ALBERTSON, Judge:
Pursuant to his conditional pleas of guilty, appellant was found guilty of 16 specifications of various drug-related activities, including 14 specifications of distribution of crystal methamphetamine on board ship to shipmates, in violation of Article 112a, Uniform Code of Military Justice (UCMJ), 10 U.S.C. § 912a. He was sentenced by officer members to confinement for five years, forfeiture of all pay and allowances, a fine of $5000.00, reduction to pay grade E-l, and a dishonorable discharge from the Naval Service. The convening authority approved the sentence adjudged.
The appellant made several motions before entering his pleas at trial, one of which was to dismiss the charges and specifications for lack of speedy trial. The denial of that motion by the military judge is now one of three specified assignments of error on review. We find no merit in the three assignments of error.1 Nevertheless, we will discuss the speedy trial assignment because it involves an interpretation of Rule for Courts-Martial (R.C.M.) 707(c)(9), Manual for Courts-Martial, United States, 1984, within a factual setting that has not [588]*588heretofore been judicially addressed by this Court.
Undisputed at trial and on review is the fact that, at the time of trial, appellant had been in continuous pretrial confinement for a period of 96 days. The dispute at trial and on review, however, revolves around the issue of whether nine days (9-17 July 1987) were excludable days under R.C.M. 707. While appellate counsel for both sides argue that the speedy trial dispute involves the application of three provisions, R.C.M. 707(c)(3), 707(c)(5)(A), and 707(c)(9), we will address the issue only insofar as it involves R.C.M. 707(c)(9).
First, we relate the chronology of events as gleaned from the record:
DATE OF EVENT TOTAL # # DAYS ELAPSED EVENT
DAYS BETWEEN EVENTS
17 April 1987 0 0 Appellant (A) interviewed by NIS: A confessed; A confined Navy Brig.
21 April 1987 4 NIS laboratory analysis prepared; presence of controlled substance confirmed.
23 April — 1 May 14 10 A’s commanding officer requests appointment of defense counsel for A; NIS interviews persons involved in case.
22 May 35 21 Original charge sheet with preferred charges (according to Art. 32 I.O. report, though SJA’s pretrial advice says 26 May) (original charge sheet is not contained in the record of trial).
28 May 41 NIS Investigation closed; report of investigation signed.
3 June 47 Original discovery package provided to trial defense counsel.
5 June 49 Detailed trial defense counsel receives case file from NLSO San Diego.
12 June 56 Article 32 Investigation scheduled.
18 June 62 USS HOEL (A’s command) officially informed of participation in READIEX, 9-17 July.
18-19 June Article 32 Investigation conducted; Government represents all witnesses will be available; lists witnesses; I.O. submits report of Article 32 recommending various deletions, additions, and consolidation of charges.
25 June 69 6 Notice of READIEX promulgated in POD of USS HOEL.
7 July 81 12 Charges re-preferred.
[589]*589DATE OF EVENT TOTAL # # DAYS ELAPSED EVENT DAYS BETWEEN EVENTS
8 July 82 1 SJA signs pretrial advice; Charges referred to GCM; A served with referred charges at approximately 1800.
9 July 83 1 Defense counsel received referred charges; defense counsel notified by trial counsel that Art. 39(a) session is scheduled for 10 July; USS HOEL departed on READIEX. R.C.M. 802 conference held. Defense counsel serves trial counsel with discovery request and witness request.
10 July 84 1 Article 39(a) session held. Trial counsel announced he was ready for trial with tangible evidence and witnesses Special Agent Eckrich; Special Agent Starnes; FN Baker; and HTFN Womer. Trial counsel stated some relevant and necessary witnesses and documents were on board USS HOEL and unavailable until 17 July 1987. Military judge continued case until 22 July. Defense states it’s not requesting continuance, so time attributable to government.
16 July 90 6 Some discovery provided defense counsel.
17 July 91 1 Members’ questionnaires provided defense; USS HOEL returns to San Diego; documents and witnesses made available to defense.
18-19 July 93 2 Additional discovery provided defense.
