United States v. New York Central Railroad Co.

252 F. Supp. 508, 1965 U.S. Dist. LEXIS 6920
CourtDistrict Court, D. Massachusetts
DecidedNovember 9, 1965
Docket63-72
StatusPublished
Cited by7 cases

This text of 252 F. Supp. 508 (United States v. New York Central Railroad Co.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. New York Central Railroad Co., 252 F. Supp. 508, 1965 U.S. Dist. LEXIS 6920 (D. Mass. 1965).

Opinion

FRANCIS J. W. FORD, District Judge.

In this action the United States seeks to recover from defendant railroads 1 the cost of removal by the United States of an alleged obstruction to the navigable waters of the Chelsea River.

Under authorization of the Secretary of War given on March 8, 1917 defendants constructed, maintained and operated a drawbridge across the Chelsea River, a navigable waterway lying between Chelsea and East Boston. This river was in active use by vessels, particularly for the passage of tankers carrying petroleum products to storage facilities located on the banks of the river.

The bridge as constructed in accordance with the 1917 authorization afforded a channel for passage of vessels with a horizontal clearance of 70 feet. Around 1945 the oil companies and other shipping interests began to complain that a wider channel was needed to accommodate the larger tankers which were being used for the transportation of oil. There were also complaints that the bridge was constructed so as to have a maximum opening angle of 83 degrees, and in actual operation was opened only to an angle of 76 degrees. As a result empty tankers had to take on ballast and move on low water so as to clear the upraised span of the bridge.

After hearing on these complaints the Corps of Engineers on April 25, 1949 notified the Boston and Albany Railroad that the draw should be widened to provide a horizontal clearance of 150 feet. This notice appears to have been in the form of a recommendation rather than *510 an order. The recommendation was never accepted by the railroads, although steps were taken toward action for rebuilding the bridge under the provisions of the Truman-Hobbs Act, 33 U.S.C.A. §§ 511-524, under which the government would have paid part of the cost of the work.

Before any final action under this act, the bridge collapsed on February 28,1955. An undetected crack in the southwest channel of the vertical tower imposed strain on the remaining metal, causing the counterweight to fall and damaging the span of the bridge. The wreckage from this accident was removed at the expense of the railroad so as to clear the existing 70 foot channel.

However, there remained portions of the bridge structure including piers, trestles and fenders which still limited the use of the river to the 70 foot channel. Moreover, there were complaints that the fenders were in a deteriorated condition which caused additional danger of injury to tankers which might scrape against them.

The railroads made arrangements to move their traffic over the lines of another railroad and on October 17, 1956 on petition of the railroads the Interstate Commerce Commission issued a certificate permitting abandonment of the bridge by the Boston and Albany and abandonment of operation of the bridge by the New York Central.

On May 19, 1959 the Corps of Engineers denied the railroads’ request that removal of the bridge structure be made under the Truman-Hobbs Act 2 and ordered the railroad to remove certain portions of the hulk of the bridge with accompanying piers, trestles and fenders, which were deemed to obstruct navigation unreasonably. The railroad did not comply with this order but requested a hearing on the matter under the Truman-Hobbs Act. This request was denied.

On April 1, 1960, however, the Corps of Engineers held a public hearing on the question of the removal of the remnants of the bridge. Thereafter on April 28, 1960 the Secretary of the Army ordered the railroads to remove certain portions of the bridge, said work of removal to be commenced within 30 days. The railroads did nothing to comply with this order. On June 17, 1960 the Corps of Engineers notified the Boston and Albany that the bridge remains would be removed by the United States, with reservation of all rights of the United States to recover from the railroads the expense of removal. Thereafter the bridge was removed by a contractor under contract with the United States at a cost to the United States of $214,746.40 and the United States in this action seeks to recover this expense from the railroads.

The uncontradicted evidence by four experts presented by plaintiff proved that the remains of the bridge removed by the United States constituted an unreasonable obstruction to navigation of the Chelsea River. The 70 foot existing channel in the river provided a barely adequate passage to the 68 foot tankers in use in the oil industry. The fenders along the abutments of the bridge had been allowed to deteriorate, leaving exposed bolts which could be avoided with difficulty, and the danger of sparks setting fire to a tanker which scraped these bolts created a serious fire hazard for tankers using the river. Moreover, the increasing use of larger tankers in the industry made the 70 foot channel inadequate to serve the needs of navigation and prevented adequate use of the full available navigable width of the rivers.

The difficulty in this case arises from the fact that there is no statutory provision explicitly authorizing the United States to remove an obstruction to navigation and then recover the expense of removal from the parties respon *511 sible. The railroads contend that the only-remedy. available to the United States in the present situation was a criminal prosecution of the railroads for failure to comply with an order of the Secretary of the Army directing removal or alteration of the bridge. 33 U.S.C.A. §§ 495, 502. The statute can no longer be so narrowly interpreted. In United States v. Republic Steel Corp., 362 U.S. 482, 80 S.Ct. 884, 4 L.Ed.2d 903, the Supreme Court gave a broad interpretation to § 10 of the Rivers and Harbors Act of 1899, 33 U.S.C.A. § 403, holding that obstruction to navigation was not limited to the structures specifically enumerated therein but included diminution of the navigable capacity of a waterway by other means. It further upheld the granting of an injunction enjoining respondents from depositing industrial solids in the Calumet River and ordering them to remove existing deposits to restore the depth of the channel to 21 feet, on the ground that while the Act did not specifically authorize the bringing of a suit for an injunction in such a case, Congress had in § 403 defined the purpose and interest of the United States in maintaining the navigable capacity of waterways and the courts could fashion appropriate remedies to fit contingencies not specifically provided for.

In United States v. Perma Paving Co., Inc., 2 Cir., 332 F.2d 754, the defendant had placed fill on property on the bank of the Bronx River, which caused a mud wave which produced shoaling in the river which interfered with navigation. In reliance on the Republic Steel case, supra, it was held that where the United States had dredged the river it was entitled to recover its expense from those responsible for causing the obstruction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
252 F. Supp. 508, 1965 U.S. Dist. LEXIS 6920, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-new-york-central-railroad-co-mad-1965.