United States v. R.M. Packer Co.
This text of 355 F. Supp. 3d 66 (United States v. R.M. Packer Co.) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
CASPER, District Judge.
I. Introduction
Plaintiff United States of America ("USA") seeks partial summary judgment on claims pursuant to the Clean Air Act,
II. Standard of Review
Summary judgment is appropriate where there is no genuine dispute as to any material fact and the undisputed facts establish that the movant is entitled to judgment as a matter of law. Fed. R. Civ. P. 56(a). "A fact is material if it carries with it the potential to affect the outcome of the suit under the applicable law." Santiago-Ramos v. Centennial P.R. Wireless Corp.,
III. Factual Background
A. Tisbury Towing
The following facts are undisputed unless otherwise noted. Tisbury Towing is a marine transportation company and is regulated by the Massachusetts State Implementation Plan ("SIP").2 310 C.M.R. § 7.00 ; D. 41-2 ¶¶ 4-5; D. 44-3 ¶¶ 4-5. For at least twenty-five years, Tisbury Towing has owned a single hull barge called the Rando 200. D. 41-2 ¶ 6; D. 44-3 ¶ 6; D. 44-3 at n.1. Under the SIP, the Rando 200 qualifies as a "marine tank vessel," D. 41-2 ¶ 6; D. 44-3 ¶ 6, defined as "any marine vessel [ ] capable of carrying liquid bulk cargo in tanks," 310 C.M.R. § 7.00. Until December 31, 2015, the Rando 200 was used to transport gasoline from the Tisbury Towing pier in New Bedford to Martha's Vineyard. D. 41-2 ¶ 7; D. 44-3 ¶ 7. Because the Rando 200 transported "organic liquids," Tisbury Towing was subjected *71to the "Marine Volatile Organic Liquid Transfer" regulation, pursuant to the SIP, commencing from its 2000 approval until December 2015, when its' operation ceased. D. 41-2 ¶ 8; see 310 C.M.R. § 7.24(8)(a). Under this regulation, no person may load a marine tank vessel unless it is "vapor tight" or is loaded at less than atmospheric pressure. 310 C.M.R. § 7.24(8)(e)(1). Here, the transfer at issue could not be done at less than atmospheric pressure3 so Tisbury Towing's compliance with the regulation turns upon whether the "vapor tight" condition was met.
On November 8, 2011, gasoline was transferred from a tanker trunk into the Rando 200. D. 41-2 ¶ 9; D. 44-3 ¶ 9. Tisbury Towing asserts that this transfer was a "planned test of the barge, Rando 200, for the purpose of complying with all the applicable regulations." D. 44-3 ¶ 9. Daniel Gavin ("Inspector Gavin") and Steven Risi ("Inspector Risi") from the Massachusetts Department of Environmental Protection "(MassDEP"), William Osbahr ("Inspector Osbahr") and Michael Looney from the Environmental Protection Agency ("EPA"), Raymond Colicci ("Colicci") and Nate Pierce from the United States Coast Guard ("Coast Guard") and Captain Paul Bangs ("Captain Bangs"), captain of the Rando 200 at Tisbury Towing observed this loading event. D. 41-2 ¶ 9; D. 44-3 ¶ 9. This loading event revealed that the Rando 200 was not "vapor tight through any of the three available methods set forth in the SIP." D. 41-2 ¶ 10; D. 44-3 ¶ 10; 310 C.M.R.
Free access — add to your briefcase to read the full text and ask questions with AI
CASPER, District Judge.