21 July 95 2 Certain prosecution witnesses received grants of immunity. Defense counsel received Government’s list of witnesses from trial counsel.
22 July 96 1 Trial begins.
At trial the military judge made essential findings of fact on the speedy trial motion raised by the appellant.2 While he addressed his findings to each of [590]*590the three theories offered by the Government as to why the motion should be denied, we will discuss his findings only in relation to the third theory, involving the application of R.C.M. 707(c)(9).3
[591]*591The third theory advanced by the Government was that the trial proceedings were delayed because of unusual operational requirements and military exigencies (READIEX) facing USS HOEL during the period 9-17 July 1987 and, as a result, the Government could not meet the defense’s R.C.M. 701 requeste and therefore could not proceed to try the appellant until the ship returned from the exercise. The military judge accepted this theory of the Government’s case. We will discuss the merits of this theory and the propriety of the military judge’s ruling.
As a general rule, the Government is accountable for bringing an accused to trial within 90 days if he is in continuous pretrial confinement. United States v. McCallister, 27 M.J. 138 (C.M.A.1988); United States v. Burton, 21 U.S.C.M.A. 112, 118, 44 C.M.R. 166, 172 (1971); United States v. Kohl, 26 M.J. 919 (N.M.C.M.R. 1988); R.C.M. 707(d). Because appellant had been in continuous pretrial confinement for 96 days on 22 July 1987, the day trial commenced,4 he was entitled to the relief of having the charges dismissed for lack of speedy trial unless the Government demonstrated that six or more days were excludable under R.C.M. 707(c).
We must determine, therefore, whether the military judge properly found that the nine days the USS HOEL was deployed and participating in READIEX were excludable under R.C.M. 707(e). If his finding was correct, then the appellant was not denied a speedy trial.
The nine days in question are ex-cludable if the Government can establish first, that “the period of delay was for good cause, including unusual operational requirements and military exigencies” (R.C.M. 707(c)(9); (United States v. Kuelker, 20 M.J. 715 (N.M.C.M.R.1985)); and second, that a nexus existed between the event established as good cause and the proceedings. United States v. Harris, 20 M.J. 795 (N.M.C.M.R.1985). This is the two-pronged analysis first enunciated by the U.S. Army Court of Military Review in United States v. Durr, 21 M.J. 576 (A.C.M.R.1985), and subsequently adopted by this Court in United States v. Lilly, 22 M.J. 620 (N.M.C.M.R.1986). Durr
Free access — add to your briefcase to read the full text and ask questions with AI
ALBERTSON, Judge:
Pursuant to his conditional pleas of guilty, appellant was found guilty of 16 specifications of various drug-related activities, including 14 specifications of distribution of crystal methamphetamine on board ship to shipmates, in violation of Article 112a, Uniform Code of Military Justice (UCMJ), 10 U.S.C. § 912a. He was sentenced by officer members to confinement for five years, forfeiture of all pay and allowances, a fine of $5000.00, reduction to pay grade E-l, and a dishonorable discharge from the Naval Service. The convening authority approved the sentence adjudged.
The appellant made several motions before entering his pleas at trial, one of which was to dismiss the charges and specifications for lack of speedy trial. The denial of that motion by the military judge is now one of three specified assignments of error on review. We find no merit in the three assignments of error.1 Nevertheless, we will discuss the speedy trial assignment because it involves an interpretation of Rule for Courts-Martial (R.C.M.) 707(c)(9), Manual for Courts-Martial, United States, 1984, within a factual setting that has not [588]*588heretofore been judicially addressed by this Court.
Undisputed at trial and on review is the fact that, at the time of trial, appellant had been in continuous pretrial confinement for a period of 96 days. The dispute at trial and on review, however, revolves around the issue of whether nine days (9-17 July 1987) were excludable days under R.C.M. 707. While appellate counsel for both sides argue that the speedy trial dispute involves the application of three provisions, R.C.M. 707(c)(3), 707(c)(5)(A), and 707(c)(9), we will address the issue only insofar as it involves R.C.M. 707(c)(9).
