United States v. Conservation Chemical Co.

681 F. Supp. 1394, 1988 U.S. Dist. LEXIS 2122, 1988 WL 21405
CourtDistrict Court, W.D. Missouri
DecidedFebruary 23, 1988
DocketCiv. 82-0983-CV-W-5
StatusPublished
Cited by5 cases

This text of 681 F. Supp. 1394 (United States v. Conservation Chemical Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Conservation Chemical Co., 681 F. Supp. 1394, 1988 U.S. Dist. LEXIS 2122, 1988 WL 21405 (W.D. Mo. 1988).

Opinion

MEMORANDUM OPINION AND ORDER

SCOTT O. WRIGHT, Chief Judge.

On November 23, 1987, a hearing was held to consider approval of the Consent Decree submitted on June 16, 1987 1 , by Armco, Inc. (“Armco”), AT & T Technologies, Inc. (“AT & T”), FMC Corporation (“FMC”), and International Business Machines Corporation (“IBM”) (collectively “Original Generator Defendants” or “OGDs”), and Defendants Conservation Chemical Company (“CCC”), Norman B. Hjersted (“Hjersted”), and Conservation Chemical Company of Illinois (“CCCI”) (collectively “CCC Defendants”), and Plaintiff United States (hereinafter “the United States”).

The hearing was conducted inter alia to allow presentation of evidence to support substitution of the hydraulic containment (“pump and treat”) remedy 2 contained in the proposed Consent Decree in lieu of the source isolation (“slurry wall”) remedy included in the Preliminary Agreement approved by the Court in 1985 as well as to determine whether such newly proposed remedial action was legal, fair and reasonable and otherwise in compliance with the National Contingency Plan. 3

For the reasons hereinafter stated, the Court finds that pursuant to Rule 42 of the Federal Rules of Civil Procedure, the hydraulic containment remedy should be substituted for the previously approved source isolation or “slurry wall” remedy, but that the Consent Decree as submitted must be further conditioned to assure that it is legal, fair, and reasonable and thus appropriate for final approval by the Court.

I. Background.

On May 25, 1985, the OGDs and the United States advised the Court that a settlement had been reached whereby the OGDs would implement a remedy at the Conservation Chemical Company Site (“CCC Site” or “Site”) and the United States would settle its claim for past response costs. The arrangement was set out in a document entitled “Preliminary Agreement,” and called for a remedy generally consisting of surface cleanup and a “cap,” flood protection for the Site, off-site ground water monitoring, a wall extending from bedrock under the Site to the surface “cap” completely encircling the Site, and an interior withdrawal well to prevent contaminants from leaking through the wall or underlying bedrock out of the contaminant area. 4

On August 2, 1985 the United States and OGDs filed the Preliminary Agreement with the Court. (A Supplement was filed August 29, 1985, and First and Second Amendments were subsequently made on December 24, 1985 and January 22, 1986, respectively). A Federal Register notice was thereafter published regarding the Preliminary Agreement, as amended, and public comment was invited.

On October 21, 1985, the Court conducted a hearing concerning the Preliminary Agreement and the suggested remedial action to cleanup the CCC Site. Based upon evidence and testimony received at the October 21, 1985 hearing, the Court found that the “slurry wall” remedy recommended in the Preliminary Agreement was legal, fair, and reasonable following the *1397 factors outlined in United States v. Seymour Recycling Corp., 554 F.Supp. 1334, 1337-1338 (S.D.Ind.1982). 5 On December 12,1985, the Court entered a Memorandum Order approving the “slurry wall” remedial action proposed in the Preliminary Agreement. See, United States v. Conservation Chem. Co., 628 F.Supp. 391 (W.D.Mo.1985). In its Order, the Court found that the source isolation or “slurry wall” remedial action was consistent with the National Contingency Plan (“NCP”), Section 107 of the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), 42 U.S.C. § 9607(a)(l)-(4)(B), 6 as amended by the Superfund Amendments and Reauthorization Act of 1986 (SARA) and directed the parties to prepare “forthwith” a Consent Decree incorporating the approved “slurry wall” remedy for subsequent consideration by the Court. 7

Following Court approval of the remedy proposed by the Preliminary Agreement, statements were made by counsel for the OGDs at hearings, in written motions and memoranda that unexpected and previously unknown geologic conditions and subsurface anomalies had been encountered at the CCC Site which cast some doubt upon the ultimate efficacy and appropriateness of the approved “slurry wall” remedy. The concern centered around the discovery that bedrock on the northwest side of the CCC Site extended down over one hundred (160) feet whereas the maximum depth anticipated had been approximately one hundred (100) feet. It was further suggested that unanticipated geologic conditions, including fractured bedrock with large voids, the existence of large boulders and cobble size materials, and increased permeability 8 might render the previously-approved “slurry wall” remedy unreasonable, 9 technically impossible or financially catastrophic.

The United States apparently disagreed with the OGDs’ statements concerning the technical feasibility of the “slurry wall” remedy and its overall implementability, and sought to compel performance of the “slurry wall” remedy by filing a “Motion to Enforce the Preliminary Agreement Between the United States and the Original Generator Defendants.”

*1398 After denial of the motion by the Court, 10 the United States continued discussions with the OGDs, and thereafter they agreed upon an alternative plan for remediation of the CCC Site based upon hydraulic containment. 11

On June 16, 1987, a Consent Decree, incorporating the hydraulic containment or “pump and treat” remedy, was submitted to the Court by the United States, OGD’s, and CCC Defendants. The proposed Consent Decree was offered to the Court in settlement of the litigation between the parties under Section 122 12 of CERCLA, 42 U.S.C. § 9622, as amended by SARA. 13

Because the Consent Decree contained a remedy different from that previously approved, the Court ordered the Special Master to conduct a hearing to review the proposed Consent Decree and to hear testimony regarding the feasibility of the hydraulic containment remedy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
681 F. Supp. 1394, 1988 U.S. Dist. LEXIS 2122, 1988 WL 21405, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-conservation-chemical-co-mowd-1988.