I. Introduction
Plaintiff United States of America ("USA") seeks partial summary judgment on claims pursuant to the Clean Air Act,
II. Standard of Review
Summary judgment is appropriate where there is no genuine dispute as to any material fact and the undisputed facts establish that the movant is entitled to judgment as a matter of law. Fed. R. Civ. P. 56(a). "A fact is material if it carries with it the potential to affect the outcome of the suit under the applicable law." Santiago-Ramos v. Centennial P.R. Wireless Corp.,
III. Factual Background
A. Tisbury Towing
The following facts are undisputed unless otherwise noted. Tisbury Towing is a marine transportation company and is regulated by the Massachusetts State Implementation Plan ("SIP").2 310 C.M.R. § 7.00 ; D. 41-2 ¶¶ 4-5; D. 44-3 ¶¶ 4-5. For at least twenty-five years, Tisbury Towing has owned a single hull barge called the Rando 200. D. 41-2 ¶ 6; D. 44-3 ¶ 6; D. 44-3 at n.1. Under the SIP, the Rando 200 qualifies as a "marine tank vessel," D. 41-2 ¶ 6; D. 44-3 ¶ 6, defined as "any marine vessel [ ] capable of carrying liquid bulk cargo in tanks," 310 C.M.R. § 7.00. Until December 31, 2015, the Rando 200 was used to transport gasoline from the Tisbury Towing pier in New Bedford to Martha's Vineyard. D. 41-2 ¶ 7; D. 44-3 ¶ 7. Because the Rando 200 transported "organic liquids," Tisbury Towing was subjected *71to the "Marine Volatile Organic Liquid Transfer" regulation, pursuant to the SIP, commencing from its 2000 approval until December 2015, when its' operation ceased. D. 41-2 ¶ 8; see 310 C.M.R. § 7.24(8)(a). Under this regulation, no person may load a marine tank vessel unless it is "vapor tight" or is loaded at less than atmospheric pressure. 310 C.M.R. § 7.24(8)(e)(1). Here, the transfer at issue could not be done at less than atmospheric pressure3 so Tisbury Towing's compliance with the regulation turns upon whether the "vapor tight" condition was met.
On November 8, 2011, gasoline was transferred from a tanker trunk into the Rando 200. D. 41-2 ¶ 9; D. 44-3 ¶ 9. Tisbury Towing asserts that this transfer was a "planned test of the barge, Rando 200, for the purpose of complying with all the applicable regulations." D. 44-3 ¶ 9. Daniel Gavin ("Inspector Gavin") and Steven Risi ("Inspector Risi") from the Massachusetts Department of Environmental Protection "(MassDEP"), William Osbahr ("Inspector Osbahr") and Michael Looney from the Environmental Protection Agency ("EPA"), Raymond Colicci ("Colicci") and Nate Pierce from the United States Coast Guard ("Coast Guard") and Captain Paul Bangs ("Captain Bangs"), captain of the Rando 200 at Tisbury Towing observed this loading event. D. 41-2 ¶ 9; D. 44-3 ¶ 9. This loading event revealed that the Rando 200 was not "vapor tight through any of the three available methods set forth in the SIP." D. 41-2 ¶ 10; D. 44-3 ¶ 10; 310 C.M.R. § 7.24(8)(e)(2).4 That is, Tisbury Towing neither provided documentation of a vapor-tightness pressure test or vapor-tightness leak test conducted in the 12 months prior to the loading event nor conducted a vapor-tightness leak test during the event. D. 44-3 ¶ 10. Moreover, during the loading event, "EPA inspector [ ] Osbahr and MassDEP inspector [ ] Gavin ("Inspector Gavin") heard an audible hiss, indicating the presence of a leak, from a pressure vacuum valve." D. 41-2 ¶ 15; D. 44-3 ¶ 15. Both Captain Bangs and Inspector Obahr smelled gasoline, indicative of a vapor leak. D. 41-2 ¶ 16; D. 44-3 ¶ 16. With a device called a Flame Ionization Detector,5 EPA Inspector Obahr confirmed volatile organic compound ("VOC") vapors on the Rando 200 that exceeded 10,000 parts per million ("ppm") coming from the high velocity pressure vacuum valve. D. 41-2 ¶ 17; D. 44-3 ¶ 17. EPA inspectors also detected and confirmed emissions leaks from the valve using an infrared video camera. D. 41-2 ¶ 18; D. 44-3 ¶ 18. Accordingly, the "inspectors detected and confirmed the presence of a leak through auditory, olfactory, visual and technological means." D. 41-2 ¶ 19; D. 44-3 ¶ 19. As a result, the Coast Guard issued an order on November 8, 2011 to "make repairs prior to loading further cargo onto the Rando 200." D. 41-2 ¶ 20; D. 44-3 ¶ 20. Tisbury Towing contends that it complied with this order. D. 44-3 ¶ 20.
