United States v. Murdock Machine

Court of Appeals for the Tenth Circuit·Decided April 3, 1996·No. 95-4071·Published

Opinion

PUBLISH

UNITED STATES COURT OF APPEALS Filed 4/3/96 TENTH CIRCUIT

UNITED STATES OF AMERICA, )

)

Appellant, )

)

vs. )

) No. 95-4071 MURDOCK MACHINE AND ) ENGINEERING COMPANY OF UTAH, ) LOGAN A. BAGLEY, Trustee for Murdock ) Machine and Engineering Company of Utah, )

)

Appellees. )

APPEAL FROM THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF UTAH

(D.C. No. 93-C-0918-S)

Richard P. Nockett, Attorney, Civil Division, Commercial Litigation Branch, United States Department of Justice, Washington, D.C., for Appellant.

Robert H. Koehler, of Patton Boggs, L.L.P., Washington, D.C. (James B. Lee, Craig B. Terry, E. Russell Vetter, of Parsons, Behle & Latimer, Salt Lake City, Utah, with him on the brief), for Appellee.

Before BALDOCK, McWILLIAMS, and KELLY, Circuit Judges.

BALDOCK, Circuit Judge.

Cases governed by the Bankruptcy Act of 1898, 11 U.S.C. §§ 1-1103 (1976)

(repealed) (“the Act”) and the former Bankruptcy Rules, 11 U.S.C. appx. (1976)

(superseded in 1983), are, like cowboys, a vanishing breed. We deliver in this case one of the final parting shots under the Act and former Rules.1 We hold that in proceedings under Chapter VII of the Act, the United States government enjoys sovereign immunity from the automatic stays imposed by former Rules 401 and 601 because Congress did not waive the government’s sovereign immunity in the Act. Accordingly, we reverse the decision of the district court and remand.

I. Background

A. Contract Awards & Terminations In June 1971, the government awarded Murdock Machine and Engineering Company of Utah (“Murdock”) a multi-year, $10.6 million, fixed-price contract to supply antisubmarine rocket launchers (“ASROC launchers”) to the Department of the Navy (“the ASROC contract”). Murdock did not timely produce the ASROC launchers,

1 The Bankruptcy Act of 1898 applies to the instant case because Murdock filed its Chapter VII petition in 1975, prior to the effective date of the current Bankruptcy Code. United States v. Bagley (In re Murdock Mach. & Eng’g Co.), 990 F.2d 567, 569 n.1 (10th Cir. 1993); see also Bankruptcy Reform Act of 1978, Pub. L. No. 95-598, § 403(a), 92 Stat. 2549, 2683 (providing that prior law and procedures apply to cases initiated before October 1, 1979). By an April 25, 1983 Order, 11 U.S.C. Index, XIII, the Supreme Court provided that the current Bankruptcy Rules would take effect and supersede the former Rules on August 1, 1983 and that the current Rules “shall be applicable to proceedings then pending, except to the extent . . . their application . . . would not be feasible or would work injustice, in which event the former procedure applies.” We apply Former Bankruptcy Rules 401 and 601 in the instant case because they supplied the automatic stays which the government allegedly violated. Hence, they are the Rules pertinent to the instant case. Unless otherwise noted, references hereinafter will be to the Bankruptcy Act of 1898 (“the Act”) and to the former Rules of Bankruptcy Procedure (“Rule ___”).

however, due to financial and production problems. Concerned with the production delay, the Navy Procuring Command (“NPC”) and Naval Sea Systems Command (“NAVSEA”) met with Murdock, and agreed to provide Murdock a $2.5 million government-guaranteed loan from the Commercial Security Bank of Ogden, Utah (“Murdock’s Bank”). NAVSEA also assured Murdock that it could apply for additional financial assistance under the extraordinary contractual relief provisions of Public Law No. 85-804, 50 U.S.C. §§ 1431-36 (“P.L. 85-804") if the $2.5 million guaranteed loan proved to be insufficient. See 50 U.S.C. §§ 1431-36 (granting agency head authority to provide extraordinary relief to a contractor when a contract is deemed essential to the national defense).

