United States v. Maloney

4 App. D.C. 505, 1894 U.S. App. LEXIS 3355
CourtCourt of Appeals for the D.C. Circuit
DecidedNovember 23, 1894
DocketNo. 345
StatusPublished
Cited by1 cases

This text of 4 App. D.C. 505 (United States v. Maloney) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Maloney, 4 App. D.C. 505, 1894 U.S. App. LEXIS 3355 (D.C. Cir. 1894).

Opinion

Mr. Chief Justice Alvey

delivered the opinion of the Court:

This action was instituted upon a bond against the principal, William Z. Partello, and his two sureties, Patrick Maloney and Harry L. Fillius; but there being no service of process upon the principal the action was prosecuted to trial against the sureties. The trial resulted in a verdict for the defendants, under the direction of the court, and the United States have appealed.

The bond was given for the due performance of a contract entered into by Partello, the principal in the bond» with the Government of the United States, for the furnishing of materials and the execution of certain works of improvement, according to plans and specifications, in what is known as the Yellowstone National Park, a government reservation in the State of Wyoming. This contract was entered into under and in pursuance of an act of Congress of [507]*507the 30th of August, 1890, Ch. 837, being the general appropriation act of that date. In this act the sum of $75,000 was thereby appropriated for completing, improving, maintaining and extending roads and ways in the Park, and the appropriation was made with this proviso, “ That not less than fifty thousand dollars of this appropriation shall be expended for work to be let in sections, after advertisement, to the lowest responsible bidder or bidders therefor, to be executed under the supervision and inspection of an engineer officer of the Army under the direction of the Secretary of War.”

After all preliminaries had been observed and complied with, as prescribed by the statute, and Partello had become the lowest bidder for sections 1, 2, 3 and 5 of the work offered to be let under the proviso of the statute referred to, he executed the contract for doing the work, and the bond sued on, given for the performance of the contract. The contract bears date the 16th of May, 1891, and the bond was executed on the 29th of May, 1891.

The recitals and conditions of the bond are as follows:

“ Whereas the above bounden William Z. Partello has, on the sixteenth (16th) day of May, 1891, entered into a contract with Major William A. Jones, Corps of Engineers, U. S. Army, for furnishing all necessary material and labor and constructing wagon roads in the Yellowstone National Park:

“ Now, therefore, if the above bounden William Z. Partello, his heirs, executors, and administrators, shall and will, in all respects duly and fully observe and perform all and singular the covenants, conditions and agreements, in and by the said contract agreed and covenanted by him to be observed and performed, according to the true intent and meaning of said contract, and as well during any period of extension of said contract that may be granted on the part of the United States as during the original term of the same, including the covenant that the said William Z. Partello [508]*508shall be responsible for and pay all liabilities incurred in the prosecution of the work for labor and material; then the above obligation shall be void and have no effect; otherwise, to remain in full force and virtue.”

The breaches of the contract were not assigned in the declaration; and the sureties, severally, pleaded non est factum. And without joining issue upon the plea, the plaintiffs spread the contract upon the record, and suggested breaches thereof, covered by the condition of the bond. To entitle the plaintiffs to recover damages for the breaches of the condition of the bond, though the issue of non est factum be found in its favor, it was necessary, under the statute of 8 and 9 W. 3, Ch. 11, Sec. 8, that breaches should be assigned. It is only ip respect to alleged breaches of the condition of the bond that the plaintiff is entitled to recover damages, and such breaches must show the extent of the damnification suffered. In the case of a plea of non est factum, or that the bond was obtained by fraud, and the breaches have not been assigned in the declaration, the established practice is to allow the plaintiff to suggest the breaches upon the record, in making up the issue to be tried on the plea; and to proceed to have the damages assessed by the same jury that determines the issue on the plea, if that issue be found for the plaintiff. This suggestion of breaches may be entered at any time before the trial, as well as after the judgment for the plaintiff on the issue of non est factum, or fraud in obtaining the bond. Roberts v. Mariett, 2 Wms. Saund. 187a, note (2); Ethersey v. Jackson, 8 T. Rep. 255. Here the breaches were assigned before the issues were made up for trial.

The parts of the contract with reference to which the breaches have been assigned, and which are material to the questions raised in this action, are the following:

“ The said William Z. Partello shall commence work on or before the 16th day of June, 1891, and shall complete the work on or before the 1st day of October, 1891. If, in any [509]*509event, the party of the second part shall delay or fail to commence with the delivery of material or the performance of the work on the day specified herein, or shall, in the judgment of the engineer in charge, fail to prosecute faithfully and diligently the work in accordance with the specifications and requirements of this contract, then, in either case, the party of the first part, or his successor legally appointed, shall have power, with the sanction of the chief of engineers, to annul this contract by giving notice in writing to that effect to the party (or parties, or either of them) of the second part; and, upon the giving of such notice, all money or reserved percentage due or to become due to the party or parties of the second part, by reason of this contract, shall be and become forfeited to the United States; and the party of the first part shall be thereupon authorized, if an immediate performance of the work or delivery of the materials be in his opinion required by the public exigency, to proceed to provide for the same by open purchase or contract, as prescribed in Section 3709 of the Revised Statutes of the United States. . . . It is further understood and agreed that in case of failure on the part of the party of the second part to complete this contract as specified and agreed upon, that all sums due and percentage retained, shall thereby be forfeited to the United States, and that the said United States shall also have the right to recover any or all damages due to such failure in excess of the sums so forfeited, and also to recover from the party of the second part, as part of said damages, whatever sums may be expended by the party of the first part in completing said contract, in excess of the price herein stipulated to be paid to the party of the second part for completing the same. . . . All rights of action to recover for any breach of this contract by the said William Z. Partello are reserved to the United States. . . . This contract shall be subject to approval of the Chief of Engineers, U. S. A.”

The plaintiffs assigned several breaches of this contract, [510]*510and claim to have sustained damages to the amount of $13,614.40, in doing and executing the work; that amount being in excess of the price stipulated to be paid to the contractor Partello. Whether the bond could be held liable for any amount beyond the penalty, is a question not presented on this appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paige International, Inc. v. Xl Speciality Insurance Company
267 F. Supp. 3d 205 (District of Columbia, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
4 App. D.C. 505, 1894 U.S. App. LEXIS 3355, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-maloney-cadc-1894.