Moreover, Tisbury Towing did not comply with the requirement to submit an Emissions Control Plan to MassDEP within *72the requisite time frame. 310 C.M.R. § 7.24(8)(f) ; D. 41-2 ¶ 21; D. 44-3 ¶ 21. An Emission Control Plan is necessary to ensure that a facility like Tisbury Towing's "will not cause or contribute to a condition of air pollution or a violation of any other regulation." 310 C.M.R. § 7.18(20)(g). Within 180 days of the Rando 200's first entry into service or the effective date of the applicable regulation, whichever is later, Tisbury Towing was required to submit such plan to the MassDEP. 310 C.M.R. § 7.18(20)(a)(1) ; D. 41-2 ¶ 21; D. 44-3 ¶ 21. Since the Rando 200 had been operating since at least 1992 and the regulation became effective upon the EPA's approval of it on April 11, 2000, Tisbury Towing's plan was due no later than October 8, 2000. D. 41-2 ¶ 21; D. 44-3 ¶ 21. As of November 8, 2011, when the loading event described above occurred, Tisbury Towing still had not submitted this plan. D. 41-2 ¶ 22; D. 44-3 ¶ 22. It submitted a draft Emissions Control Plan to the EPA on June 17, 2014, but this draft failed to comply with the minimum requirements of SIP regulations. D. 41-2 ¶ 24; D. 44-3 ¶ 24. The EPA, MassDEP, Coast Guard and Tisbury Towing subsequently exchanged drafts and comments and Tisbury Towing eventually submitted a revised draft on May 27, 2016, which was approved by MassDEP on April 7, 2017. D. 41-2 ¶¶ 25-26; D. 44-3 ¶¶ 25-26.
B. R.M. Packer
1. Material Facts Concerning the Clean Air Act
R.M. Packer owns and operates a Bulk Fuel Facility (the "Facility") in Vineyard Haven, also on Martha's Vineyard, where "[g]asoline and other organic liquids are stored in above-ground tanks and disbursed through a loading rack into tanker trucks for distribution." D. 46-2 ¶ 2; D. 48-3 ¶ 2. Absent air pollution control equipment and practices, the pumping of liquid gasoline into the tanker trucks can displace vapors within the trucks. D. 46-2 ¶ 3; D. 48-3 ¶ 3. These vapors include VOCs and hazardous air pollutants like benzene, toluene and ethylene. D. 46-2 ¶ 4; D. 48-3 ¶ 4. Given the concerns about releasing ozone into the air,
On June 10, 2013, the EPA observed a pressure vacuum relief valve emitting VOC vapors via an infrared video camera, which revealed that R.M. Packer had not collected and disposed of all vapors discharged during the transfer of gasoline. D. 46-2 ¶ 11; D. 48-3 ¶ 11. The pressure vacuum relief valve, when properly functioning and maintained, is designed to "prevent a tank rupture, arising from a high pressure within the system, or an implosion, resulting from a vacuum within the system." D. 46-2 ¶ 12; D. 48-3 ¶ 12. Neither high pressure nor vacuum conditions were present during the June 10, 2013 inspection thereby indicating that the pressure vacuum relief valve was not functioning properly and had not been properly maintained.
Sometime after Steiner's inspection, R.M. Packer's electrician performed some work on its electrical system and valves and R.M. Packer replaced the pressure vacuum relief valves in either late 2014 or 2015. D. 46-2 ¶ 18; D. 48-3 ¶ 18. R.M. Packer hired Timothy Levanduski (brother of Thomas) to reevaluate its Vapor Recovery Unit.
2. Material Facts Concerning the Clean Water Act
The Facility, owned by R.M. Packer, includes 188, 190, and 199 Beach Road in Tisbury and lot 34 (an adjacent parcel). D. 46-2 ¶ 38; D. 48-3 ¶ 38. On these properties, R.M. Packer conducts several different industrial operations, which "includes fuel transport and sales, boat repair, and the transport of products over water using barges." D. 46-2 ¶ 38; D. 48-3 ¶ 38. Performing these activities on-site requires R.M. Packer to store and distribute petroleum products, waste and scrap material, welds, sandblasts and to repair and lubricate engines on the properties.