The government then awarded Murdock five additional fixed-price contracts--the contracts at issue in this appeal--including an: (1) Army contract for supply of Rocket fin and nozzle assemblies; (2) Army contract for construction of delay plungers; (3) Air Force contract for construction of practice bombs; (4) Navy contract for construction of Zuni launchers; and (5) Navy contract for construction of A/B dispensers (hereinafter collectively referred to as “the Non-ASROC contracts”). Each contract contained a standard “default” clause and “disputes” clause. See 48 C.F.R. §§ 52,249-8, 52,249-2. The default clause provided that if the government’s default termination was proper, the government could recover from the contractor its excess costs of reprocurement, unliquidated progress payments, and other damages. The default clause provided further,

however, that if the government’s default termination was improper, (e.g., if the contractor’s default was excusable because it was beyond its control), the government would not be entitled to recover the above and, in turn, the government could potentially be liable to the contractor under the “termination for convenience” clauses of the Non-ASROC contracts.2 The disputes clause provided that:

(A) Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer. . . . The decision of the Contracting Officer shall be final and conclusive unless, within thirty days from the date of receipt of such copy, the Contractor mails or otherwise furnishes to the Contracting Officer a written appeal addressed to the Secretary [or his duly authorized representative--the Armed Services Board of Contract Appeals (“ASBCA”)].

With the funds from the guaranteed loan, Murdock continued performance on the ASROC contract and began performance on the Non-ASROC contracts. Murdock again encountered financial and production problems, and in August 1974 submitted a Request for Extraordinary Contractual Relief under P.L. 85-804. In its Request, Murdock explained that its total probable completion costs for the ASROC contract would be $20 million and asked the Navy to convert the $10.6 million fixed-price ASROC contract into

2 Under the standard termination for convenience clauses of government contracts, convenience terminations permit the contractor to claim its incurred and allowed costs from the government, against which the government recoups its contract financing (loans and progress payments). See Dewey Elec. Corp., ASBCA No. 33,869, 91-1 BCA ¶ 23,433 (1990).

a cost-reimbursement contract with a $22 million ceiling.3 NAVSEA recommended that the Navy Contract Adjustment Board (“NCAB”) grant Murdock P.L. 85-804 relief.4 In April 1975, NCAB granted Murdock P.L. 85-804 relief and converted the ASROC contract to a cost-reimbursement contract with a $22 million ceiling.

Thereafter, NAVSEA learned that it could obtain ASROC launchers from another source. NAVSEA immediately informed Murdock and NCAB that it was withdrawing its recommendation for P.L. 85-804 relief. The Navy then informed Murdock that it would not convert the ASROC contract to a cost-reimbursement contract and that Murdock had ten days to cure its delinquent ASROC delivery schedule or face default termination. Murdock apparently did not cure, and on May 16, 1975, a Navy contract officer terminated the ASROC contract for default. The Navy authorized Murdock’s bank to call the guaranteed loan, and cut off progress payments to Murdock.

Seven days after the Navy terminated the ASROC contract, on May 23, 1975, Murdock filed a voluntary petition for relief under Chapter VII of the Act in the District

3 Under a fixed-price contract, the contractor cannot bill the government for additional costs. In contrast, under a cost-reimbursement contract, the contractor can bill the government for additional production costs, subject to the ceiling imposed.

4 The NCAB is an administrative board designated by the Secretary of the Navy to rule on P.L. 85-804 requests.

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. Murdock Machine, (10th Cir. 1996).

United States v. Murdock Machine (United States v. Murdock Machine) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Decatur v. Paulding
39 U.S. 497 (Supreme Court, 1840)
Hill v. the United States
50 U.S. 386 (Supreme Court, 1850)
Carr v. United States
98 U.S. 433 (Supreme Court, 1879)
United States v. Thompson
98 U.S. 486 (Supreme Court, 1879)
Belknap v. Schild
161 U.S. 10 (Supreme Court, 1896)
Naganab v. Hitchcock
202 U.S. 473 (Supreme Court, 1906)
Minnesota v. United States
305 U.S. 382 (Supreme Court, 1939)
United States v. Shaw
309 U.S. 495 (Supreme Court, 1940)
United States v. Summerlin
310 U.S. 414 (Supreme Court, 1940)
United States v. Sherwood
312 U.S. 584 (Supreme Court, 1941)
United States v. N. Y. Rayon Importing Co.
329 U.S. 654 (Supreme Court, 1947)
Larson v. Domestic and Foreign Commerce Corp.
337 U.S. 682 (Supreme Court, 1949)
Hatahley v. United States
351 U.S. 173 (Supreme Court, 1956)
Crown Coat Front Co. v. United States
386 U.S. 503 (Supreme Court, 1967)
Bradley v. School Bd. of Richmond
416 U.S. 696 (Supreme Court, 1974)
United States v. Testan
424 U.S. 392 (Supreme Court, 1976)
United States v. Mitchell
463 U.S. 206 (Supreme Court, 1983)
Granfinanciera, S.A. v. Nordberg
492 U.S. 33 (Supreme Court, 1989)