United States v. Dico, Inc.

4 F. Supp. 3d 1047, 2014 U.S. Dist. LEXIS 35761, 2014 WL 1046886
CourtDistrict Court, S.D. Iowa
DecidedFebruary 24, 2014
DocketNo. 4:10-cv-00503
StatusPublished
Cited by3 cases

This text of 4 F. Supp. 3d 1047 (United States v. Dico, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Dico, Inc., 4 F. Supp. 3d 1047, 2014 U.S. Dist. LEXIS 35761, 2014 WL 1046886 (S.D. Iowa 2014).

Opinion

ORDER ON BENCH TRIAL

ROBERT W. PRATT, District Judge.

This lawsuit arose out of the United States of America’s (“Plaintiff’) claims against Dico, Inc. (“Dico” or “Defendant”) and Titan Tire Corporation (“Titan Tire”) (collectively “Defendants”), under “Sections 106, 107 and 113(g) of the Comprehensive Environmental Response, Compensation, and Liability Act [“CERCLA”] of 1980.” Compl. (Clerk’s No. 1) ¶2. Plaintiff sought to recover unreimbursed response costs from Defendants, and civil penalties and punitive damages from Dico, in connection with the release and/or the threat of release of polychlorinated biphe-nyls (“PCBs”)1 at Southern Iowa Mechanical’s (“SIM”) site in Ottumwa, Iowa. See id. Plaintiff also requested that the Court enter a declaratory judgment holding Defendants liable for all future response costs that Plaintiff would incur as a result of the release and/or threat of release of PCBs at the SIM site. See id.

The Court resolved all but one of the issues presented by the parties during the summary judgment phase of the litigation. In particular, the Court held that: (1) Defendants arranged for the disposal of PCBs by selling some of its PCB-contaminated buildings to SIM, see Order (Clerk’s No. 119) at 16-40; (2) Defendants were liable for all response costs that Plaintiff had already incurred or would incur as a result of the SIM site removal action, see Order (Clerk’s No. 128) at 43; and (3) Dico was liable for both civil penalties and punitive damages for violating the 1994 Unilateral Administrative Order (the “1994 Building UAO”), see id. The sole issue reserved for trial was the amount, if any, of civil penalties and/or punitive damages to be assessed against Dico. See id. The Court held a bench trial on this issue from December 2-5, 2013. See Clerk’s Nos. 186-89. On January 15, 2014, the parties submitted their proposed findings of fact and conclusions of law. See Clerk’s Nos. 196-97. The matter is fully submitted.

I. CONSIDERATIONS ON REVIEW

Federal Rule of Civil Procedure 52(a) requires that in all cases tried without a jury or with an advisory jury, “the court [1050]*1050must find the facts specially and state its conclusions of law separately.” In determining the credibility of the witnesses and the weight to be accorded their testimony, the Court has taken into consideration: the character of the witnesses, their demeanor and manner of testifying on the stand, their interest, if any, in the result of the trial, their relation to or feeling toward the parties to the trial, the probability or improbability of their statements, and all other facts and circumstances given in evidence. See United States v. Phillips, 522 F.2d 388, 391 (8th Cir.1975); Clark v. United States, 391 F.2d 57, 60 (8th Cir.1968); United States v. Earles, 983 F.Supp. 1236, 1254 (N.D.Iowa 1997); Manual of Model Civil Jury Instructions for the District Courts of the Eighth Circuit, Instruction 3.03 (2013). With these considerations in mind, the Court finds facts and makes conclusions of law as articulated herein.

II. FINDINGS OF FACT

A. Stipulated Facts

The parties have stipulated to many of the facts in this case. See Am. Proposed Order on Final Pretrial Conference (Clerk’s No. 181) at 2-6. Pursuant to this stipulation, the Court finds the following facts:

• Dico is a corporation organized and existing pursuant to the laws of the State of Delaware.

• Dico owns property located at 200 Southwest 16th Street in Des Moines, Iowa, which is part of the Des Moines TCE Superfund Site.

• The Des Moines TCE2 Superfund Site is divided into four Operable Units (“OU”).

• OU1 involves a groundwater extraction, treatment, and monitoring system designed to address historical volatile organic compound contamination in the groundwater on the Dico property.

• OU3 involves groundwater in the area north of the Dico property. Dico does not own the land at issue in OU3.

• OU2 and OU4 include several buildings on the Dico property where, among other things, formulation of pesticides and herbicides once occurred. OU4 also includes soil and sediment associated with an aldrin tank that once existed on the property; the South Pond area; and a drainage channel south and east of the Dico property. As part of the remedial work associated with OU4, Dico installed an asphalt cap over a substantial portion of the Site. To this day, Dico is responsible for maintaining the asphalt cap.

• In 1992, PCBs were discovered in the insulation of five buildings (Buildings 2-5 and the Maintenance Building, collectively the “Dico Buildings”) on Dico’s property within what is now 0U4.

• [The Environmental Protection Agency] [ (“the] EPA[” or the “Agency”) ] issued ... the 1994 Building UAO to Dico to address contamination within the Dico Buildings. The 1994 Building UAO did not cover certain other buildings on the Dico property, including the Weld Shop and [the] Production Building.

• Dico performed the work set forth in the approved Removal Action Work Plan required by the 1994 Building UAO and submitted a final report to [1051]*1051[the] EPA on April 11, 1997 (“the 1997 Report”)....

Mary Peterson [ (“Peterson”) ], [the] EPA’s project manager for the Dico Site, reviewed and approved the 1997 Report.

On May 8, 1997, [the] EPA issued a notice of completion approving the 1997 Report and noting that “the continuing obligations” of the ... [1994 Building UAO] remained in effect....

Dico prepared and revised the [Operations and Maintenance Plan] [ (“]0 & M Plan[”) ] pursuant to [the] EPA’s directions in accordance with Paragraph 31 of the 1994 Building UAO, and submitted the revised 0 & M Plan to [the] EPA for approval on June 10, 1994.

[The] EPA approved the June 10, 1994 O & M Plan on February 5, 1997.

In December 2002, Dico wrote a letter to ... Peterson regarding proposed modifications to the OU1 groundwater treatment and monitoring system, and raised the possibility of modifying the O & M Plan applicable to the Dico Buildings. Dico and [the] EPA exchanged additional communications, including a draft work plan, regarding these modifications in subsequent months.

On July 2, 2003, Dan Buttars, on behalf of Dico, sent a letter to ... Peterson providing a revised “Work Plan for Proposed Modification of Des Moines TCE Site.” The July 2, 2003 revised Work Plan included a statement that Dico “has intentions of possible future demolition or dismantling of these buildings. No date of certainty can be given for this however.” [The] EPA and Dico exchanged additional letters in subsequent months.

• On September 3, 2003, [the] EPA wrote a letter to Dico in which it approved the modifications to the O & M Plan applicable to the Dico Buildings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Renn v. Otay Lakes Brewery, LLC
S.D. California, 2024
Zaitzeff v. City of Seattle
W.D. Washington, 2019
United States v. Dico, Inc.
920 F.3d 1174 (Eighth Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
4 F. Supp. 3d 1047, 2014 U.S. Dist. LEXIS 35761, 2014 WL 1046886, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-dico-inc-iasd-2014.