According to R.M. Packer's 2015 Stormwater Pollution Prevention Plan ("SWPPP"), its Facility has four outfalls to navigable water. D. 46-2 ¶ 41; D. 48-3 ¶ 41. During the 2008 SWPPP period, however, R.M. Packer failed to "perform quarterly visual inspections or benchmark monitoring of the outfalls" and thus did not submit data to the EPA as required under the 2008 Multi-Section General Permit ("MSGP")
IV. Procedural History
On April 21, 2016, USA instituted this action against the Defendants seeking civil penalties and injunctive relief. D. 1 in 16-10769; D. 1 in 16-10767. In the amended complaint, USA asserted claims under the Clean Air Act against Tisbury Towing for "failure to conduct a loading event from a marine tank vessel in a vapor tight manner" ("Claim 1") and failure to submit an emission control plan ("Claim 2"). D. 33 in 16-10769. Against R.M. Packer, the USA asserts claims under the Clean Air Act for failure to operate in a manner consistent with safety and good air pollution control practices ("Claim 1"), failure to timely submit an initial notification ("Claim 2"), failure to timely submit notification of compliance status ("Claim 3"), failure to conduct monthly leak inspections and maintain records ("Claim 4"), failure to collect and dispose of discharged vapor ("Claim 5"), failure to properly maintain and operate the vapor recovery unit ("Claim 6"), failure to comply with and an EPA issued testing order ("Claim 7"), and claims under the Clean Water Act for failure to perform effluent benchmark monitoring, outfall inspections, facility inspections, site evaluations and employee training ("Claim 8"), failure to minimize discharges related to blasting and painting into receiving waters ("Claim 9"), failure to modify storm water pollution prevention plan ("Claim 10") and failure to comply with request for information letter ("Claim 11"). D. 33 in 16-10767. The USA has now moved for partial summary judgment on liability against Tisbury Towing, D. 41, and R.M. Packer, D. 44. The Court heard arguments and took the matters under advisement. D. 48; D. 52.
V. Discussion
A. Claims under the Clean Air Act
1. The USA Is Entitled to Summary Judgment on Its Clean Air Act Claims against Tisbury Towing
a. Tisbury Towing Failed to Conduct a Loading Event in a Vapor-Tight Manner (Claim 1)
The USA contends that Tisbury Towing failed to demonstrate that its vessel was vapor tight during the loading event as required. D. 41-1 at 9. It is undisputed that during the loading event on November 8, 2011, Tisbury Towing provided no proof of vapor tightness under any of the three methods specified under the regulation and the presence of a leak was confirmed through auditory, olfactory, visual and technological means by the inspectors present, D. 41-2 ¶ 19; D. 44-3 ¶ 19. Tisbury Towing has not produced evidence indicating its compliance with the vapor tightness requirement.
*75Instead, Tisbury Towing contends that the November 8, 2011 loading event was a "planned test of the Rando 200 for the purpose of complying with all applicable regulations," D. 44-3 ¶ 10; see also D. 44-1 at 2-3, and, therefore, should not give rise to liability. Even if the loading event is properly characterized as a "planned test," the regulatory scheme does not provide any exception for Tisbury Towing's compliance with the regulations in such circumstances. See 310 C.M.R. § 7.24(8)(e)(1). The regulatory obligation to demonstrate vapor tightness is on Tisbury Towing, see
b. Tisbury Towing Failed to Submit an Emissions Control Plan As Required (Claim 2)
Tisbury Towing failed to submit any Emissions Control Plan to the EPA and MassDEP until 2014 even when it is undisputed that it was required to do so by no later than October 8, 2000. D. 41-1 at 11-12, 24.
The parties agree that on June 17, 2014, Tisbury Towing finally submitted a draft emissions control plan to the EPA, which failed to comply with the minimum requirements of the Massachusetts SIP regulations. D. 41-2 ¶ 24; D. 44-3 ¶ 24. A revised draft was submitted on May 27, 2016, and was approved by MassDEP on April 7, 2017. D. 41-2 ¶ 26; D. 44-3 ¶ 26. Tisbury Towing's contention that it was "unaware of the requirement of an emissions control plan until Mr. Packer was advised by the EPA," D. 44-1 at 3, does not excuse the failure. See United States v. International Minerals & Chemical Corp.,
2. USA Is Entitled to Summary Judgment on the Clean Air Act Claims against R.M. Packer
a. R.M. Packer Failed to Operate in a Manner Consistent with Safety and Good Air Pollution Control Practices (Claim 1)
The USA contends that R.M. Packer is liable for failing to operate in a manner consistent with safety and good air pollution control practices. D. 45 at 13. Specifically, it argues that when the EPA inspected the Facility on June 10, 2013, its "equipment had fallen into disrepair and started leaking harmful emissions." D. 45 at 14. At the time, inspectors detected VOC vapors emitting from a pressure vacuum relief valve, which is connected to the Vapor Recovery Unit.