First, we relate the chronology of events as gleaned from the record:
DATE OF EVENT TOTAL # # DAYS ELAPSED EVENT
DAYS BETWEEN EVENTS
17 April 1987 0 0 Appellant (A) interviewed by NIS: A confessed; A confined Navy Brig.
21 April 1987 4 NIS laboratory analysis prepared; presence of controlled substance confirmed.
23 April — 1 May 14 10 A’s commanding officer requests appointment of defense counsel for A; NIS interviews persons involved in case.
22 May 35 21 Original charge sheet with preferred charges (according to Art. 32 I.O. report, though SJA’s pretrial advice says 26 May) (original charge sheet is not contained in the record of trial).
28 May 41 NIS Investigation closed; report of investigation signed.
3 June 47 Original discovery package provided to trial defense counsel.
5 June 49 Detailed trial defense counsel receives case file from NLSO San Diego.
12 June 56 Article 32 Investigation scheduled.
18 June 62 USS HOEL (A’s command) officially informed of participation in READIEX, 9-17 July.
18-19 June Article 32 Investigation conducted; Government represents all witnesses will be available; lists witnesses; I.O. submits report of Article 32 recommending various deletions, additions, and consolidation of charges.
25 June 69 6 Notice of READIEX promulgated in POD of USS HOEL.
7 July 81 12 Charges re-preferred.
[589]*589DATE OF EVENT TOTAL # # DAYS ELAPSED EVENT DAYS BETWEEN EVENTS
8 July 82 1 SJA signs pretrial advice; Charges referred to GCM; A served with referred charges at approximately 1800.
9 July 83 1 Defense counsel received referred charges; defense counsel notified by trial counsel that Art. 39(a) session is scheduled for 10 July; USS HOEL departed on READIEX. R.C.M. 802 conference held. Defense counsel serves trial counsel with discovery request and witness request.
10 July 84 1 Article 39(a) session held. Trial counsel announced he was ready for trial with tangible evidence and witnesses Special Agent Eckrich; Special Agent Starnes; FN Baker; and HTFN Womer. Trial counsel stated some relevant and necessary witnesses and documents were on board USS HOEL and unavailable until 17 July 1987. Military judge continued case until 22 July. Defense states it’s not requesting continuance, so time attributable to government.
16 July 90 6 Some discovery provided defense counsel.
17 July 91 1 Members’ questionnaires provided defense; USS HOEL returns to San Diego; documents and witnesses made available to defense.
18-19 July 93 2 Additional discovery provided defense.
21 July 95 2 Certain prosecution witnesses received grants of immunity. Defense counsel received Government’s list of witnesses from trial counsel.
22 July 96 1 Trial begins.
At trial the military judge made essential findings of fact on the speedy trial motion raised by the appellant.2 While he addressed his findings to each of [590]*590the three theories offered by the Government as to why the motion should be denied, we will discuss his findings only in relation to the third theory, involving the application of R.C.M. 707(c)(9).3
[591]*591The third theory advanced by the Government was that the trial proceedings were delayed because of unusual operational requirements and military exigencies (READIEX) facing USS HOEL during the period 9-17 July 1987 and, as a result, the Government could not meet the defense’s R.C.M. 701 requeste and therefore could not proceed to try the appellant until the ship returned from the exercise. The military judge accepted this theory of the Government’s case. We will discuss the merits of this theory and the propriety of the military judge’s ruling.
As a general rule, the Government is accountable for bringing an accused to trial within 90 days if he is in continuous pretrial confinement. United States v. McCallister, 27 M.J. 138 (C.M.A.1988); United States v. Burton, 21 U.S.C.M.A. 112, 118, 44 C.M.R. 166, 172 (1971); United States v. Kohl, 26 M.J. 919 (N.M.C.M.R. 1988); R.C.M. 707(d). Because appellant had been in continuous pretrial confinement for 96 days on 22 July 1987, the day trial commenced,4 he was entitled to the relief of having the charges dismissed for lack of speedy trial unless the Government demonstrated that six or more days were excludable under R.C.M. 707(c).
