United States v. Hillyer

457 F.3d 347, 36 Envtl. L. Rep. (Envtl. Law Inst.) 20151, 2006 U.S. App. LEXIS 19306, 2006 WL 2129845
CourtCourt of Appeals for the Fourth Circuit
DecidedAugust 1, 2006
DocketNo. 05-4295
StatusPublished
Cited by5 cases

This text of 457 F.3d 347 (United States v. Hillyer) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Hillyer, 457 F.3d 347, 36 Envtl. L. Rep. (Envtl. Law Inst.) 20151, 2006 U.S. App. LEXIS 19306, 2006 WL 2129845 (4th Cir. 2006).

Opinion

Vacated and remanded by published opinion. Judge MICHAEL wrote the opinion, in which Judge KING and Chief Judge ANDERSON joined.

OPINION

MICHAEL, Circuit Judge:

Michael Eugene Hillyer pled guilty to two federal environmental crimes involving illegal dredging in North Carolina’s Croa-tan Sound. The government appeals Hil-lyer’s sentence of three years’ probation, contending that the district court erred both in calculating the advisory guideline range and in imposing a non-guideline (or variance) sentence. We conclude that the guideline range was improperly calculated because the departure granted under U.S.S.G. § 5K2.20 for aberrant behavior was unwarranted. We therefore vacate the sentence and remand for resentencing.

I.

A.

We recount the facts as established by the guilty plea and presented without objection in the presentence report and at the sentencing hearing. In March 1998 the U.S. Army Corps of Engineers (the Corps) granted a permit to the North Carolina Department of Transportation (DOT) to build a 5.25 mile bridge across the Croatan Sound from Manns Harbor to Manteo. The bridge would be named the Virginia Dare Memorial Bridge. In April 1998 DOT awarded a $100 million construction contract to Balfour Beatty Construction, Inc. (Balfour). The contract required Balfour to comply with the Corps permit, which was issued under the Rivers and Harbors Act of 1899, 33 U.S.C. §§ 401 et seq., and the Clean Water Act, 33 U.S.C. §§ 1251 et seq. Construction began in 1998, but by mid-2000 the project was over budget and far behind schedule. Moreover, the project had an “abysmal safety record.” J.A. 51. In June 2000 Balfour, in an effort to salvage the job, brought in Hillyer as project manager. Hillyer had supervised some of the largest and most complicated bridge projects in the country. He had earned a reputation for competence and for being a hardnosed and sometimes bullheaded manager who [349]*349demanded quality work from his employees. As the project’s new manager, Hil-lyer assumed responsibility for Balfour’s compliance with all applicable permits and the federal environmental laws that they incorporated.

The original permit from the Corps prohibited the excavation of material from, and the fill or disposal of material within, the affected waters and wetlands, except as authorized by the permit or any modification. In 1998 at Balfour’s request, DOT obtained a permit modification to allow construction of a temporary load-out trestle (or bridge) to be built on pilings driven into the bottom of the Croatan Sound. The permit authorized Balfour to hammer-drive the pilings into the bottom of the sound; it did not authorize prop washing or jetting, techniques used to dredge and displace material from the bottom of a water course. (“Dredged soil” is a pollutant under the Clean Water Act, 33 U.S.C. § 1362(6).) The trestle, completed in the fall of 1998, extended 700 feet into the water and was 60 feet wide. It facilitated the transport of construction materials from the shoreline to barges out in the water.

The Virginia Dare Memorial Bridge opened August 9, 2002, on schedule. Hil-lyer had completely rehabilitated the project, reducing costs, ensuring a timely finish, and garnering an award for “the safest project on the East Coast.” J.A. 45. The positive run of events began to turn, however, the day before the bridge opened. On August 8, 2002, Hillyer directed his employees to dump fill material from the project into wetlands at a nearby marina site, in violation of the permit and applicable federal laws. DOT requested that Balfour cease dumping material at the marina site, but the company refused. A Corps representative for regulatory matters then met with Hillyer to advise him that depositing fill material was impermissible and would require permit modification. He further instructed Hillyer on how to contact the Corps directly for “guidance and authorization on regulatory compliance matters.” J.A. 132. Hillyer, however, “responded with profanity and essentially told the [Corps representative] that it was his (Hillyer’s) fill and he (Hil-lyer) would do what he (Hillyer) wanted.” Id.

After the bridge opened, Balfour began efforts to remove the trestle so that it could be transported and reassembled at another bridge project, where it was urgently needed. Balfour tried using a crane to extract the trestle pilings, but sediment around the pilings blocked the crane from getting close enough for the extraction. In late October 2002 Hillyer directed his employees to excavate a channel around the trestle to facilitate crane access. Hillyer first instructed the employees to use a clam bucket, but was promptly notified by DOT that this activity constituted dredging and was impermissible under existing permits. On October 22, 2002, Hillyer directed employees to use another dredging technique, specifically prop dredging or prop washing with tugboat propellers, to displace material from the sound bottom. The following day, upon discovering the prop dredging, DOT faxed Hillyer a letter notifying him once again that he was violating existing permits and must cease all dredging unless and until a permit modification was obtained. In response, Hillyer sent DOT a request that it seek permit modification from the Corps.

Without waiting for the necessary modification, Hillyer ordered more prop dredging. He assembled the workers at 6 p.m. on Sunday, October 27, at a nearby marina and arranged for them to be shuttled by boat to the site, where they resumed the [350]*350prop dredging. He ordered his crew to shut down the dredging operation early the next two days, around 3 or 4 p.m., only to return at night and resume the work under cover of darkness, with the tugboat’s navigation lights turned off. Hillyer took these unusual steps in an obvious attempt to conceal the unpermitted activity from DOT. The concealment effort failed, however. A Balfour employee on board the tugboat the night of October 29 called Hillyer to report that “DOT was watching” and videotaping the activity. J.A. 133. Hillyer, who was under considerable pressure from Balfour to remove the trestle as quickly as possible, became irate and instructed the crew to continue the prop dredging.

The dredging continued until October 31, 2002, when removal of the trestle was completed. DOT thereafter sent three letters to Balfour notifying it that the prop dredging was a permit violation. In late December 2002 the Corps issued a notice of violation against Balfour for the unauthorized dredging. In January 2003, at DOT’s request, Balfour removed Hillyer from all bridge projects (and eventually fired him) because of his “inability to follow the reasonable direction of the DOT’s resident engineers” and his violation of the permit and applicable environmental laws. J.A. 133. DOT determined that the unauthorized dredging displaced roughly 5,500 cubic yards (about 500 dump truck loads) of sound bottom and disturbed 8.2 acres of shallow water habitat designated as “high quality.” J.A. 133. To mitigate the damage and facilitate restoration, DOT deposited several tons of “ ‘oyster clutch’ material” at the dredge site. J.A. 134.

B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Jacquemain
Sixth Circuit, 2009
United States v. Carson
560 F.3d 566 (Sixth Circuit, 2009)
United States v. Diaz-Calderon
216 F. App'x 331 (Fourth Circuit, 2007)
United States v. Jackson
467 F.3d 834 (Third Circuit, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
457 F.3d 347, 36 Envtl. L. Rep. (Envtl. Law Inst.) 20151, 2006 U.S. App. LEXIS 19306, 2006 WL 2129845, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-hillyer-ca4-2006.