United States v. Schluneger

CourtCourt of Appeals for the Tenth Circuit
DecidedJuly 9, 1999
Docket98-5200
StatusPublished

This text of United States v. Schluneger (United States v. Schluneger) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Schluneger, (10th Cir. 1999).

Opinion

F I L E D United States Court of Appeals Tenth Circuit PUBLISH JUL 9 1999 UNITED STATES COURT OF APPEALS PATRICK FISHER Clerk TENTH CIRCUIT

UNITED STATES OF AMERICA,

Plaintiff - Appellee, v. No. 98-5200 STEVEN L. SCHLUNEGER,

Defendant - Appellant.

Appeal from the United States District Court for the Northern District of Oklahoma (D.C. No. 97-CR-98-C)

Submitted on the briefs:

Robert G. Green, Tulsa, Oklahoma, for Defendant-Appellant.

Stephen C. Lewis, United States Attorney, Tulsa, Oklahoma, and Gordon B. Cecil, Special Assistance United States Attorney, Muskogee, Oklahoma, for Plaintiff-Appellee.

Before TACHA, MAGILL, * and BRISCOE, Circuit Judges.

MAGILL, Circuit Judge.

* Honorable Frank Magill, Senior Circuit Judge, United States Court of Appeals for the Eighth Circuit, sitting by designation. A jury convicted Stephen Schluneger on one count of conspiracy to defraud

the government. The district court denied Schluneger’s motions for a judgment of

acquittal and for a new trial, and sentenced Schluneger to twelve months’

imprisonment. Schluneger appeals both his conviction and his sentence. We

affirm.

I.

In February 1988 the United States Army Corps of Engineers (Corps)

awarded a $1.8 million contract to Frank Minelli, doing business as Swiss Craft

Professional Painters, for sandblasting and painting various locks and dams along

the Arkansas River (Minelli contract). As a condition of the contract, Minelli was

required to provide the Corps with payment and performance bonds. Thomas

Rhoades and Schluneger furnished the bonds as sureties in case Minelli defaulted

on the government contract.

Minelli eventually defaulted on the contract, and on July 18, 1989, the

Corps terminated him as the contractor. The Corps then demanded that Rhoades

and Schluneger satisfy their obligations and liability under the terms of the bonds.

The unpaid balance at the time of termination was approximately $1.69 million.

Under the bonds’ terms and relevant federal acquisition regulations, Rhoades and

Schluneger had three options: complete the work with a contractor of their choice

-2- that was acceptable to the government, complete the work with their own

resources, or discharge their liability under the bond by payment to the

government. Rhoades and Schluneger opted to complete the work with a

contractor of their choice.

Rhoades and Schluneger subsequently accepted a bid from Skyline

Painting, Inc. (Skyline) to complete the work on the Minelli contract for $1.2

million. On August 4, 1989, Rhoades and Schluneger informed the Corps of their

intent to have Skyline finish the contract and asked to sign a takeover agreement.

The Takeover Agreement, as executed by Rhoades and Schluneger with the Corps,

restricted Rhoades and Schluneger from receiving any compensation for the work

performed except for “actual costs and expenses incurred in the completion of the

work.” Takeover Agreement at ¶ 8. The Takeover Agreement provided that

Rhoades and Schluneger were not to be compensated for “any amount in excess of

[their] total expenditures necessarily made in completing the work and

discharging” their liability under the performance bond. Id. at ¶ 10. The

Takeover Agreement was eventually signed on August 14, 1989.

Between the time they notified the Corps of their intent to have Skyline

finish the Minelli contract and the time they signed the Takeover Agreement,

Rhoades and Schluneger entered into a series of agreements, not disclosed to the

Corps, which had the intent and effect of billing the government for more than

-3- their actual costs and expenses. Although Skyline’s bid to complete the Minelli

contract was $1.2 million, Rhoades and Schluneger requested that Skyline sign an

agreement (Skyline Subcontract), prepared by attorney T. Robert Hughes, stating

that Skyline would complete the work for the “agreed contract price of

$1,690,000,” the entire amount remaining on the Minelli contract. Skyline

Subcontract at 1. This agreement was signed on August 10, 1989.

