United States v. Deschutes Pine Timber Co.

35 F. Supp. 72, 1940 U.S. Dist. LEXIS 2468
CourtDistrict Court, W.D. Washington
DecidedApril 22, 1940
DocketNo. 20701
StatusPublished

This text of 35 F. Supp. 72 (United States v. Deschutes Pine Timber Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Deschutes Pine Timber Co., 35 F. Supp. 72, 1940 U.S. Dist. LEXIS 2468 (W.D. Wash. 1940).

Opinion

BOWEN, District Judge.

The plaintiff, United States of America, sues to recover from the defendant Deschutes Pine Timber Company the sum of $270,900.80 for breach by the defendant of á contract for the purchase of approximately 526,000,000 feet of timber on the Metolius Logging Unit of the Warm Springs Indian Reservation in Oregon. Of that sum plaintiff seeks to recover $40,000 only against defendant United States Fidelity & Guaranty Company on its surety bond given for the faithful performance by the other defendant of the purchase contract. The primary, or as called by counsel, “the master”, contract was entered into on January 22, 1923, between the Superintendent of the Warm Springs Agency on behalf of the Confederated Tribes and Bands of Middle Oregon, as seller, and the River Logging and Lumber Company (which later changed its name to Deschutes Pine Timber Company), as purchaser. The form and terms of the contract with the exception of the identity of parties and the location, kinds, amount and contract price of timber were in all material respects identical with the contract involved in the case of United States v. Harris, 9 Cir., 100 F.2d 268, to which reference is made for greater detail of the contract provisions. There were also made a part of this contract the same timber sale regulations which were involved in the Harris suit. Certain salient facts will later appear. Many of the questions in issue here were involved in the Harris case.

Some of the payments required by the contract in suit were made by the purchaser but the payments were usually delayed and in fact nearly all of the partial performance made by the purchaser was most desultory in character. With the exception of relatively short periods of time usually following immediately after extensions of time after partial payments were accepted by the Government, there was scarcely any time when this contract was not in default so far as the purchaser’s performance was concerned. Finally after repeated' defaults and long periods of default the Government undertook definite steps in 1931 to declare the contract terminated and succeeded in making all parties understand that the contract was cancelled as of March 21, 1931. After that, however, the Government delayed suit because of certain renewed efforts at rehabilitation of the contract by and on behalf of the purchaser and the defendant Surety Company. Some such action on behalf of the purchaser is indicated by a letter written March 19, 1931, by Henry Scattergood, Assistant Commissioner of Indian Affairs, to the Secretary of the Interior, in which the writer said among other things: “Subsequently this office notified Mr. J. P. Van Orsdell on February 19, 1931, who visited this Office for the Company, that if the cash payment of $30,000 was made, in payments of $5,000 immediately, $10,000 additional on or before March 21, and $15,000 on or before April 21, 1931, an extension of time until October 1, 1931 might be given the Company within which to begin construction of a sawmill and appurtenances necessary to the logging and milling of this timber.”

Those further negotiations and the indulgent attitude of the Government resulted in postponement of suit until August 1932 when the present action was finally commenced.

The question in this case of greatest concern to the court in determining the issue which is indispensable to the plaintiff’s maintaining this action turns on the breach of the contract and when the breach occurred. In view particularly of the Washington state authorities cited by counsel, it seems to me that a breach could have been claimed by the plaintiff, United States of America, on almost any day subsequent to that last extension of time and part payment which occurred in the year 1928. The Government was reluctant to take steps to terminate this contract or declare a breach of the contract. In view of all the circumstances, the court finds that the breach of this contract occurred before and not later than March. 21, 1931, which date was properly treated [74]*74as the performance dead line and cancellation date of the contract, and that the Government in undertaking to measure the damages as of that date was acting within the authority not only of the Washington state court cases cited by counsel but also within the authority of the case of Metropolitan Casualty Insurance Company v. United States, 87 F.2d 144, decided by the 9th Circuit Court of Appeals. That case is authority for the action of the Government in measuring the damages as of the date when the contract in suit was cancelled because here, as in the Metropolitan Casualty Insurance Company case, there was a continuing contract calling for further performance after date of cancellation. For that reason, computing the damages as of the date of cancellation, as was done in the estimate later to be discussed, does not under the rule of the Metropolitan Casualty Insurance case prejudice either of the defendants.

Before cancellation was finally made the Government had been exceedingly fair and indulgent in trying to avoid a termination of the contract with the hope that the defendant purchaser would some day be able to perform it. Prior to the 1928 modification there had been long and successive defaults, with different arrangements for modified performance and time extensions consented to by the surety. Subsequent to the 1928 modification, the purchaser continued in default against the repeated protests and without approval of the Government and in spite of its demands for performance by the purchaser. When the contract was finally cancelled the -defendant surety was still bound under its bond for the performance of the uncompleted contract. As stated in the quoted language in the Metropolitan Casualty Insurance case, supra, 87 F.2d 144, at page 146, “The rule as respects the time for computing value is not without flexibility where justice requires it.” Under all the circumstances here, and, as regards the surety, since the full penalty of the surety’s bond is far below the damages sustained by the plaintiff and computed as of the cancellation date, measuring the damages as of that date works no prejudice against the defendants.

The court is of the opinion and decides that this contract, as to what circumstance or occasion gives rise to the cause of action herein sued upon, is not materially different from other ordinary contracts. In contracts generally the breach of performance of them rather than the act of computing the damages is what gives rise to a cause of action for damages for failure to perform, and in that respect this case is not different from the ordinary one. It is true that here the contract calls for an estimate to be made by the • official who approved the contract, but that requirement was merely the means of determining the amount of recovery and was an incident following not creating the cause of action. The breach of the contract by the purchaser’s persistent failure to perform it created the cause of action and the making of an estimate of the remaining timber and its value was an incident that was to follow the breach of the contract in case the Government should sue upon the contract because of its breach. Defendants’ contention that a correct estimate made after the breach and within the coverage period of the performance bond was necessary to create a valid cause of action cannot prevail.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Harris
100 F.2d 268 (Ninth Circuit, 1938)
Metropolitan Casualty Ins. v. United States
87 F.2d 144 (Ninth Circuit, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
35 F. Supp. 72, 1940 U.S. Dist. LEXIS 2468, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-deschutes-pine-timber-co-wawd-1940.