United States v. South Coast Mechanical, Inc.

CourtDistrict Court, C.D. California
DecidedOctober 7, 2020
Docket2:18-cv-09733
StatusUnknown

This text of United States v. South Coast Mechanical, Inc. (United States v. South Coast Mechanical, Inc.) is published on Counsel Stack Legal Research, covering District Court, C.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. South Coast Mechanical, Inc., (C.D. Cal. 2020).

Opinion

O 1

2 3 4 5 6 7

8 United States District Court 9 Central District of California

11 UNITED STATES OF AMERICA, for the Case № 2:18-cv-09733-ODW (RAOx) use and benefit of CLEAVER-BROOKS, 12 INC., ORDER DENYING MOTION FOR

13 Plaintiff, SUMMARY JUDGMENT [57]

14 v.

15 SOUTH COAST MECHANICAL, INC., et al., 16

17 Defendants.

18 AND RELATED CROSS-ACTIONS. 19 20 I. INTRODUCTION 21 Before the Court is Defendant, Use Cross-Claimant, and Cross-Defendant 22 South Coast Mechanical, Inc.’s (“SCM”) Motion for Summary Judgment and 23 Alternatively Partial Summary Judgment (“Motion”). SCM seeks summary judgment 24 in its favor on (a) SCM’s cross-claims against Defendants, Use Cross-Claimants, and 25 Cross-Defendants BVB Construction, Inc. (“BVB”) and Hanover Insurance Company 26 (“Hanover”), and (b) BVB and Hanover’s cross-claims against SCM. (SCM’s Mem. 27 of P. & A. in Supp. of Mot. for Summ. J. (“Mot.”) 1, 18, ECF No. 57-1.) In the 28 alternative, SCM seeks (a) partial summary judgment in its favor in the form of an 1 adjudication establishing BVB and Hanover’s duty to pay, and (b) dismissal of BVB 2 and Hanover’s cross-claims against SCM. (Id.) For the following reasons, the Court 3 DENIES the Motion.1 4 II. BACKGROUND2 5 On or about June 14, 2016, the United States Department of Veteran Affairs 6 (“VA”) and BVB entered into a written contract (“Prime Contract”) for improvements 7 to replace boilers in one of the VA’s buildings at the Greater Los Angeles Healthcare 8 System (the “Project”). (SCM’s Separate Statement of Uncontroverted Facts (“SUF”) 9 1, ECF No. 57-7.) BVB, as principal, and Hanover, as surety, executed and delivered 10 a Miller Act payment bond for the Project to the United States. (SUF 2.) BVB hired 11 SCM as subcontractor, specifically to purchase and install three boilers. (SUF 3, 6.) 12 Thus, BVB and SCM entered into a written subcontract agreement. (SCM’s 13 App. of Exs. in Supp. of Mot., Ex. 3 (“Subcontract”), ECF No. 57-4.) In relevant part, 14 the Subcontract provides: 15 In the event of elimination or reduction of the Work to be performed under this [Subcontract] by reason of termination or modification of the 16 [Subcontract] or [Prime Contract] or by default by the [VA], [SCM] shall 17 in no case be entitled to recover from [BVB] more than any sum equal to 18 the percentage of Work completed by [SCM] and approved by [BVB] and/or [the VA] that is properly invoiced at the time of termination or 19 modification of the [Subcontract]. [SCM] may not be entitled to the full 20 sum commensurate with the percentage of Work completed. 21 (Subcontract § 31(A).) The Subcontract also states, “Payment will reflect the 22 percentage of the work completed by [SCM] for the payment period as determined by 23 1 Having carefully considered the papers filed in connection with the Motion, the Court deemed the 24 matter appropriate for decision without oral argument. Fed. R. Civ. P. 78; C.D. Cal. L.R. 7-15. 25 2 Both parties submitted objections to evidence. Some of the evidence to which the parties object is unnecessary to the resolution of the Motion, and other such evidence supports facts not in dispute. 26 The Court need not resolve those objections at this time. To the extent the Court relies on objected- to evidence in this Order, the objections thereto are OVERRULED. See Burch v. Regents of Univ. 27 of Cal., 433 F. Supp. 2d 1110, 1119 (E.D. Cal. 2006) (“[O]bjections to evidence on the ground that it 28 is irrelevant, speculative, and/or argumentative, or that it constitutes an improper legal conclusion are all duplicative of the summary judgment standard itself.”). 