Skyline understood, however, that it was to receive only $1.2 million, and

that the difference was to be paid to Rhoades and Schluneger as finder’s fees and

engineering consulting fees. Although Skyline believed these fees to be

legitimate, in fact they were bogus, and, as the evidence at trial showed, neither

Schluneger nor his associates ever performed any consulting work. This fee

arrangement was memorialized in another agreement, prepared by Hughes and

signed on the same day as the Skyline Subcontract, obligating Skyline to pay to

ARCO Business Services, Ltd., a business trust administered by Hughes, finder’s

fees and engineering consulting fees (Skyline/ARCO Fee Agreement). Under

this agreement, Skyline would pay ARCO Business Services approximately

twenty-nine percent of each progress payment paid by the government to Skyline

during the course of the work, plus any remaining amounts paid by the

government to Skyline in excess of $1.2 million.

-4- On August 14, 1989, Rhoades and Schluneger signed the Takeover

Agreement. They did not disclose to the Corps either the arrangement for finder’s

fees and consulting fees or Skyline’s initial bid to complete the work for $1.2

million.

Before Skyline commenced work on the project, Hughes prepared another

agreement (ARCO/Rhoades Fee Agreement), on August 18, 1989, obligating

ARCO Properties, Ltd. (another Hughes business trust) to pay kickbacks to

Rhoades equal to fifty percent of all money received by ARCO Business Services

under the Skyline/ARCO Fee Agreement.

The payment scheme, which took place over the next three years, was

carried out in the following manner: Nancy Norvell, president of Skyline,

prepared all requests for progress payments, which included the bogus finder’s

fees and engineering fees. She included these fees in her progress reports based

on the misrepresentations by Rhoades and Schluneger that they were incurring

costs and expenses to ARCO Business Services in their performance of the

government contract. Norvell submitted these progress payment requests to

Rhoades who reviewed and approved them. Rhoades then sent the requests for

payment to the Corps.

Payments were mailed to Rhoades and made jointly payable to Rhoades and

Schluneger. After obtaining Schluneger’s endorsement, Rhoades usually made

-5- disbursements to Skyline. Skyline then made disbursements to ARCO Business

Services, which in turn made disbursements to ARCO Properties. Both ARCO

companies made kickback payments to Rhoades, Schluneger and Rhoades’s

spouse. Schluneger received about $38,000 throughout the course of the scheme.

The scheme was uncovered when Skyline abandoned the project due to financial

problems, and Rhoades and Schluneger defaulted on the contract.

The government indicted Schluneger, Rhoades, Hughes, ARCO Business

Services and ARCO Properties each on one count of conspiracy to defraud the

government. The jury returned guilty verdicts against all defendants. 1 Schluneger

and the other defendants moved for judgments of acquittal and a new trial. The

district court denied all motions. Schluneger was subsequently sentenced to

twelve months’ imprisonment and three years’ supervised release, and was

ordered to pay $10,000 in restitution.

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Pretty
98 F.3d 1213 (Tenth Circuit, 1996)
United States v. Janusz
135 F.3d 1319 (Tenth Circuit, 1998)
United States v. Brown
164 F.3d 518 (Tenth Circuit, 1998)
United States v. Kim A. Wise
990 F.2d 1545 (Tenth Circuit, 1992)
United States v. Virgil Allan Copus
110 F.3d 1529 (Tenth Circuit, 1997)
United States v. Gary Martin Banta
127 F.3d 982 (Tenth Circuit, 1997)
United States v. Clyde Wayne Melton
131 F.3d 1400 (Tenth Circuit, 1997)
United States v. Timothy Byrne
171 F.3d 1231 (Tenth Circuit, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
United States v. Schluneger, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-schluneger-ca10-1999.