We must determine, therefore, whether the military judge properly found that the nine days the USS HOEL was deployed and participating in READIEX were excludable under R.C.M. 707(e). If his finding was correct, then the appellant was not denied a speedy trial.
The nine days in question are ex-cludable if the Government can establish first, that “the period of delay was for good cause, including unusual operational requirements and military exigencies” (R.C.M. 707(c)(9); (United States v. Kuelker, 20 M.J. 715 (N.M.C.M.R.1985)); and second, that a nexus existed between the event established as good cause and the proceedings. United States v. Harris, 20 M.J. 795 (N.M.C.M.R.1985). This is the two-pronged analysis first enunciated by the U.S. Army Court of Military Review in United States v. Durr, 21 M.J. 576 (A.C.M.R.1985), and subsequently adopted by this Court in United States v. Lilly, 22 M.J. 620 (N.M.C.M.R.1986). Durr also established a balancing test, wherein any determination of good cause, including reasons of unusual operational requirements and military exigencies, requires that the military judge weigh the interests of the appellant and the military in a speedy trial against the ends of justice that may be served by a delay in the trial proceedings.5
[592]*592In making this factual determination, R.C.M. 905(d) requires that the military judge enter essential findings on the record. Those essential findings must include a statement of the legal basis for his decision and any other statements that might clarify the reasons for his decision. United States v. Postle, 20 M.J. 632, 640 (N.M.C.M.R.1985). The absence of essential findings and conclusions of law relevant to the issue presented can, in some cases, require returning the record to the military judge to state the essential findings upon which he decided the motion. See United States v. Butterbaugh, 21 M.J. 1019 (N.M.C.M.R.1985), aff'd on remand, 22 M.J. 759 (N.M.C.M.R.1986), aff'd 25 M.J. 159 (C.M.A.1987).6
As in many motions to dismiss for denial of a speedy trial, the speedy trial motion in this case involved complicated issues of fact. As a result, R.C.M. 905(d), as interpreted by this Court in Postle, was applicable. Additionally, the critical legal issue involved in this case (application of R.C.M. 707(c)(9))7 also requires the employment of the aforementioned good cause/nexus analysis. United States v. Lilly and United States v. Durr, both supra. Thus, this case requires us to apply two overlapping concepts involving Durr/Lilly on the substantive speedy trial issue and Postle/Lilly on the adequacy of the military judge’s essential findings.
Appellant first asserts that the military judge did not adhere to this R.C.M. 905(d) Postle/Lilly mandate, arguing that, while the judge made some essential findings relating to the the good cause prong of the Durr/Lilly analysis, he failed to address the second, nexus prong. More specifically, appellant argues that the military judge did not state whether a nexus existed between the ship’s participation in READIEX and the delay in the trial proceedings. Appellate defense counsel further argues that this failure resulted in “substantial prejudice to the appellant.” Appellant’s Brief at 12.
As previously noted, the military judge did enter essential findings, stating both findings of fact and conclusions relating facts to the law. While he did not specifically cite to the Lilly or Durr case, our review of his essential findings indicates that he followed substantially both prongs of the requisite analysis when he stated that
[t]he delay in these proceedings was indeed caused by an unusual operational requirement and military exigencies. The underway period of USS HOEL from 9 to 17 July 1987 was unusual and unexpected. Although deployment dates for combatant ships are always changing, the incident involving the USS STARK in the Persian Gulf precipitated these short notice changes in the schedule of USS HOEL. The USS STARK incident occurred at a critical time in the progression of this case to trial.
(Emphasis added.) Appellate Exhibit XXXIV, p. 3-4.
We do not believe that Postle or Lilly intended to establish a hard and fast rule that the military judge must state explicitly his findings in strict formalistic accordance with their two-tiered analytical framework. Rather, we believe that Postle/Lilly and R.C.M. 905(d) stand for the proposition that so long as the record demonstrates that the military judge applied the correct law to the facts, and that the facts he found are supported by the evidence of record, then his ruling should be upheld. In this case, the above-quoted statement of the military judge implicitly meets the R.C.M. 905(d) Postle/Lilly mandate.