1 [BVB] and/or [the VA].” (Id. § 23(A).) Under the Subcontract, if the VA separately 2 estimates the amount of work done by SCM, then the VA’s estimates “shall be final 3 and binding upon the parties and shall conclusively establish the amount of work done 4 by [SCM] for which payment is to be made.” (Id.) 5 On July 3, 2018, the VA suspended the Project. (SUF 19.) On August 20, 6 2018, the VA terminated the Prime Contract for convenience. (SUF 21.) And on 7 August 30, 2018, BVB notified SCM of the VA’s termination of the Prime Contract. 8 (SUF 22.) 9 At issue are four monthly payment applications SCM submitted to BVB with a 10 total billed sum of $1,902,592.30. (SUF 26–30.) BVB submitted its own payment 11 applications to the VA that incorporated SCM’s billed work. (BVB & Hanover’s 12 Resp. to SCM’s Separate Statement of Unconverted Facts (“RSUF”) 39–41, ECF 13 No. 58-2.) The VA disputed billed items in BVB’s applications concerning SCM’s 14 work and rendered estimated completion percentages lower than SCM’s estimates as 15 billed to BVB. (RSUF 43–46, 59–61.) In March 2020, BVB paid SCM $190,898.96, 16 the value of SCM’s work based on the VA’s estimated completion percentages. 17 (SUF 34; RSUF 53.) 18 Whether BVB and Hanover owe the unpaid balance of SCM’s billings to BVB 19 (plus interest) is in dispute. SCM sues for (1) recovery on the Miller Act payment 20 bond against BVB and Hanover and (2) breach of the Subcontract against BVB. (Ans. 21 & Cross-Claim of SCM, Cross-Claim ¶¶ 6–18, ECF No. 17.) BVB and Hanover sue 22 SCM for (1) negligence and (2) breach of the Subcontract. (Ans. & Cross-Claim of 23 BVB & Hanover, Cross-Claim ¶¶ 5–16, ECF No. 37.)3 24 III. LEGAL STANDARD 25 A court “shall grant summary judgment if the movant shows that there is no 26 genuine dispute as to any material fact and the movant is entitled to judgment as a 27 3 The claims of Use Plaintiff Cleaver-Brooks, Inc.—SCM’s sub-subcontractor—seeking payment for 28 the materials it manufactured for the Project, are not relevant to this Motion. (See generally Compl., ECF No. 1) 1 matter of law.” Fed. R. Civ. P. 56(a). The burden of establishing the absence of a 2 genuine issue of material fact lies with the moving party, see Celotex Corp. v. Catrett, 3 477 U.S. 317, 322–23 (1986), and the court must view the facts and draw reasonable 4 inferences in the light most favorable to the nonmoving party. Scott v. Harris, 550 5 U.S. 372, 378 (2007). A disputed fact is “material” where the resolution of that fact 6 might affect the outcome of the suit under the governing law, and the dispute is 7 “genuine” where “the evidence is such that a reasonable jury could return a verdict for 8 the nonmoving party.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). 9 Conclusory or speculative testimony in affidavits is insufficient to raise genuine issues 10 of fact and defeat summary judgment. Thornhill Publ’g Co. v. GTE Corp., 594 11 F.2d 730, 738 (9th Cir. 1979). Moreover, though the Court may not weigh conflicting 12 evidence or make credibility determinations, there must be more than a mere scintilla 13 of contradictory evidence to survive summary judgment. Addisu v. Fred Meyer, Inc., 14 198 F.3d 1130, 1134 (9th Cir. 2000). 15 Once the moving party satisfies its burden, the nonmoving party cannot simply 16 rest on the pleadings or argue that any disagreement or “metaphysical doubt” about a 17 material issue of fact precludes summary judgment. Matsushita Elec. Indus. Co., Ltd. 18 v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
United States v. South Coast Mechanical, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-south-coast-mechanical-inc-cacd-2020.