UNITED STATES DISTRICT COURT DISTRICT OF MASSACHUSETTS

CIVIL ACTION NO. 85-489-RGS

UNITED STATES OF AMERICA

v.

METROPOLITAN DISTRICT COMMISSION, et al.

CIVIL ACTION NO. 83-1614-RGS

CONSERVATION LAW FOUNDATION OF NEW ENGLAND, INC.

METROPOLITAN DISTRICT COMMISSION

SCHEDULE SEVEN COMPLIANCE ORDER NUMBER 249 July 23, 2021 STEARNS, D.J. On June 25, 2021, the Massachusetts Water Resources Authority (MWRA) filed its Biannual Compliance and Progress Report (the 249th such report over the course of this decades-old litigation). With the Report, the MWRA filed a copy of the Semiannual CSO (Combined Sewer Overflow) Discharge Report No. 6, July 1, 2020 – December 31, 2020, which issued on April 30, 2021. The Conservation Law Foundation and the United States have offered no comments on the Report. There were no scheduled activities during the past six-month period on the court’s Schedule 7.

As the court noted in its previous Report, the performance assessment (the last of the contemplated Milestones) has proven an invaluable tool in assessing both the strengths and shortcomings of the implementation of the Long-Term Combined Sewer Control Plan (LTCP). On July 19, 2019, acting

on a joint motion of the MWRA, the United States Environmental Protection Agency (EPA), and the Massachusetts Department of Environmental Protection (DEP), the court approved an agreement extending the

performance assessment completion date one year to December 31, 2021.1 The extension allowed time for the MWRA, among other tasks, to conduct receiving water quality modelings distinguishing the environmental impacts of CSO sources from non-CSO sources on the affected waters.2 In its July 16,

2020 Compliance Order, the court observed that the data gathered since the modeling improvements had been of particular assistance in identifying

1 As part of the Agreement, the EPA and the DEP granted the MWRA’s request to extend existing water quality variances affecting the Lower Charles River/Charles River Basin and Alewife Brook/Upper Mystic River to August 31, 2024.

2 In its current Report, the MWRA appropriately notes that the court mistakenly identified this aspect of the parties’ agreement as based on a recalibration of the MWRA’s hydraulic assessment model in its January 3, 2021 Compliance Order. See June 25, 2021 Report at 12 n.2. regulators and outfalls where CSO activity was exceeding the desired levels. Nonetheless, because the process was ongoing, and the data to that point

were inconclusive, the court was unable to then make any definitive evaluation. In its June 25 Report, the MWRA concludes that it can now make an informed assessment of those outfalls that it expects to be in full compliance

with LTCP targets by the current December 31, 2021 deadline;3 those that can be brought into compliance by the date that the current variances expire (August 31, 2024); and those that, barring some unexpected technical

breakthrough, will not meet the LTCP activation or volume goals, and for which the costs of achieving 100% compliance may not be justified by the resulting benefit.4 Within the first and largest category are the 70 outfalls that will be in

full compliance with the LTCP by the December 31, 2021 performance assessment deadline. Of those, 35 of the 70 have been closed permanently. Five of the remaining outfalls are along the beaches in South Boston. The

3 As previously noted, the original Milestone anticipated a final performance assessment completion date of December 31, 2020.

4 The MWRA’s tentative conclusion did not come as a surprise as a preliminary forecast of the assessment data had been presented to the court at the status conference held with the parties on April 2, 2021. superior performance of the CSO storage tunnel gives assurance that the goal of preventing CSO discharges up to the 25-year storm standard has been or

will be achieved at these sites. The second category consists of six outfalls that are currently out of compliance but that, with additional improvements, can be brought to the desired performance standard. The six in the order they appear in Table 1-5

of Semiannual CSO Report No. 6 are: (1) SOM007A/MWR205A on the Upper Mystic River; (2) MWR205 on the Mystic River; (3) BOS014 on Chelsea Creek; (4) CHE008 on Chelsea Creek; (5) BOS009 on the Upper

Inner Harbor; and (6) BOS003 on the Lower Inner Harbor. See Dkt #1889- 1 at 17-18. The remedial measures to be undertaken with respect to these six outlets include: (1) the installation of a second interceptor connection to regulate CSO overflows (MWR205 and SOM700A/MWR205A); (2) MWRA

financial assistance to the Boston Water & Sewer Commission in the amount of approximately $2.2 million (approved by the MWRA Board of Directors on April 14, 2021) to permit upgrades of outfalls BOS003, BOS009, and BOS014; and (3) an enlargement of the interceptor connection at CHE008

from the present diameter of 30 inches to 48 inches. These measures the MWRA is confident will bring these six outlets into full compliance by the end of 2024 at the very latest. See Table 3-3. The third category consists of the ten outfalls for which full compliance will not be achieved by the variance expiration date of August 31, 2024, or

the proposed new Milestone date, December 21, 2024. These include outfall MWR201 at the College Farm Facility, four outfalls on the Charles River, MWR 018, 019, o2o, and CAM oo5 (clustered on the Lower Charles), SOM001A at Alewife Brook, BOSo17 in Charlestown at the Mystic/Chelsea

Confluence, and three outfalls on the Fort Point Channel, BOS062, 065, and 070. See Table 3-4. As for these ten, any conclusive determination would be premature. As stated in the most recent Report,

[f]or these 10 outfalls, the Authority, in coordination with the CSO communities, continues to evaluate hydraulic conditions contributing to the higher CSO discharges, and identify and model CSO reduction alternatives. Based on the results to date, the Authority is currently focusing its evaluations on the types of measures identified for each outfall in Exhibit C (Table 1-6 in Semiannual Progress Report No. 6). The Authority will present its further progress with these evaluations in Semiannual Progress Report No. 7, due October 31, 2021.

Report at 9-10. Consequently, the court will defer judgment with respect to these ten outfalls until a more complete picture can be assembled. The court understands that among the options under consideration by the parties is a request to the court to extend the December 2021 Milestone to August 31, 2024, or possibly December 31, 2024. Whether the extension request would involve the LTCP as a whole or only the sixteen “problem” outfalls appears an open question. The MWRA reports that it will continue discussions with the EPA, the DEP and the CLF, and intends to bring the

interested watershed associations to the table as well.5 The goal is to reach an agreement so that the parties can, by September 2021, jointly “advise the court of a framework to bring the case to successful completion.” Report at 3. The court would welcome any such proposal from the parties and the

interested watershed groups. Turning to other topics, the MWRA reports continued progress with the capital improvements undertaken by the CSO communities. Among

them are the BWSC’s construction of the first of five sewer separation projects in South Boston, the City of Somerville’s ongoing construction of a new storm drain at Union Square, the City of Cambridge’s planning of new sewage separation projects, and the City of Chelsea’s implementation of the

first phase of its Citywide Sewer Separation Master Plan.

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. M.D.C., (D. Mass. 2021).

United States v. M.D.C. (United States v. M.D.C.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related