We next address the primary question as to whether the military judge committed legal error in arriving at his decision denying appellant’s motion to dismiss.8 The evidence establishes that the [593]*593USS HOEL had been initially scheduled to deploy to the Western Pacific in December, some four to five months after the July date which had been announced for appellant’s court-martial. Prior to appellant’s trial, however, the ship’s departure date was moved up to July. This earlier deployment schedule was precipitated by “two national events, one being the attaek on the STARK and the other being the general situation in the deployment of forces worldwide on an unclass level.” R. 36. This earlier schedule required that the preparation period prior to deployment be compressed. The HOEL’s participation in READIEX was part of the preparation and, because of the compressed schedule, the ship was required to utilize the days in question, 9-17 July, for the exercise. Certainly, preparation for an ordinary operational schedule does not constitute a military exigency. See United States v. Harris, supra. The HOEL’s schedule went beyond the ordinary, however, when its preparation period for deployment was substantially compressed and when the deployment preparation period required participation in READIEX, which in and of itself involved an intense and complicated schedule of events. Additionally, the STARK incident enhanced the intensity of the situation because it raised “a lot of different questions ... about composition of ships, who was equipped and who was not equipped to deal with an assignment in the Middle East, and as a result of those questions three of our ships, because of their weapons capabilities,” (R. 43) were being considered for possible assignment. The HOEL was “[a] candidate for an earlier deployment ... and a candidate for the MISSOURI battle group at some point in time after that Monday [the day of the STARK incident].” READIEX was the “final exam” for any ship to be deployed to WESTPAC. The exercise determined whether the ships as a group could function as one for any engagement; it tested “the communications, the coordination, and the control of all of those elements to function smoothly____” R. 44. It would be difficult to imagine a better example of a peacetime military exigency or unusual operational requirement than a combatant ship facing an advanced and compressed schedule under the pressures of ensuring that its imminent deployment to a tense theater of operations would be accomplished without any question of its complete capability to support the force structure in that theater. We find that the evidence presented at trial supports the military judge’s essential finding of fact that the period of delay caused by HOEL’s deployment was for good cause. We specifically agree that the situation presented by the HOEL’s advanced READIEX schedule in combination with the STARK incident was both a “military exigency” and an “unusual operational requirement” as defined in R.C.M. 707(c)(9).
Having found the military judge correct in ruling that the HOEL’s nine day deployment constituted good cause for delay, we move on to determine whether he was correct in finding the existence of the nexus prong of Postle/Lilly. And, we do. Since the defense requested witnesses and documents were aboard the HOEL at sea and the defense believed it could not prepare or present a proper defense without those witnesses and documents, the military judge properly ruled that the Government had to comply with the R.C.M. 701 discovery request before the trial could proceed. Accordingly, a nexus between the HOEL’s nine-day deployment and the delay in appellant’s court-martial existed and was properly found by the military judge.
In sum, therefore, we concur with the military judge’s findings that (1) the [594]*594Government was required to comply with the R.C.M. 701 request before it could proceed to trial; (2) the witnesses and documentary evidence requested by the defense were aboard the USS HOEL then at sea participating in READIEX; (3) the deployment of the HOEL was an unusual operational requirement and military exigency that was good cause for the nine-day delay in appellant’s court-martial; and (4) the inability of the Government to comply with the defense request for witnesses and documents located aboard the HOEL at sea until after the HOEL’s nine-day deployment prevented the court-martial from proceeding.9 Finally' we concur that in light of the fact that the witnesses and documents aboard the HOEL were requested by the defense and apparently necessary for the preparation and presentation of its case, the balancing required by Durr/Lilly overwhelmingly tilts in favor of exclusion, of the nine days under R.C.M. 707(c)(9). Accordingly, we find that the military judge did not err in denying the defense motion for dismissal of the charges for lack of speedy trial.10
Finally, we conclude that no error prejudicial to the substantial rights of the appellant was committed. Accordingly, the find[595]*595ings and sentence as approved on review below are affirmed.
Senior Judge COUGHLIN concurs.