Steiner recommended R.M. Packer to first address the seal fluid glycol levels and then conduct a basic operating test. D. 44-20 at 7. "If performance was not acceptable, [Steiner] suggested R.M. Packer consider replacing the activated carbon and performing a field capacity test on the liquid ring vacuum pump," or in the alternative, completely replacing the liquid ring pump. D. 46-2 ¶ 17; D. 48-3 ¶ 17. The parties agree that Steiner's observations demonstrate the equipment was not properly maintained and that Steiner recommended R.M. Packer contract for quarterly maintenance. D. 46-2 ¶ 17; D. 48-3 ¶ 17. With this record as a backdrop, Ralph Packer, President of R.M. Packer, testified that R.M. Packer's emissions control equipment was not properly maintained. D. 46-2 ¶ 20; D. 48-3 ¶ 20; D. 44-3 at 22.
R.M. Packer, however, does dispute the USA's contention that it failed to take immediate and adequate action to repair and maintain its Vapor Recovery Unit. D. 46-2 ¶¶ 18, 23; D. 48-3 ¶¶ 18, 23. Although R.M. Packer replaced its pressure vacuum relief valves in either late 2014 or 2015, it is undisputed that the quarterly preventive maintenance recommended by Steiner and Timothy Levanduski was not implemented. D. 46-2 ¶ 22; D. 48-3 ¶ 22. Moreover, it is undisputed that R.M. Packer did not maintain adequate glycol levels and ceased inspecting the equipment and recording measurements as instructed by the Bryer Manual. D. 46-2 ¶¶ 24-25; D. 48-3 ¶¶ 24-25. It is also undisputed that it was not until June 26, 2015, that R.M. Packer's equipment had been sufficiently repaired indicating acceptable emissions of VOC. 46-2 ¶ 22; 48-3 ¶ 22.
Even if R.M. Packer's equipment did not leak more than 80 milligrams per liter, as this defendant contends, D. 48-1 at 5, it would still not absolve R.M. Packer of its liability for failure to maintain and operate its equipment properly. As 310 C.M.R. § 7.24(2)(a) makes clear, the requirement that "the amount of organic material released to the ambient air is less [than] 80 milligrams per liter of liquid loaded or unloaded" is only one of a series of a requirements that must be met before an operator of a bulk terminator can transfer "organic material with a vapor pressure of 1.5 psi or greater under actual storage conditions." That is, there is still sufficient evidence to determine that it was in violation of at least two of the other prerequisites, specifically that its Facility was not "equipped with a vapor collection and disposal system, which ... maintained and operated in accordance with the operating instructions of the manufacturer," see D. 46-2 ¶ 25, and that not all "vapor discharged during transfer of the organic material [was] collected and disposed of by the vapor collection and disposal system," see D. 46-2 ¶ 11; 310 C.M.R. §§ 7.24(2)(a), (1) and (2). Accordingly, the USA is entitled to summary judgment as to Claim 1 against R.M. Packer.
b. R.M. Packer Failed to Submit Required Notifications (Claims 2 and 3)
The Gasoline Distribution Air Standard (the "Standard") requires owners or operators of existing affected sources to submit an initial notification within 120 days of the effective date of the Standard,
c. R.M. Packer Failed to Conduct Monthly Leak Inspections and Maintain Records (Claim 4)
Pursuant to the Gasoline Distribution Air Standard, an owner or operator of a bulk gasoline terminal is required to conduct monthly leak inspections of all equipment in gasoline service.
