United States v. DTE Energy Co.

845 F.3d 735, 2017 FED App. 0006P, 47 Envtl. L. Rep. (Envtl. Law Inst.) 20007, 2017 WL 83392, 83 ERC (BNA) 1937, 2017 U.S. App. LEXIS 416
CourtCourt of Appeals for the Sixth Circuit
DecidedJanuary 10, 2017
Docket14-2274/2275
StatusPublished
Cited by1 cases

This text of 845 F.3d 735 (United States v. DTE Energy Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. DTE Energy Co., 845 F.3d 735, 2017 FED App. 0006P, 47 Envtl. L. Rep. (Envtl. Law Inst.) 20007, 2017 WL 83392, 83 ERC (BNA) 1937, 2017 U.S. App. LEXIS 416 (6th Cir. 2017).

Opinions

DAUGHTREY, J., delivered the opinion in which BATCHELDER, J., joined in the result. BATCHELDER, J. (pp. 741-45), delivered a separate opinion concurring in the judgment. ROGERS, J. (pp. 745-56), delivered a separate dissenting opinion.

OPINION

MARTHA CRAIG DAUGHTREY, Circuit Judge.

This case is before us for a second time, following an order of remand in United States v. DTE Energy Co. (DTE I), 711 F.3d 643 (6th Cir. 2013). As we noted there, regulations under the Clean Air Act require a utility seeking to modify a source of air pollutants to “make a preconstruction projection of whether and to what extent emissions from the source will increase following construction.” Id. at 644. This projection then “determines whether the project constitutes a ‘major modification’ and thus requires a permit” prior to construction, as part of the Act’s New Source Review (NSR) program. Id.; see also 42 U.S.C. §§ 7475, 7503; 40 C.F.R. § 52.21. The NSR regulations require an [737]*737operator to “consider all relevant information” when estimating its post-project actual emissions but allow for the exclusion of any emissions “that an existing unit could have accommodated during the [baseline period] ... and that are also unrelated to the particular project, including any increased utilization due to product demand growth.” 40 C.F.R.- § 52.21 (b)(41)(ii)(a) and (c). An operator must document and explain its decision to exclude emissions from its projection as resulting from future “demand growth” ¿nd provide such information to the EPA or to the designated state regulatory agency. 40 C.F.R. § 52.21(r)(6)(i)-(ii).

Defendants DTE Energy Co. and its subsidiary, Detroit Edison Co. (collectively DTE), own and operate the largest coal-fired power plant in Michigan at their facility in Monroe, where, in 2010, DTE undertook a three-month-long overhaul of Unit 2 costing $65 million. On the day before it began construction, DTE submitted a notification to the Michigan Department of Environmental Quality stating that DTE predicted an increase in post-construction emissions 100 times greater than the minimum necessary to constitute a “major modification” and require a pre-construction permit. DTE initially characterized the projects as routine maintenance, repair, and replacement activities, a designation that, if accurate, would exempt the projects from triggering NSR.1 See New York v. U.S. Envtl. Prot. Agency, 443 F.3d 880, 883-84 (D.C. Cir. 2006). DTE also informed the state agency that it had excluded the entire predicted emissions increase from its projections of Unit 2’s post-construction emissions based on “demand growth.” This designation, if it could be established to the agency’s satisfaction, also would have exempted DTE’s modification from the necessity of a permit and, thus, allowed DTE to postpone some of the pollution-control installations that were planned as a future upgrade.2 See 40 C.F.R. § 52.21(b)(41)(ii)(c). DTE began construction on Monroe Unit 2 without obtaining an NSR permit.

After investigation of DTE’s projections, the EPA filed this enforcement action, challenging the company’s routine-maintenance designation and its exclusion for “demand growth,” and insisting that DTE should have secured a preconstruction permit and included pollution controls in the Unit 2 overhaul to remediate the projected emissions increases. The district court granted summary judgment to DTE, holding that the EPA’s enforcement action was premature because the construction had not yet produced an actual increase in emissions. On appeal, we reversed and remanded, holding that the EPA was authorized to bring an enforcement action based on projected increases in emissions without first demonstrating that emissions actually had increased after the project. DTE I, 711 F.3d at 649.

On remand, the district court again entered summary judgment for DTE, this time focusing on language in our first opinion to the effect that “the regulations allow operators to undertake projects without having EPA second-guess their projections.” Id. at 644. The district court appar[738]*738ently (and mistakenly) took this to mean that the EPA had to accept DTE’s projections at face value, holding that:

EPA is only entitled to conduct a surface review of a source operator’s pre-construction projections to determine whether they comport with the letter of the law. Anything beyond this cursory examination would allow EPA to “second-guess” a source operator’s calculations; an avenue which the Sixth Circuit explicitly foreclosed to regulators. [Emphasis added.]
In this case, EPA claims that defendants improperly applied the demand growth exclusion when they “expected pollution from ... Unit 2 to go up by thousands of tons each year after the overhaul,” and then discounted this entire emissions increase by attributing it to additional consumer demand. In other words, EPA does not contend that defendants violated any of the agency’s regulations when they computed the preconstruction emission projections from Unit 2. Rather, EPA takes defendants to task over the extent to which they relied upon the demand growth exclusion to justify their projections. This is exactly what the Sixth Circuit envisioned when it precluded EPA from second-guessing “the making of [precon-struction emission] projections.” [Internal citations omitted.]

The problem with the district court’s analysis is two-fold. First, the focus on so-called “second-guessing” is misplaced. That language from our earlier opinion is, technically speaking, dictum, because the holding of the opinion was, as noted above, that the EPA could bring a preconstruction enforcement action to challenge DTE’s emissions projections. Second, in reviewing an operator’s attribution of increased emissions to demand growth, the EPA definitely is not confined to a “surface review” or “cursory examination.”

Indeed, two agency pronouncements, dating back to 1992, make clear that the EPA must engage in actual review. The first is in 57 Fed. Reg. 32,314, 32,327 (July 21, 1992), which is quoted in our first opinion: “[W]hether the [demand growth] exclusion applies ‘is a fact-dependent determination that must be resolved on a case-by-case basis’ DTE I, 711 F.3d at 646 (emphasis added). The second is found in 72 Fed. Reg. 72,607, 72,611 (Dec. 21, 2007) (emphasis added): NSR record-keeping requirements “establish[ ] an adequate paper trail to allow enforcement authorities to evaluate [an operator’s] claims concerning what amount of an emissions increase is related to the project and what amount is attributable to demand growth.”

But the EPA cannot evaluate a fact-dependent claim on a case-by-case basis unless the operator supplies supporting facts, which the record establishes was not done here. In other words, a valid projection must consist of more than the following list, which is, in effect, all that DTE provided to the EPA:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Ameren Missouri
9 F.4th 989 (Eighth Circuit, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
845 F.3d 735, 2017 FED App. 0006P, 47 Envtl. L. Rep. (Envtl. Law Inst.) 20007, 2017 WL 83392, 83 ERC (BNA) 1937, 2017 U.S. App. LEXIS 416, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-dte-energy-co-ca6-2017.