United States v. Rueth Devmt Co

CourtCourt of Appeals for the Seventh Circuit
DecidedJuly 10, 2003
Docket02-2045
StatusPublished

This text of United States v. Rueth Devmt Co (United States v. Rueth Devmt Co) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Rueth Devmt Co, (7th Cir. 2003).

Opinion

In the United States Court of Appeals For the Seventh Circuit ____________

No. 02-2045 UNITED STATES OF AMERICA, Plaintiff-Appellee, v.

RUETH DEVELOPMENT CO. and HAROLD G. RUETH, Defendants-Appellants. ____________ Appeal from the United States District Court for the Northern District of Indiana, Hammond Division. No. 2:96-cv-540—James T. Moody, Judge. ____________ ARGUED APRIL 9, 2003—DECIDED JULY 10, 2003 ____________

Before FLAUM, Chief Judge, and POSNER and KANNE, Circuit Judges. FLAUM, Chief Judge. In 1996 the United States sued the Rueth Development Company and Harold Rueth (col- lectively “Rueth”) under the Clean Water Act, 33 U.S.C. § 1251 et seq. (“CWA” or “the Act”), for failure to obtain a permit before discharging dredged or fill material into four acres of wetlands located in Dyer, Indiana. Rueth chose to settle the suit and entered into a consent decree that required him to restore the wetlands by specified dates. When he failed to meet those deadlines, the gov- ernment moved to enforce the agreement, seeking over $6,750,000 in penalties. Rueth responded by petitioning for 2 No. 02-2045

modification or vacatur of the consent decree based on the Supreme Court’s decision in Solid Waste Agency of N. Cook County v. United States Army Corps of Eng’rs, 531 U.S. 159 (2001) (“SWANCC”), which he claimed was a material change in law affecting the decree’s validity. The district court disagreed, granted the government’s mo- tion to enforce, and assessed penalties in the amount of $4,018,500, and Rueth appeals. We affirm.

I. BACKGROUND In April 1991 the Environmental Protection Agency (“EPA”) issued an administrative compliance order under 33 U.S.C. § 1319(a), finding that Rueth had illegally discharged dredged or fill material into wetlands located in the Castlewood subdivision of southeastern Dyer. The fill was specifically found to have been placed in wetlands “adjacent to an unnamed tributary to Dyer Ditch, which flows north to Hart Ditch, which flows north to the Little Calumet River, which is a navigable water of the United States.” The compliance order directed Rueth to cease all discharges and restore the wetlands to their original condition, warning that noncompliance could re- sult in the assessment of substantial penalties under the CWA. Rueth then proceeded to apply for an after-the-fact per- mit from the United States Army Corps of Engineers (“Corps”). The Corps declined to give approval, however, noting its concern that Rueth was presenting his develop- ment plans in a piecemeal fashion in an attempt to avoid a comprehensive review of their cumulative environ- mental impact. The Corps stated that it would reconsider its position if Rueth modified his plans so that less than ten acres of wetlands were affected. Rueth did not submit new development plans, reapply for a permit, or undertake the restoration activities out- No. 02-2045 3

lined in the administrative compliance order. Instead, he filed a complaint for equitable relief in the district court, claiming that the government lacked regulatory jurisdic- tion over the wetlands in the Castlewood subdivision. But because the administrative compliance order was a pre- enforcement action not subject to judicial review, the district court dismissed the suit, and we affirmed, stating that Rueth could contest jurisdiction if and when the EPA sought judicial or administrative enforcement of penalties against him. Rueth v. EPA, 13 F.3d 227, 230 (7th Cir. 1993) (“Rueth I”). We also remarked in passing, We acknowledge that our holding places Rueth some- what in limbo until such time as the EPA seeks to enforce the compliance order or assess administrative penalties. . . . Responsibility for this predicament does not fall entirely on the EPA and the Corps of Engi- neers, as any reasonable and experienced developer such as Rueth should have known that the wetlands were potentially subject to regulation. Perhaps Rueth is in its present predicament because it attempted to short cut and take an end-run around the permit requirement. . . . Of course, Rueth now argues that it had no idea the wetlands at the Castlewood develop- ment were “waters of the United States” [within the meaning of the CWA]. As our decision in Hoffman Homes, Inc. v. EPA, 999 F.2d 256, 261 (7th Cir. 1993), makes clear, however, nearly all wetlands fall within the jurisdiction of the CWA since one test for whether the wetland affects interstate commerce is whether migratory birds use the wetland. Decisions such as Hoffman Homes, give full effect to Congress’s intent to make the Clean Water Act as far-reaching as the Commerce Clause permits. On the other hand, it is not inconceivable that the EPA or the Corps of Engi- neers might completely overextend their authority. In such a case, we suggest to those agencies that we 4 No. 02-2045

will not hesitate to intervene in pre-enforcement ac- tivity, but this is not the case as we are of the opinion that the wetland at issue falls under the broad defini- tion of “waters of the United States” in Hoffman Homes. Rueth I, 13 F.3d at 230-31 (citation omitted). By November 1996 Rueth had still not performed the tasks outlined in the administrative compliance order, prompting the government to file this enforcement action. The complaint asserted two bases for the government’s regulatory jurisdiction: (1) adjacency—specifically, that the Castlewood wetlands were “adjacent to waters which flow into the Little Calumet River, an interstate stream, which itself is a ‘water of the United States’ within the meaning of the CWA,” see 40 C.F.R. § 230.3(s)(7); and (2) effect on interstate commerce, see id. § 230.3(s)(3). In addition to injunctive relief, the complaint requested that the district court assess a civil penalty under 33 U.S.C. § 1319(d) for each day that Rueth was in violation of the CWA and the administrative compliance order. After over a year of negotiations, the parties entered into a proposed consent decree, which the court then entered as a final judgment in January 1999. In the con- sent decree, Rueth agreed to perform a number of “mile- stone” tasks—such as excavating fill, sealing and raising storm sewers, and replacing wetland vegetation—by set deadlines. The agreement also required Rueth to pay a $23,000 civil penalty and set forth additional stipulated penalties that would result from failure to meet “any milestone” according to the specified timetable. Rueth ultimately completed the wetland restoration at a cost of around $100,000 but failed to perform a number of the interim milestones in a timely fashion. Because of this failure, the government moved to enforce the stip- ulated-penalties provision of the consent decree, alleging that Rueth had “in very large part” disregarded his ob- No. 02-2045 5

ligations under the agreement. For instance the govern- ment asserted that Rueth was 67 days late in paying the $23,500 penalty, 579 days late in excavating the fill and performing the storm-sewer tasks, and 158 days late in replacing the wetland vegetation. The government sought a separate stipulated penalty for each alleged violation of the agreement, resulting in a grand total of $6,757,500. But before the district court could rule on the govern- ment’s motion to enforce, Rueth moved under Fed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
United States v. Rueth Devmt Co, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-rueth-devmt-co-ca7-2003.