United States v. Raley Contracting Company

210 F. Supp. 54, 10 A.F.T.R.2d (RIA) 5565, 1962 U.S. Dist. LEXIS 4891
CourtDistrict Court, N.D. Mississippi
DecidedAugust 6, 1962
DocketE-C-13-61
StatusPublished
Cited by3 cases

This text of 210 F. Supp. 54 (United States v. Raley Contracting Company) is published on Counsel Stack Legal Research, covering District Court, N.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Raley Contracting Company, 210 F. Supp. 54, 10 A.F.T.R.2d (RIA) 5565, 1962 U.S. Dist. LEXIS 4891 (N.D. Miss. 1962).

Opinion

CLAYTON, District Judge.

This is a suit by the United States-instituted against Raley Contracting Company, incorporated 1 to collect taxes,, admittedly owing by W. L. Wells. Plaintiff attempts enforcement of a lien it. claims by reason of levies made against. Raley to subject to payment of said taxes debts plaintiff claims were payable byRaley to Wells. Against plaintiff’s claims the assertion is made that Raley owed Wells nothing at the time of the levies and has owed him nothing since. Facts necessary to disposition are without dispute.

Plaintiff’s first levy was made on Raley on February 25, 1959. A second levy was made on May 4, 1959, for $5,-128.44. This amount included the amount which was the subject of the first levy. If on either of the dates when the levies were made Raley owed Wells any amount then or since payable as of' right to Wells, plaintiff must prevail. *55 However, if Raley did not owe Wells anything on either of said dates and has since not owed Wells anything, then plaintiff’s suit must fail. This seems a concise but perhaps basic general statement of the underlying issues.

Wells was a subcontractor to Raley, which was the prime contractor, on six construction projects for public works being undertaken for public agencies. Raley had the contracts with the public agencies in its name, and Raley with the surety on its performance bond were responsible to the owners (the public agencies) for the completion of the work contemplated by the contracts in accordance with the plans and specifications therefor. Work on these projects was undertaken by Wells pursuant to separate contracts between Raley and Wells. Five of these projects were completed by Wells and accepted by the owner. (One of these projects was completed by Raley and his surety after Wells became hopelessly involved thereon, as will be mentioned later.) The five completed by Wells with pertinent dates are as follows :

PROJECT DATE OF PAYMENT TO RALEY WELLS’ PART
(Contract)
Lake Monroe May 2,1959 $1,211.63
Clay County December 8,1959 822.88
Pickens County (255) December 31,1959 2,674.56
Pickens County (898) February 12,1959 2,828.88
Pickens County (3241) February 12,1959 1,829.86

Under the contracts between Raley and Wells, payment was to be made by Raley to Wells of his part of final payments fifteen days after such payments were received by Raley. Thus, for example, the earliest final payment to Raley shown above, which was on February 12, 1959, would have required Raley to pay Wells his part no earlier than February 27, 1959. This date was the first date, with respect to the aforementioned four projects, upon which Wells could have demanded payment from Raley in .any event.

The sixth project for which the contract was taken in Raley’s name and on which Wells was the subcontractor, as aforementioned, was a rather large highway construction project undertaken for the State Highway Department of Mississippi in Simpson County. In December, 1958, Wells told Raley’s president that he could not continue with the Simpson County job unless defendant furnished him substantial amounts of money for payrolls and other expenses. In January, 1959, Wells again told defendant that he was through. In January, 1959, and again on February 24, 1959, defendant’s president visited the site of the Simpson County project to determine what yet remained to be done. As a result of these inspections, defendant estimated that it would cost it between forty and fifty thousand dollars, over and above remaining contract payments to be made by the owner, to complete the contract.

Nine days before the first of the final payments heretofore listed was received by defendant, Wells wrote defendant that he could not finish the Simpson County contract “unless you can advance me with weekly payrolls and haulage and some additional money with which to pay local bills”.

“I am sending you, under separate cover, a list of bills giving the amount and the parties to whom due, for labor, materials or supplies furnished on this project.”

On February 9, 1959, Wells sent the list of bills which totaled $11,291.46. *56 On February 11, 1959, Wells sent defendant another such bill amounting to $1,339.08.

The substance of the foregoing is that Wells told defendant that he would not undertake completion of the contract unless defendant advanced money to pay for labor, materials and supplies used by Wells therefor. At February 11, 1959, the known bills then amounted to $14,-058.19. And, it was then known, as a result of the notice given in December, 1958, by Wells to defendant and as a result of the January visit of defendant’s president to the project site that a great deal more money would be required to support completion of this contract. Thus, it is clear that no later than February 11, 1959, defendant knew that it would owe Wells nothing by reason of the forthcoming collections to be made on the five projects heretofore listed, but that, on the contrary, Wells would ultimately owe defendant a great deal more than the $5,326.83 which was afterward to be collected as Wells’ part on the four mentioned projects. Before the date of the first final payment on the four above listed projects (February 12, 1959) defendant and Wells both knew that there was only $11,557.43 retainage held on the Simpson County project by the Highway Department.

On March 13, 1959, defendant wrote Wells that defendant was taking over for completion the Simpson County project. On 1 June, 1959, defendant began working on this project and completed it, together with certain overrun (work over and above that specified by the contract). Completion of this project was effected at a loss to defendant and its surety on its performance bond therefor, far in excess of the amounts which were nominally payable to or creditable to Wells under the four projects which were completed by him.

Plaintiff cites five sections of the Internal Revenue Code 2 and one Treasury Regulation 3 . The claim is that Wells had a right to the four payments above listed as “Wells’ part” at the time of the levies or that such a right accrued to him thereafter. The cases of United States v. Graham, D.C., 96 F.Supp. 318 (1951); aff’d, State of California et al. v. United States (9 Cir. 1952), 195 F.2d 530; cert. denied, 344 U.S. 831, 73 S.Ct. 36, 97 L.Ed. 647 (1952) and Bank of Nevada v. United States (9 Cir. 1957), 251 F.2d 820, cert. denied, 356 U.S. 938, 78 S.Ct. 780, 2 L.Ed.2d 813 (1958) are cited as supporting plaintiff’s view that set off is not available against a claim for taxes due the United States.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bankers Trust Savings & Loan Ass'n v. Cooley
362 F. Supp. 328 (N.D. Mississippi, 1973)
United States v. Akron Mechanical Contractors, Inc.
308 F. Supp. 496 (D. Maryland, 1970)
Monroe Banking & Trust Company v. Allen
286 F. Supp. 201 (N.D. Mississippi, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
210 F. Supp. 54, 10 A.F.T.R.2d (RIA) 5565, 1962 U.S. Dist. LEXIS 4891, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-raley-contracting-company-msnd-1962.