United States v. Thurston Motor Lines, Inc.

718 F.2d 616, 1978 U.S. App. LEXIS 11862
Court of Appeals for the Fourth Circuit·Decided April 4, 1978·No. 76-2230·Published

Opinion

PER CURIAM:

Executive Order 11246 requires that nondiscrimination-in-employment and related clauses be included in all government contracts in excess of $10,000 and in all government bills of lading. 1 Those provisions of the Executive Order were incorporated by reference in the bills of lading of Thurston Motor Lines under which it performed extensive carriage for the Defense Department. This action was brought by the United States alleging that Thurston had broken its contractual commitments by (1) refusing access to its personnel records, (2) refusing to develop and produce employment records with a racial identification of the employees, (3) discriminating in its employment practices, and (4) failing to develop and implement a formal affirmative action program for the employment of new black employees and for the promotion or transfer of black employees. The district court granted summary judgment for the defendant as to all phases of the case except the claimed denial of access to personnel records. It did so on the ground that there had been no attempt to conciliate other phases of the controversy, a general prerequisite to the institution of legal proceedings. As to the special affirmative action and special reporting claims, the district court also held that the relevant provisions of the Executive Order were inapplicable to Thurston because it had no single contract of $50,000 or more.

We think summary judgment for Thurston was mistaken.

I.

CONCILIATION

The representatives of the United States Postal Service, a contract compliance agency assigned to monitor Thurston’s employment practices, repeatedly sought access to Thurston’s personnel records. Such access was always denied. Though Moore, the Postal Service monitor, never explicitly threatened a referral of the matter to the Department of Justice unless he was given access to the personnel records, such access was repeatedly sought over a period of years and consistently refused. The district judge recognized that this met the requirement of “reasonable efforts within a reasonable time limitation to secure compliance with contract provisions of this Order by methods of conference, conciliation, mediation and persuasion * * *.” Under § 209(b) of the Executive Order, such reasonable efforts are a prerequisite to the institution of legal action. It seems equally clear, however, that Moore also persistently sought records with racial identification, particularly such records relating to new hires, promotion, transfers and seniority data. Thurston’s response was that it kept no such records. Indeed, it thought that *618 recording the racial identification of its employees would be in violation of other laws. However, under 41 C.F.R. § 60-1.7(a)(3), a contractor having more than fifty employees and a contract of $50,000 or more may be required to keep such special records and to furnish them to a compliance agent upon request and in specified form. As to this, there was simply an impasse between the monitoring agent and Thurston’s officials, the one repeatedly seeking such records while the others were equally insistent that they were under no obligation to keep or to produce them. At one time at least, Thurston offered to produce a computer printout listing all of Thurston’s employees with considerable employment data, but this was not acceptable because of the absence of racial data, which Mr. Moore felt essential for his purposes.

It is less clear that there was adequate compliance with § 209(b)’s requirement of conference, conciliation, mediation and persuasion with respect to substantive discrimination by Thurston. Denied access to Thurston’s existing personnel records and without the assistance of racial information as to all of its employees developed and supplied by Thurston, Moore did make inspections of several of Thurston’s terminals, some of them more than once. This led to letters from Moore to Thurston officials. He urged them to do more than was being done to recruit black applicants. He thought that Thurston was not using sufficiently referral services for black job seekers. He complained of the general absence of blacks among the drivers and the seeming concentration of those who were employed in the more menial jobs. Thurston seems to have ignored some of these letters, but since Moore repeatedly raised these questions, indicating possible discriminatory practices, it cannot be said as a matter of law that he did not make reasonable efforts looking toward conciliation. This is not a casé in which the possibility of actual discrimination was never mentioned by the monitor. It was mentioned by him on a number of occasions, and he did urge Thurston officials to intensify their efforts to bring blacks onto its payrolls and at higher grade levels.

This is not to say at this point that this court is finding that there was compliance by the Postal Service with § 209(b) of the Executive Order with respect to the charge of discriminatory practices. After a trial, it may be that the facts will be found against the Postal Service, but at this stage there seems clearly to be a dispute between the parties about the facts as they relate to compliance with § 209(b).

As far as this record discloses, there was never any discussion between Moore and Thurston officials about Thurston’s development of formal, written, affirmative action programs for each of its terminals and its central office. That he thought applicable the special provisions for contractors having more than fifty employees and a contract of $50,000 or more may have been implicit in his request for a copy of Thurston’s formalized affirmative action plan and his persistent requests for special reports with racial data. If, however, there was no attempt at conciliation to resolve this essential legal question, the absence of such conciliatory efforts should not bar a resolution of that question in this proceeding. This is essentially a legal inquiry, and it is now clear that the parties are in complete disagreement about it. The United States contends that Thurston’s bills of lading may be aggregated for the purpose of meeting the $50,000 requirement, while Thurston insists that each bill of lading was a separate contract, the amounts of which are not subject to aggregation. This is the kind of dispute which is well beyond the possibility of conciliatory resolution. Since it is obvious that any attempt by Moore and Thurston officials to resolve such differences by agreement would have been fruitless, judicial resolution of the controversy in this proceeding should not be foreclosed.

II.

THE $50,000 CONTRACT QUESTION

Thurston is a trucking company having over 2,000 employees. It operates 32 terminals and does extensive haulage for the *619 United States. In each of the years in question its total government business exceeded $1,000,000; in two of those years, its government revenue exceeded $2,000,000.

A considerable portion of Thurston’s business with the government is done under “Perishable Subsistence Carrier Rate Tender and Service Agreements.” Under these “agreements”, Thurston transported a large volume of perishable commodities to and from military depots and other military installations.

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. Thurston Motor Lines, Inc., 718 F.2d 616, 1978 U.S. App. LEXIS 11862 (4th Cir. 1978).

718 F.2d 616 (United States v. Thurston Motor Lines, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related