United States v. ILCO, Inc.

996 F.2d 1126, 1993 WL 267355
CourtCourt of Appeals for the Eleventh Circuit
DecidedAugust 4, 1993
DocketNo. 91-1004
StatusPublished
Cited by23 cases

This text of 996 F.2d 1126 (United States v. ILCO, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. ILCO, Inc., 996 F.2d 1126, 1993 WL 267355 (11th Cir. 1993).

Opinion

FAY, Circuit Judge:

This case is an enforcement action filed by the United States Environmental Protection Agency and the State of Alabama against a secondary lead smelter for violations of federal and state environmental law. The district court held the defendant liable and awarded civil penalties and cleanup costs to the government, and ordered compliance with the law. Although the government received a favorable decision, it has appealed the district court’s conclusion that the lead components reclaimed from spent batteries are raw materials. The district court reasoned that because the smelter recycles the components into lead ingots, the components must be raw materials, and not hazardous waste subject to the provisions of the Resource Conservation and Recovery Act. The [1128]*1128defendant has cross-appealed the district court’s order awarding penalties and cleanup costs to the government. Because we find the district court’s order well founded in fact and law, we affirm it in all but one respect. We reverse the court’s conclusion regarding the lead components reclaimed from spent batteries because EPA, in accordance with its authority granted by Congress, has defined “discarded material” to include “recycled material.”

BACKGROUND

1. Industry Overview1

Over the years in the United States there has been a steady increase in the number of vehicle batteries which become useless and subject to disposal. In 1986 the number stood at approximately 70,000,-000. Each spent battery is a potential pollutant of the environment and can have serious deleterious effects on people and animals living in the area where the battery may be discarded.. Even a small number of batteries thrown into the woods, discarded along roadways or in government designated garbage areas represent a significant threat to the water we drink, the food we eat and under limited circumstances, the air we breathe. The source of this trouble in a battery is lead_ [Because lead is an expensive element, an industry has developed over the years] to reclaim the lead from spent batteries.... [In the mid-Seventies] there were approximately 50 secondary lead smelters in the United States reclaiming the lead from about 90% of all spent batteries. The smelters were themselves a major source of pollution; surface water run-off and process water discharged by the smelters created very real health-threatening problems; on-site and off-site storage or disposition of waste became an increasing risk to the quality of life; and even the air was dangerously polluted by emissions from the smelters. [In response to these problems] all levels of government began to amend existing laws and to enact new laws and regulations placing much greater controls over ownership and operation of such smelters. Compliance with these new environmental laws and regulations ... placed such a financial burden on the operation of secondary lead smelters that about 60% of the smelters operating in 1976 were out of business by 1986, and the approximately 20 smelters remaining were reclaiming only about 70% .. [of all discarded batteries.] Thus in 1986 only 55,-000,000 of the available 70,000,000 batteries were reclaimed, leaving the 15,000,000 unreclaimed spent batteries to endanger the health of all persons near the site of their repose. The 55,000,000 reclaimed batteries produced- about 60% of all lead used in the United States.... [This brief overview demonstrates the secondary lead smelting industry] is a most vital industry not only to our economy but also to [our]' environment.... Without the industry, over 70,000,000 contaminated batteries would be scattered throughout our country annually. [Nevertheless, the heart of this industry centers around the handling of hazardous materials. Exempting the industry from regulation cannot be justified on the theory that its contribution to resolving our environmental problems outweighs the environmental harm caused by its operations.]

2. Factual and Procedural Background

Against this industry backdrop the present case unfolds, spanning nearly, a decade of interaction between the .Environmental Protection Agency (“EPA”), the Alabama Department of Environmental Management (“ADEM”) and Interstate Lead Company, Inc. (“ILCO”). The voluminous facts are very briefly set forth.

ILCO owned and operated a secondary lead smelting facility in Leeds, Alabama, from the 1960’s until operations ceased in 1992. As such, it was one of the 20 smelters remaining in the country which reclaimed spent batteries. In 1986 ILCO reclaimed over 2,500,000 batteries, or about 5% of those [1129]*1129reclaimed in the United States. Diego Maf-fei is the president and majority shareholder of ILCO.

ILCO purchased batteries from various suppliers and placed them in a reclamation process. Incoming batteries were cracked open and drained of sulfuric acid. The rubber or black plastic battery boxes were chipped and washed to remove lead particles. The lead battery components known as “plates and groups” were then removed from the broken batteries and run through ILCO’s smelting process to produce lead ingots for sale. The operation produced several waste products which were the subject of litigation in the district court: waste acid, wastewater treatment sludge, broken battery casings or “chips,” and emission control dust and blast slag from the smelting process. EPA asserted, and continues to argue on appeal, that the reclaimed lead plates and groups were also waste products. The defendants viewed the plates and groups as raw materials essential to the lead recovery industry.

EPA and ADEM initiated this case as an enforcement action against ILCO and its president, Diego Maffei, seeking an injunction to curtail ongoing violations of environmental laws and regulations at ILCO’s plant in Leeds and seeking penalties for past violations.2 The amended complaint contained six claims, but two settled during trial. Of the four remaining claims, EPA first alleged ILCO violated the Clean Water Act (“CWA”), 33 U.S.C. §§ 1251-1387, by improperly. discharging waste water at or near the plant site in violation of its NPDES permit,3 and subsequent to March 1984 without any permit.4 The second and third claims concerned the treatment, storage and disposal of hazardous wastes since 1980 in violation of the Resource Conservation and Recovery Act (“RCRA”), as amended by the Hazardous and Solid Waste Amendments of 1984, 42 U.S.C. §§ 6901-92L In the second claim EPA charged ILCO with maintaining storage areas, an incinerator and a treatment tank, all containing hazardous waste, in violation of regulations applicable to 'their status as an interim facility and maintaining other storage facilities and a landfill without the requisite permit.5 The third claim encompassed the same RCRA violation, alleging that the facility permitted releases of hazardous waste into the environment. The fourth claim focused upon alleged violations of the Comprehensive Environmental Response, Compensation, and Liability Act (“CERC-LA”), 42 U.S.C. §§ 9601-75, at a place known as “the Church of God site,” located about six miles north of the plant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Talarico Bros. Bldg. Corp. v. Union Carbide Corp.
73 F.4th 126 (Second Circuit, 2023)
Tennessee Riverkeeper, Inc. v. 3M Co.
234 F. Supp. 3d 1153 (N.D. Alabama, 2017)
Hackensack Riverkeeper, Inc. v. Delaware Ostego Corp.
450 F. Supp. 2d 467 (D. New Jersey, 2006)
Quebell P. Parker v. Scrap Metal Processors
386 F.3d 993 (Eleventh Circuit, 2004)
Safe Air For Everyone v. Meyer
373 F.3d 1035 (Ninth Circuit, 2004)
United States v. Mountain Metal Co.
137 F. Supp. 2d 1267 (N.D. Alabama, 2001)
Morton Internationa, Inc. v. A.E. Staley Manufacturing Co.
106 F. Supp. 2d 737 (D. New Jersey, 2000)
Amer Petro Inst v. EPA
D.C. Circuit, 2000
United States v. Valentine
885 F. Supp. 1506 (D. Wyoming, 1995)
Chatham Steel Corp. v. Brown
858 F. Supp. 1130 (N.D. Florida, 1994)
United States v. Ilco, Incorporated
996 F.2d 1126 (Eleventh Circuit, 1993)