Upon reviewing R.M. Packer's log book on June 10, 2013, the USA uncovered that "no inspections were logged - and presumptively did not occur - in April, May and June 2012 and January, February and March 2013." D. 45 at 21. R.M. Packer contends that its employees "inspected the equipment for leaks, most times on a daily basis, and filed reports for some of these inspections." D. 48-3 ¶ 28. The underlying record suggests otherwise as Doug Seward, a R.M. Packer employee, testified that monthly inspections ceased when a contractor of R.M. Packer, who had been responsible for conducting the monthly inspections, died and had not been replaced. D. 46-2 ¶ 28. Moreover, Seward testified, contrary to R.M. Packer's suggestion otherwise, that he ceased performing daily inspections "about a few years ago," prior to his 2016 retirement. D. 44-33 at 12. Even assuming that R.M. Packer's position about the occurrence of inspections was supported by the record, it admits that it did not keep a log book and that it performed the inspections "without the associated reporting for most of the applicable time."
d. R.M. Packer Failed to Collect and Dispose Discharged Vapor (Claim 5)
The USA contends that R.M. Packer is also liable for failing to collect and dispose of discharged vapor. D. 45 at 22. It argues that at the time of the EPA inspection on June 10, 2013, R.M. Packer's emissions control equipment released VOC vapors when it loaded gasoline into a tanker truck. D. 45 at 22. The Bulk Terminal Regulation requires that "each loading rack at the bulk terminal [be] equipped with a vapor collection and disposal system" and "any vapor discharged during transfer of the organic material [be] collected *78and disposed of by the vapor collection and disposal system." 310 C.M.R. §§ 7.24(2)(a)(1), (2). Additionally, "the amount of organic material released to the ambient air [must be] less than 80 milligrams per liter of liquid or unloaded over a six hour period" and any "transfer of organic material [must] take [ ] place through a submerged fill pipe."
e. R.M. Packer Failed to Maintain and Operate its Vapor Recovery Unit Properly (Claim 6)
The SIP requires that "each loading rack at the bulk terminal [must be] equipped with a vapor collection and disposal system, which has been installed and is maintained and operated in accordance with the operating instructions of the manufacturer." 310 C.M.R. § 7.24(2)(a)(1). Here, the installer of R.M. Packer's Vapor Recovery Unit, Bryer Enterprises, provided the operating instructions in its manual ("the Bryer Manual"). D. 46-2 ¶ 24; D. 48-3 ¶ 24. The Bryer Manual contains instructions on how to properly maintain and operate the Vapor Recovery Unit. D. 46-2 ¶¶ 24-25; D. 48-3 ¶¶ 24-25. Specifically, the Bryer Manual instructed and warned that the "[l]oss of glycol in the [vapor recovery unit] will damage the vacuum pump while a low glycol level will reduce the vacuum pump performance."
f. R.M. Packer Failed to Comply with the Testing Order (Claim 7)
Pursuant to its powers delegated under the Clean Air Act,
*79B. Clean Water Act Claims against R.M. Packer
The Clean Water Act is a comprehensive program enacted in 1972 intended "to restore and maintain the chemical, physical, and biological integrity of the Nation's waters" by decreasing and eventually eradicating the discharge of pollutants into those waters.
3. USA is entitled to Summary Judgment on its Clean Water Act Claims against R.M. Packer
a. R.M. Packer Failed to Perform Certain Monitoring, Inspections, Evaluations and Training (Claim 8)
The USA argues that R.M. Packer is liable for failing to perform required monitoring, inspections, evaluations and trainings. D. 45 at 8. It asserts that the "2008 MSGP required R.M. Packer to perform quarterly benchmark monitoring for each outfall at its Facility."
Here, it is undisputed that R.M. Packer failed to comply with any of these requirements. D. 46-2 ¶ 41; D. 48-3 ¶ 41. First, the parties agree that "R.M. Packer never performed quarterly visual inspections or benchmark monitoring of outfalls during the period coverage under the 2008 MSGP."
