United States v. Stewart & Stevenson

Court of Appeals for the Fifth Circuit·Decided August 16, 2005·No. 04-20209·Unpublished

Opinion

United States Court of Appeals Fifth Circuit

F I L E D

CORRECTED

August 8, 2005

UNITED STATES COURT OF APPEALS FIFTH CIRCUIT Charles R. Fulbruge III Clerk

No. 04-20209

United States of America, ex rel., WERNER STEBNER, Plaintiff-Appellant,

versus

STEWART & STEVENSON SERVICES, INC.; MCLAUGHLIN BODY CO., Defendants-Appellees.

Appeal from the United States District Court for the Southern District of Texas (4:96-CV-3363)

Before KING, Chief Judge, BARKSDALE, and STEWART, Circuit Judges. PER CURIAM:* For this action under the qui tam provisions of the False Claims Act, 31 U.S.C. § 3729 et seq., Relator Werner Stebner challenges: (1) the summary judgment awarded Stewart & Stevenson Services, Inc. (S&S), and McLaughlin Body Co. (MBC); and (2) the costs awarded S&S. Concerning the summary judgment, Stebner contends the defendants submitted false and fraudulent claims to the United States during the course of a military contract. The judgment is AFFIRMED; the appeal from the costs-award, DISMISSED.

*

Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4.

I.

In 1991, the Government contracted with S&S to build a Family of Medium Tactical Vehicles (FMTV); they were a variety of models of two-and-a-half ton to five-ton military trucks (cargo, dump, tractor, and wrecker) with enclosed cabs. S&S contracted with MBC to produce the cabs. From 1993 until 1998, S&S produced FMTVs under the relevant contracts. (The Government has since awarded S&S two more FMTV contracts.) One specification requires that FMTVs be free of corrosion during the first ten years of use.

To monitor the FMTVs’ production, the Government established a Defense Plant Representative Office (DPRO) adjacent to S&S’s Sealy, Texas, manufacturing plant. Approximately 30 Government personnel were assigned to that DPRO: contract specialists helped administer the contract and oversaw any modifications or revisions; property specialists maintained FMTVs delivered and stored in Sealy; and quality assurance specialists audited and monitored manufacturing processes and assembly of the vehicles and conducted 100% vehicle inspection and testing.

Contract payment was conducted as follows. S&S submitted monthly progress payments for up to 85% of its costs for producing FMTVs that month. Upon conditional acceptance of a vehicle, S&S invoiced the Government for 90% of its total contract price, from which the Government deducted the 85% attributable to the progress payment. Upon final acceptance, the Government paid S&S the

balance. Progress-payment invoices were submitted on Government Standard Form 1443, which contained a certification that the costs reflected on the form were actually incurred by S&S or would be incurred. The vehicle-acceptance documents included Government form DD250 (“Material Inspection and Receiving Report”), the Vehicle Inspection Record, and the Final Inspection Record. The on-site Government officials reviewed and completed these forms and inspected the FMTVs. Upon the Government’s being satisfied with a vehicle, its representative signed the DD250, indicating conditional or final acceptance. All documents were then returned to S&S, which converted the DD250 into an invoice and submitted it for payment. The DD250 contained no express certifications of contractual compliance. (Only Government officials’ signatures appeared on the DD250.)

The Government accepted the FMTVs in stages; acceptance of produced vehicles was conditional prior to the Government’s granting First Article Approval (FAA) for full-scale production. Vehicles presented to the Government for conditional acceptance were stored in a Government-controlled area at the Sealy plant until FAA was granted. It was not granted until the vehicle design passed a series of tests; the test results informed design modifications. During the life of the contract, the Government and S&S agreed to numerous amendments which specified needed vehicle modifications suggested by the various test results.

Conditionally-accepted vehicles not in accordance with the final design were retrofitted to conform, then re-submitted for approval.

After a final design was agreed upon in 1995, S&S began retrofitting the conditionally-accepted vehicles. During the retrofit, S&S found corrosion problems on the cabs and cargo beds of many of the vehicles. S&S informed the Government immediately. In response, on 19 January 1996, S&S and the Government negotiated modifications, which, inter alia, required S&S to: produce a Cab Corrosion Report disclosing the corrosion’s “root cause”; repair vehicles that had certain corrosion levels; and refrain from submitting for acceptance vehicles with severe corrosion. The modifications allowed S&S to submit certain vehicles for acceptance but allowed the Government to withhold up to $2,000 per conditionally-accepted vehicle.

At around the same time, the FMTV was being subjected to the contractually-mandated Accelerated Corrosion Test (ACT), which simulated the required ten-years of corrosion-free use. The tested vehicle failed the ACT. Because the vehicles’ cabs, manufactured by MBC, exhibited most of the corrosion, S&S and Government inspectors began investigating MBC’s production facility and processes. Stebner, as the S&S employee in charge of the Cab Corrosion Report, also inspected the FMTVs and MBC’s facility. He found internal and external cab corrosion on the vehicles; blamed inadequacies at MBC’s production facility and its use of faulty

products and sealing procedures; and concluded MBC’s corrosion- prevention coating product and processes did not conform to contractual requirements and produced “junk”.

S&S instructed Stebner not to include the totality of his assessment in the Cab Corrosion Report, but to say the systems were only bad “some of the time”. Stebner refused, and was removed from the project. In any event, the Government was aware of the conditions at MBC’s facilities; officials from both DPRO and other Government offices inspected the facilities and determined MBC’s processes were inadequate. The Government also knew of other possible sources of corrosion, such as faulty windshield seals. The Cab Corrosion Report was presented to the Government on 2 April 1996.

Approximately six months later, after two retrofitted vehicles failed testing for the negotiated corrosion-repair, the Government suspended conditional acceptance of any vehicles evidencing corrosion or which had undergone corrosion repair. After further negotiations, the Government and S&S agreed on two contract modifications. The Government would resume acceptance if S&S: (1) provided a ten-year corrosion warranty, capped at $10 million, on vehicles already manufactured or being manufactured (entered November 1996); and (2) modified the contract to provide fully galvanized cabs (entered March 1997). The Government agreed to increase the price for the galvanized-cab vehicles because it believed galvanization would extend the vehicles’ corrosion-free

life-span past the contracted-for ten years. The Government considered these two modifications the “final resolution of the corrosion problems”.

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. Stewart & Stevenson, (5th Cir. 2005).

United States v. Stewart & Stevenson (United States v. Stewart & Stevenson) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Riley v. St Luke's Epis Hosp
252 F.3d 749 (Fifth Circuit, 2001)
United States v. Southland Management
326 F.3d 669 (Fifth Circuit, 2003)
GDF Realty Investments, Ltd. v. Norton
326 F.3d 622 (Fifth Circuit, 2003)
United States v. Bornstein
423 U.S. 303 (Supreme Court, 1976)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Brenda Pope v. MCI Telecommunications Corporation
937 F.2d 258 (Fifth Circuit, 1991)
Riley v. St. Luke's Episcopal Hospital
196 F.3d 514 (Fifth Circuit, 1999)