United States v. Plummer Excavating, Inc.

65 F. Supp. 2d 1013, 1999 U.S. Dist. LEXIS 14059, 1999 WL 701365
CourtDistrict Court, D. Minnesota
DecidedSeptember 3, 1999
DocketCriminal 99-121(2)(JRT/FLN)
StatusPublished

This text of 65 F. Supp. 2d 1013 (United States v. Plummer Excavating, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Plummer Excavating, Inc., 65 F. Supp. 2d 1013, 1999 U.S. Dist. LEXIS 14059, 1999 WL 701365 (mnd 1999).

Opinion

ORDER ADOPTING REPORT AND RECOMMENDATION ON DEFENDANT’S MOTION TO DISMISS INDICTMENT

TUNHEIM, District Judge.

This matter is before the Court upon the Government’s objections to the Report and Recommendation of Chief United States Magistrate Judge Franklin L. Noel filed June 25, 1999. The Magistrate Judge recommends that defendant Plummer Excavating, Inc.’s motion to dismiss Count I of the indictment be granted, and that defendant’s motion to dismiss Count II of the indictment be denied. The Government objects to the recommendation that Count I be dismissed. The Court has conducted a de novo review of the Report and Recommendation on this matter pursuant to 28 U.S.C. § 636(b)(1)(C) and D.Minn. LR 72.1(c)(2).

I. FACTS

The following facts are taken from the Magistrate Judge’s Findings of Fact, to which no party has objected and which the Court adopts.

The United States Secretary of Transportation requires that each state adopt a system, known as the “one-call system,” whereby pipeline operators may be alerted to potentially damaging activity in the vicinity of a pipeline via a single telephone call. Parties intending to engage in potentially damaging activity are required to make a telephone call to an assigned number to determine whether underground pipeline is present.

Defendant Plummer Excavating Inc. is an excavation company located in Plum-mer, Minnesota. Co-defendant Randy Lee Konickson is one of its Vice Presidents. On or about September 11, 1998, Konick-son directed a Plummer Excavating employee to remove piles of rocks on a field adjacent to Plummer Excavating. At the time he gave this instruction, Konickson knew that the employee would dig in the field to bury large rocks. Konickson also *1015 knew that there was a crude oil pipeline in the field and was familiar with the one-call system. Nevertheless, Konickson did not call the assigned number.

At approximately 9:00 a.m. on September 16, 1998, the Plummer Excavating employee struck and damaged the crude oil pipeline with his backhoe. The employee told Konickson about the accident, but Konickson failed to inform anyone at Lakehead Pipeline Company, the owner of the pipeline. Later that day, at approximately 8:45 p.m., Lakehead employees discovered crude oil leaking from the pipeline where it had been damaged. The leak and accompanying noxious fumes forced the evacuation of Plummer, Minnesota. The total amount of crude oil that eventually leaked from the pipeline was approximately 5,700 barrels, or 240,000 gallons. The oil spread through agricultural drainage ditches to County Ditch No. 22, which connects to the Clearwater River through County Ditch No. 57.

II. ANALYSIS

A. Count I

Count I charges defendants with violating 49 U.S.C. § 60128(d), which states:

(d) Penalty for not using one-call notification system or not heeding location information or markings. — A person shall be fined under title 18, imprisoned for not more than 5 years, or both, if the person knowingly and willfully—
(1) engages in an excavation activity—
(A) without first using an available one-call notification system to establish the location of underground facilities in the excavation area; or
(B) without paying attention to appropriate location information or markings the operator of a pipeline facility establishes; and
(2) subsequently damages—
(A) a pipeline facility that results in death, serious bodily harm, or actual damage to property of more than $50,-000;
(B) a pipeline facility that does not report the damage promptly to the operator of the pipeline facility and to other appropriate authorities; or
(C) a hazardous liquid pipeline facility that results in the release of more than 50 barrels of product.

49 U.S.C. § 60128(d). Defendant argues that the “knowingly and willfully” level of scienter applies to the “subsequently damages” element, and the Government argues that it does not. Both parties agree that if the knowing and willful level of scienter applies to the subsequently damages element, Count I must be dismissed because the Government has not alleged that defendant intentionally damaged the pipeline.

The interpretation of a statute begins with the plain meaning of its words. See United States v. Smith, 171 F.3d 617, 620 (8th Cir.1999). Courts resort to legislative history and other sources to guide their interpretation only if the meaning of the statute is ambiguous. See id.

The Court agrees with the Magistrate Judge that a plain reading of the statute establishes that the knowing and willful scienter requirement applies to the subsequently damages element. As the Magistrate Judge explained, the placement of the scienter requirement prior to the subdivision of the section into subparts 1 and 2 indicates that the scienter requirement must be read with both subparts. Because a plain reading of the statute unambiguously indicates that the scienter requirement applies to the subsequently damages element, resort to the statute’s legislative history is not necessary. See Smith, 171 F.3d at 620.

The Government and amici argue that the Court should nevertheless examine the legislative history for several reasons. First, they argue that the plain meaning of § 60123(d) is at odds with the clear Congressional purpose of the statute, and that the language of a statute is not conclusive if there is a “ ‘clearly expressed legislative *1016 intent to the contrary.’ ” Reves v. Ernst & Young, 507 U.S. 170, 177, 113 S.Ct. 1163, 122 L.Ed.2d 525 (1993) (quoting United States v. Turkette, 452 U.S. 576, 580, 101 S.Ct. 2524, 69 L.Ed.2d 246 (1981)). The Court acknowledges that the purpose of § 60123(d) is to encourage compliance with the one-call system and thereby prevent damage to pipelines, and that applying the knowing and willful scienter requirement to both elements of the crime restricts the application of the statute. The words of the statute do not purport to accomplish the opposite of what the Government argues was Congress’s intent, however. Instead, Congress enacted a version of the statute whose scope is limited in comparison to what the legislative history would suggest.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Bass
404 U.S. 336 (Supreme Court, 1971)
United States v. Batchelder
442 U.S. 114 (Supreme Court, 1979)
United States v. Turkette
452 U.S. 576 (Supreme Court, 1981)
Freytag v. Commissioner
501 U.S. 868 (Supreme Court, 1991)
Reves v. Ernst & Young
507 U.S. 170 (Supreme Court, 1993)
United States v. Dale Marvin Warren
149 F.3d 825 (Eighth Circuit, 1998)
United States v. William Maurice Smith
171 F.3d 617 (Eighth Circuit, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
65 F. Supp. 2d 1013, 1999 U.S. Dist. LEXIS 14059, 1999 WL 701365, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-plummer-excavating-inc-mnd-1999.