*8046-2 ¶ 42; D. 48-3 ¶ 42. In view of these undisputed facts, this Court allows summary judgment as to Claim 8.
b. R.M. Packer Failed to Minimize Discharges into Water (Claim 9)
Under the 2008 and 2015 MSGP, owners and operators are required to take "Good Housekeeping Measures" to limit the "potential for spent abrasives, paint chips, and overspray to discharge into receiving waters or the storm sewer systems" by taking "measures to minimize the discharge of containments "such as hanging plastic barriers or tarpaulins during blasting or painting operations to contain debris." 8.Q.3.1.2; 8.R.3.1.2. These sections also require owners and operators, when necessary, to "regularly clean stormwater conveyances of deposits of abrasive blasting debris and paint chips." 8.Q.3.1.2; 8.R.3.1.2. Additionally, under 2008 MSGP 8.R.4.3, owners and operators were required to document "any standard operating practices relating to blasting and painting" such as "prohibiting uncontained blasting and painting over open water or prohibiting blasting and painting during windy conditions, which can render containment ineffective." Moreover, Part 5.1.3.3 states that owners or operators were also required to "document where potential spills and leaks could occur that could contribute to pollutants to stormwater discharges, and the corresponding outfall(s) that would be affected by such spills and leaks... [and] all significant spills and leaks of hazardous pollutants that actually occurred at exposed areas, or drained to a stormwater conveyance."
Here, it is undisputed that when the EPA inspected the Facility on April 1, 2014, it observed paint chips as well as debris on the ground of its marine railway. D. 46-2 ¶ 43; D. 48-3 ¶ 43. It is undisputed that R.M. Packer failed to practice any of the abovementioned Good Housekeeping Measures to contain debris, in violation of the 2008 MSGP. D. 46-2 ¶ 43; D. 48-3 ¶ 43. In fact, Ralph Packer testified that R.M. Packer did not "implement or document measures to control blasting debris" prior to EPA's 2014 inspection. D. 46-2 ¶ 43; see D. 44-3 at 21. The record is devoid of any other measures R.M. Packer took to prevent or minimize the risk of abrasive and paint chips entering navigable waters, which was required under 2008 MSGP, see 2008 MSGP 8.R.3.1, and is required under 2015 MSGP, see 8.Q.3.1. Accordingly, the Court rules that the USA is entitled to summary judgment as to Claim 9.
c. R.M. Packer Failed to Modify its Storm Water Pollution Prevention Plan (Claim 10)
The USA also argues that R.M. Packer should be held liable for failing to have an adequate SWPPP. D. 45 at 26. Under Part 5 of the 2008 MSGP, R.M. Packer was required to implement a SWPPP; under Parts 4.1.1, 4.2.1, and 4.3.1, it must conduct inspections and, under Part 6 of the 2008 MSGP, it must conduct monitoring and sampling. Additionally, 2015 MSGP Part 6 requires that R.M. Packer submit an updated SWPPP. Similar to the 2008 MSGP, the 2015 MSGP requires inspections, monitoring and sampling, Parts 3.1, 3.2. Under the 2008 MSG, R.M. Packer was required to have a SWPPP that reflected the industrial activity and the locations of all stormwater inlets and outfalls and all locations where potential spills and leaks could occur that could contribute to pollution. 5.1.3.3. It is undisputed that R.M. Packer did not provide a complete copy of its 2002 SWPPP, the only one that it had during the period of coverage under the 2008 MSGP. D. 46-2 ¶¶ 44-45; D. 48-3 ¶¶ 44-45. In addition to being outdated, the parties agree that areas of the Facility, together with any description *81of their industrial activities, outfalls and pollution sources, were omitted in the 2002 SWPPP. D. 46-2 ¶ 46; D. 48-3 ¶ 46. Furthermore, it is undisputed that R.M. Packer should have, but did not, include the omitted information in its 2002 SWPPP. Because there is no genuine dispute of material fact as to this claim, this Court concludes that USA is entitled to summary judgment as to Claim 10.
d. R.M. Packer Failed to Comply with the Request for Information from the EPA (Claim 11)
The EPA is authorized under Section 308(a) of the Clean Air Act to request information pertaining to its stormwater practices.
VI. Conclusion
For the foregoing reasons, the Court ALLOWS USA's motion for a partial summary judgment against Tisbury Towing, D. 41, and ALLOWS USA's motion for partial summary judgment against R.M. Packer, D. 44.
So Ordered.
Related
Cite This Page — Counsel Stack
355 F. Supp. 3d 66, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-rm-packer-co-dcd-2018.