri
9 F.4th 989 (Eighth Circuit, 2021)
USA v. Luminant Generation Co.,L.L.C., et a
905 F.3d 874 (Fifth Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
16 F. Supp. 3d 944, 2014 WL 1577837, 2014 U.S. Dist. LEXIS 54671, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-united-states-steel-corp-innd-2014.