United States v. National Steel Corporation

767 F.2d 1176
CourtCourt of Appeals for the Sixth Circuit
DecidedJuly 26, 1985
Docket83-1600
StatusPublished

This text of 767 F.2d 1176 (United States v. National Steel Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. National Steel Corporation, 767 F.2d 1176 (6th Cir. 1985).

Opinion

767 F.2d 1176

22 ERC 2250, 15 Envtl. L. Rep. 20,678

UNITED STATES of America, Plaintiff-Appellee,
and
Wayne County Department of Health, Air Pollution Control
Division, and Frank J. Kelley, Attorney General For the
State of Michigan, Frank J. Kelley ex. rel. Michigan Natural
Resources Commission, Michigan Air Pollution Control
Commission and Howard A. Tanner, Director of the Michigan
Department of Natural Resources, Natural Resources Defense
Council, Dennis Piper, Intervenors-Appellees,
v.
NATIONAL STEEL CORPORATION, Defendant-Appellant.

No. 83-1600.

United States Court of Appeals,
Sixth Circuit.

Argued Aug. 21, 1984.
Decided July 26, 1985.

Douglas H. West, Hill, Lewis, Adams, Goodrich & Tait, Detroit, Mich., Clyde W. Armstrong, Kevin Abbott, Chester R. Babst, III (argued), Dean A. Calland, Preston T. Scott, Thorp, Reed and Armstrong, Washington, D.C., for defendant-appellant.

Dennis Piper, Robert H. Abrams, Natural Resources Defense Counsel, Ann Arbor, Mich., John Barker (argued), George Lawrence, Environmental Enforcement Service, Washington, D.C., Francis L. Zebot, Asst. U.S. Atty., Detroit, Mich., Peter Veeder, Thorp, Reed & Armstrong, Pittsburgh, Pa., Stuart Freeman, Asst. Atty. Gen., Environmental Protection Div., Lansing, Mich., William C. Achinger, Steven E. Chester, Joseph B. Klein, Wayne County Dept. of Health, Air Pollution Control Div., Detroit, Mich., Peter J. Kelly, U.S. E.P.A., Chicago, Ill., Michael Alushin, Andrew M. Jackson, Office of Gen. Counsel, U.S. E.P.A., Washington, D.C., David G. Hawkins (argued), Natural Resources Defense Council, Washington, D.C., Stephen Schuesler (argued), Asst. Atty. Gen., L. Caruso, Lansing, Mich., for intervenors-appellees.

Before ENGEL and MERRITT, Circuit Judges, and WISEMAN, District Judge.*

ENGEL, Circuit Judge.

National Steel Corporation (National) appeals from an order of the United States District Court for the Eastern District of Michigan which required National to pay penalties in excess of $5 million for violating a consent decree entered into between National, the United States, and various intervenors in settlement of an air pollution action brought by the United States against National. National appeals from the order. We affirm in part, reverse in part, and remand for modification of the final order consistent with this opinion.

On August 14, 1979, the United States filed a complaint against National pursuant to section 113(b) of the Federal Clean Air Act, 42 U.S.C. Sec. 7413(b), alleging that several facilities at National's Great Lakes Steel Plant, located near Detroit, were not in compliance with certain emission limitation requirements promulgated by the State of Michigan pursuant to the Clean Air Act. The parties entered into an extensive consent decree which settled all of the issues raised in the complaint. The district court approved the consent decree on March 31, 1981.

In April of 1983, the United States filed a motion in the district court alleging that National had violated the consent decree. The district court agreed and found National liable for the penalties stipulated therein. National appeals from the district court's order contending that the imposition of penalties violated the due process clause of the Fifth Amendment and the terms of the consent decree. In addition, National contends that the district court failed to limit the scope of the stipulated penalties as required under Paragraph V.C.3 of the decree.

I.

The consent decree required National to meet specific emission limitations at various facilities at the Great Lakes Steel Plant in accordance with stated compliance schedules. National agreed to install pollution abatement equipment on its No. 2 Basic Oxygen Furnace according to the following schedule:

(a) December 15, 1980 Issue purchase orders

(b) August 31, 1981 Start construction

(c) August 15, 1982 Complete installation of hooding and control device

(d) November 15, 1982 Achieve and demonstrate compliance with the emission limitations specified in Paragraphs VII A 1 and 2

The consent decree set forth stipulated amounts to be paid by National for failing to meet the construction schedule. Paragraph V.A.1 provided for a $1,000 per day penalty for the first ten days that an interim date in the construction schedule was not met, $2,000 per day for the next ten days, $3,500 per day for the next ten days, and $5,000 per day thereafter. Paragraph V.A.2 provided that if National fails to meet a final date in a schedule for the construction or installation of pollution control equipment on a facility, "it shall be liable for a stipulated amount of $7,500 per day for each facility for each day such failure continues. Any stipulated liability under this subparagraph will be subsequently forgiven if [National] meets the emission limitations by the attainment date set forth in the schedule."

Paragraph V.B dealt with compliance with emission limitations and provided that if National should fail to meet the final attainment date set forth in a schedule for meeting emission limitations, "[National] shall pay a stipulated amount of $7,500 per day for each day [National] operates the facility without a demonstration that it meets the applicable emission limitations...." Paragraph V.C stated important limitations on the amount of stipulated penalties National would have to pay. Paragraph V.C provided in relevant part:

C. Exclusions:

* * *

2. [National] shall not pay stipulated amounts for failure to meet emission limitations at a facility if it is paying stipulated amounts for failure to meet construction or installation schedules at the same facility.

3. If [National] fails to demonstrate compliance with an applicable emission limitation its obligation to pay under this paragraph shall cease 180 days after the effective date of the limitation.

Paragraph V.D provided that the "provisions of Part B paragraph V ..., including the exclusions in paragraph V C 1 and 2 above shall not be construed to limit any other remedies available to Plaintiff for violation of this Decree or of other provisions of law." The consent decree permitted National to seek an alternate emission reduction option for any facility covered by the decree, but required that the option be sought "in compliance with the Clean Air Act, State law and County law." The decree stated "that an application for such an option shall not be grounds for delaying the requirements of this Decree."

National sought one type of alternate emission reduction option that is popularly referred to as a "bubble." A bubble is an air pollution control concept that looks at a group of pollution-emitting sources and the group's emissions as a whole rather than focusing on each individual emission source. Under a bubble, an emission limit for one pollution source is relaxed, while a limit for another source is made more stringent, so that the resulting pollution from the two sources remains the same.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
767 F.2d 1176, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-national-steel-corporation-ca6-1985.