United States v. Malcolm P. Gardner and Herbert L. Stern, Jr.

528 F.2d 715
CourtCourt of Appeals for the Sixth Circuit
DecidedJanuary 9, 1976
Docket75--1327
StatusPublished
Cited by2 cases

This text of 528 F.2d 715 (United States v. Malcolm P. Gardner and Herbert L. Stern, Jr.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Malcolm P. Gardner and Herbert L. Stern, Jr., 528 F.2d 715 (6th Cir. 1976).

Opinion

PHILLIPS, Chief Judge.

The sole issue on this appeal is whether the United States, on the facts here presented, is barred from suing on its debt priority under 31 U.S.C. §§ 191 and 192 1 and by the statute of limitations set forth in 28 U.S.C. § 2415. 2 The District Court determined, inter alia, that the right of action accrued on the date of the company’s default, and that the Government’s suit is barred by the statute. We reverse and remand.

In 1966, Drillmation, Inc. (the Company) entered into two contracts with the Department of the Army for carbine bolts and flash suppressors. The Company encountered difficulties in proceeding with both contracts and eventually notified the Army on April 27, 1967, that it was unable to continue performance. The Government contracting officer then terminated the two contracts for default on May 19, 1967, and May 24, 1967, respectively. Pursuant to the standard “disputes clause” 3 of the contracts, *717 which provides for ah administrative appeal from the decision of the contracting officer to the Armed Services Board of Contract Appeals (ASBCA), the Company appealed from the contracting officer’s factual finding that it had defaulted on the contracts.

Between May and November 1967, the Company sold its unrelated Army assets and changed its name to Eight Mile Road Defense Contractors, Inc. (Eight Mile Inc.). All remaining assets of Eight Mile Inc. were surrendered to its lien-holder, the American National Bank of Chicago, which after sale and satisfaction of its lien returned $170,528.43 to appellees as surplus. The appellees, officers of Eight Mile Inc., although aware of the obligation due the United States, distributed this amount to general creditors and did not pay any part of the indebtedness owed to the Government.

On January 19, 1968, pending the appeal to the ASBCA, Eight Mile Inc. entered into a contract with the Government whereby the Army agreed not to put Eight Mile Inc. on certain Government lists and not to refer the debt to the General Accounting Office until 45 days after the ASBCA decision. 4 This deferral agreement also provided that Eight Mile Inc. would pay the amount found owing by the ASBCA promptly within 45 days of the decision. Such payment, however, would be without prejudice to the contractor’s right to move for reconsideration or to pursue other remedies available at law. The decision of the Appeals Board was handed down on April 10, 1969.

Subsequently, on November 6, 1973, the United States instituted this suit against the appellees, as fiduciaries of Eight Mile Inc., to hold them personally liable for distributing the funds in violation of their statutory duty under 31 U.S.C. § 192. The District Court held that the action was barred by the six year statute of limitations of 28 U.S.C. § 2415, finding that the right of action accrued on the date of default in May 1967.

The Government relies upon three grounds for reversal:

1) That the deferral agreement of January 19, 1968, constituted an independent contract to pay the claim, which was breached by the Company in 1969; therefore, the six year limitation period *718 had not run in 1973 when the Government filed this suit;

2) That, in any event, the deferral agreement was a contract to toll the statute of limitations during the pendency of the appeal to the ASBCA; and

3) Alternatively, that the Government’s cause of action under 31 U.S.C. § 192 did not accrue until the defendants’ payment of debts in violation of the Government’s priority.

We agree with the first ground asserted by the Government. Therefore, it is not necessary to reach the other issues in disposing of this appeal.

28 U.S.C. § 2415(a) (n. 2) provides a six year period of limitations for suits “founded upon any contract express or implied in law or fact.” The record demonstrates that the present action is a suit founded on a contract, viz, the deferral agreement entered into between the Company and the Government on January 19, 1968.

The deferral agreement provides in part as follows:

AGREEMENT BETWEEN
DRILLMATION COMPANY, INC. NOW KNOWN AS EIGHT MILE ROAD DEFENSE CONTRACTORS, INC.
1601 Wanda Avenue Ferndale, Michigan 48220 and
THE DEFENSE SUPPLY AGENCY CAMERON STATION, ALEXANDRIA, VIRGINIA 22314
1. A Defense Supply Agency (DSA) Contracting Officer by formal decision has found that Drillmation Company, Inc. (Eight Mile Road Defense Contractors, Inc.), hereinafter referred to as the Contractor, owes the U. S. Government a total principal amount of $1,541,321.60 plus interest at the rate of 6% per annum as stipulated on the reverse hereof under Contracts DA 19-058-AMC-1509(W) and DA 19-058-AMC-1645(W).
2. The Contractor denies existence of such debt and has appealed the Contracting Officer’s decision to the Armed Services Board of Contract Appeals (ASBCA).
3.. The ASBCA has docketed the appeal as No. 12501 for Contract 1509(W) and 12579 for Contract 1645(W).
4. The Contractor agrees to pay to the DSA the amount, plus accrued interest, found due by reason of the ASBCA decision on the appeal, or if the appeal is dismissed by the Board without decision, the amount mentioned in paragraph 1 above. Such payment in either case shall be without prejudice to the Contractor’s right to move for reconsideration or to pursue such other remedies at law as it may have. The Contractor further agrees to make such payment in full within 45 days of the date of the ASBCA decision or dismissal of the appeal or to make arrangements within that 45 day period to pay the amount on an installment basis within the bounds of the minimum requirement outlined in paragraph 5 below. ******
6. The DSA agrees not to circulate the name of the Contractor on certain U.S. Government lists designed to effect settlement of accounts of recalcitrant debtors and agrees not to transfer the case to the U.S. General Accounting Office or the Department of Justice before 45 days after the ASBCA decision on the appeal is published and to do so then only if the Contractor fails to comply with paragraph 4 above or fails to fulfill any agreement reached under paragraph 5 above.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
528 F.2d 715, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-malcolm-p-gardner-and-herbert-l-stern-jr-ca6-1976.