United States v. Freeman

113 F. 370, 1902 U.S. Dist. LEXIS 358
CourtDistrict Court, D. Washington
DecidedJanuary 13, 1902
StatusPublished
Cited by8 cases

This text of 113 F. 370 (United States v. Freeman) is published on Counsel Stack Legal Research, covering District Court, D. Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Freeman, 113 F. 370, 1902 U.S. Dist. LEXIS 358 (washd 1902).

Opinion

HANFORD, District Judge.

This proceeding was instituted by the government of the United States for the purpose of appropriating a number of lots and parcels of land required by the government for military purposes, and to enlarge Ft. Worden. A special venire was issued for jurors, from whom 12 were selected and impaneled in the ustial manner of selecting jurors, and sworn to determine all disputed questions of fact as to ownership of the property, and fix the valuation thereof, and assess any damages resulting to the owners from the taking of their property. As provided by the act of congress authorizing the condemnation of land re[371]*371quired for fortifications (see I Supp. Rev. St. [2d Ed.] pp. 601, 780), the proceedings were conducted as near as practicable according to the procedure prescribed by the laws of this state. On the trial before the court and the jury there was no controversy as to the ownership of the property, and the jury was required only to determine the value and assess the damages. Witnesses, including business men of Port Townsend, were called on the part of the government, as well as of the owners, who gave their estimates of the value of the land and of the improvements thereon, and the court and jury visited the premises for the purpose of viewing the same, and, after returning to the court room, arguments were made to the jury by counsel representing all the parties, and the case was submitted to the jury with instructions by the court that they were to determine the reasonable value at the present time of the land sought to be condemned and the improvements thereon, and assess damages in favor of any of the owners who were shown by the evidence to have been damaged by the taking of their property, and afterwards the jury returned into court a separate verdict as to each of the different lots and parcels of land appropriated. Compared with the estimates testified to by the witnesses on the part of the government, the sums awarded are just and reasonable, but, measured by the testimony introduced by the defendants, the sums awarded are in some instances very much below the reasonable value. The defendants are dissatisfied with the verdicts, and have moved the court to set the same aside and grant a new trial on a number of specified grounds, all of which, by disregarding legal verbiage, may be resolved into the following: (1) Error in law committed by the court on the trial in excluding evidence offered by the defendants to prove the price of adjoining lands, which was fixed by agreement, and was paid by the government. (2) Misconduct on the part of a superintending engineer in the employment of the government at the time the jury were taken to view the premises, in this: that said engineer conducted the jury to and upon lands other than the land to be condemned. (3) Error in the findings of the jury, in this: that the sums awarded by their verdicts are inadequate, and not sufficient to constitute just compensation for the property taken.

The price which a purchaser pays for one piece of property is not a fair criterion by which to determine the value of an adjoining tract several years after the transaction, for the reason that the necessity of the purchaser, the disposition of the vendor, and peculiar circumstances and conditions may be such as to oblige a purchaser to submit to severe exactions in order to consummate a purchase without delay. Therefore evidence of a particular transaction is likely to be misleading unless all the circumstances and conditions are explained, and it is not practicable for parties to be ready on the trial to produce witnesses to explain transactions not involved in the issues. It was for this reason that the court excluded the testimony offered by the defendants, and I believe now, as I believed at the time, that the evidence was incompetent. It is not shown by the affidavits filed that the jury were misinformed with respect to the identity of the land to and upon which they were conducted [372]*372It was fair to all parties that the jury should have an opportunity to see the land, and the mere circumstance of their being conducted over adjoining property would not necessarily, nor probably, be prejudicial to the defendants. The intelligence and good sense of jurymen must be appealed to when they are called upon to determine questions of value and assess damages; and an opportunity to see the property which is the subject of controversy, and also to see and compare other property in the immediate vicinity, cannot reasonably be presumed to have diminished the knowledge, experience, and common sense which qualifies jurymen to discharge their functions in cases of this character. I do not think there was any intentional misconduct on the part of the engineer, nor that any error which he may have committed in conducting the jury justifies a suspicion that the land condemned was appraised lower than it would have been if the jury had not been permitted to see other land contiguous thereto. I adhere to the ruling made by this court in the case of U. S. v. Tennant (D. C.) 93 Fed. 613, to the effect that in condemnation cases in this state the law does not authorize the court of original jurisdiction to set aside the verdict of a jury on the ground that the appraisement was erroneous or unfair. Upon a re-examination of the question I am confirmed in the opinion that the statutes of this state as expounded by its supreme court prescribe a special and peculiar mode of procedure distinct from the practice in civil actions. Therefore the provisions of the civil practice act authorizing courts in which actions are tried to set aside verdicts for error in assessment of damages are not applicable, and do not authorize the same courts to grant new trials in condemnation cases. See Railway Co. v. O’Meara, 4 Wash. 17, 29 Pac. 835; Tacoma v. State, 4 Wash. 64, 29 Pac. 847; Long v. Billings, 7 Wash. 267, 34 Pac. 936; Western American Co. v. St. Ann Co., 22 Wash. 158, 60 Pac. 158. The act prescribing a special method of procedure in condemnation cases (section 5616 et seq., 2 Ballinger’s Ann. Codes & St. Wash.) does not in express terms, nor by any fair implication, authorize the court to set aside the verdict of a jury, nor to grant a new trial; and, as the law providing for new trials in civil actions does not apply, there is no statute giving the court power to grant a new trial. If the court has the power, it exists not by virtue of any statute, but because it is necessarily one of the inherent powers of the court. I believe that the court has inherent power to correct its own errors, but by the constitution and laws of this state the compensation to be paid to the owner of property condemned for public use must be determined by the verdict of a jury; and if a jury errs in assessing damages the law does not confer upon the court of original jurisdiction power to correct the error, nor leave the court free to exercise any inherent and unnamed power to resubmit the case to a second jury, but allows an appeal to the supreme court of the state, and provides that the propriety and justness of the award shall be for the consideration of the appellate court; and I hold that by authorizing an appeal and Specially conferring power upon the appellate court to pass upon the propriety and justness of the award the legislature in effect [373]*373has denied the right o£ the court of original jurisdiction to interfere with the verdict oí a jury.

It is contended on the part of the defendants that a statute authorizing the appellate court to determine finally the amount to be awarded as compensation for property condemned to public use is contrary to section 16, art.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Justice v. United States
145 F.2d 110 (Ninth Circuit, 1944)
United States v. Certain Parcels of Land
45 F. Supp. 899 (E.D. Washington, 1942)
Hannan v. United States
131 F.2d 441 (D.C. Circuit, 1942)
Houston Independent School Dist. v. Reader
38 S.W.2d 610 (Court of Appeals of Texas, 1931)
Charleston & Western Carolina Ry. Co. v. Spartanburg Bonded Warehouse, Inc.
149 S.E. 236 (Supreme Court of South Carolina, 1929)
Grays Harbor Boom Co. v. Lownsdale
102 P. 1041 (Washington Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
113 F. 370, 1902 U.S. Dist. LEXIS 358, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-freeman-washd-1902.