United States v. City of Niagara Falls

674 F. Supp. 1013, 26 ERC (BNA) 2140, 1987 U.S. Dist. LEXIS 11523, 1987 WL 23040
CourtDistrict Court, W.D. New York
DecidedDecember 7, 1987
DocketNo. CIV-81-363C
StatusPublished
Cited by1 cases

This text of 674 F. Supp. 1013 (United States v. City of Niagara Falls) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. City of Niagara Falls, 674 F. Supp. 1013, 26 ERC (BNA) 2140, 1987 U.S. Dist. LEXIS 11523, 1987 WL 23040 (W.D.N.Y. 1987).

Opinion

CURTIN, Chief Judge.

On June 10, 1987, this court approved a schedule proposed by the parties for the resolution of the dispute arising from the discharge of various chemicals from the Falls Street Tunnel in Niagara Falls, New York, into the Niagara River (Item 118); see also Item 130 (amending the June 10, 1987, schedule). Plaintiffs United States of America [United States] and the State of New York [the State] now argue that the defendant City of Niagara Falls [the City] is under a legal obligation to prevent these flows pursuant to the Clean Water Act, 33 U.S.C. § 1251, et seq., and its 1975 National Pollutant Discharge Elimination System permit [NPDES permit]. Plaintiffs say that because the City is presently in violation of its obligations, it is entitled to summary judgment. Defendant City and defendant-intervenor Industrial Liaison Committee of the Niagara Falls Area Chamber of Commerce [ILC] oppose.

The factual and procedural history of this case can be briefly summarized as follows. During the 1970s, it was determined that the Niagara Falls Wastewater Treatment Plant [WWTP] was discharging an unacceptably high amount of toxic pollutants into the Niagara River. Pursuant to the terms of the City’s 1975 NPDES permit, additional construction was required at the WWTP in order to make the plant capable of accomplishing chemical-physical treatment followed by carbon adsorption by December 31, 1976. Although this construction was actually not completed until 1978 and at considerable expense, the new carbon treatment system still failed to function properly. As a result, plaintiffs filed the instent lawsuit, alleging violations of the Clean Water Act and the City’s 1975 NPDES permit.

Subsequently, on January 19, 1984, the parties filed a proposed consent decree with the court [1984 Consent Decree] which required reconstruction of the WWTP’s faculty carbon adsorption system and the completion of other related projects to eliminate the unlawful discharge or diversion of untreated wastewater into the Niagara River (Item 16). That same day, this court issued an Interim Order requiring that all parties to comply with this decree until further notice (Item 15). The Interim Order remains in effect to date.

[1015]*1015As the United States outlines in its original papers on the question of the Falls Street Tunnel discharge (Item 97), the 1984 Consent Decree set deadlines for the completion of various phases of the construction. More specifically, plaintiffs required the City 1) to complete reconstruction of the 22 carbon bed adsorption system by March 1, 1985, and to commence operation two weeks later; 2) to complete construction and begin operation of the carbon regeneration system by July 27, 1984; and 3) to certify by January 31, 1986, that the WWTP had met all effluent limitations since July 31, 1985, and that the WWTP is capable of complying with all design plans and specifications as well as the City’s 1982 State Pollutant Discharge Elimination System permit [1982 SPDES permit]. In addition, the parties agreed that:

[f]or the first year of actual operation of the revised plant after July 31, 1985, the regeneration furnace shall be operated according to a schedule sufficient to insure that all of the carbon is regenerated at least twice and that no less than 22 contactors are on-line and operating at all times, and whenever possible, 24 con-tactors shall be so operated.

Item 16, 11VIII A. For present purposes, this shall be referred to as the “One-Year Test.”

As an initial measure, the parties also agreed that the flows to the then-overloaded WWTP should be reduced by completion of the Falls Street Tunnel Conversion Project by March 1, 1985. See 1984 Consent Decree, ¶ XI.A.1. The parties also agreed that the City would eliminate all known dry weather overflow discharges by January 1, 1985, except those from the Gorge Pump Station which would be eliminated by March 1,1985. The United States says that these measures were agreed to allow

the carbon adsorption system at the WWTP to operate within its hydraulic loading treatment capacity after rehabilitation in accordance with its original design specifications of 48 mgd [million gallons per day] on a dry weather basis, and to maximize the pollutant removal capacity of the plant by treating more concentrated wastewaters up to the plant’s hydraulic capacity.

Item 97, p. 7.

Upon stipulation of the parties, this court entered an order on or about July 9, 1985 [July 1985 Order], which effectively modified the 1984 Consent Decree (Item 42). At the request of the City and upon its representation that the flow of wastewater into the WWTP was as low as 32 mgd in dry weather, this order allowed the City some flexibility regarding the number of carbon beds that must be operating at a given time depending on the flow into the plant. In return for this flexibility, the City agreed, inter alia, to abide by the final effluent limitations and monitoring requirements of 1985 SPDES permit (see Item 96, Exh. B), and to have all 22 carbon beds available for on-line operation at all times. Plaintiffs also note that the City agreed to operate the plant to maximize the removal of pollutants. See July 1985 Order, 113.D.

As was stated above, the 1984 Consent Decree required construction of the Falls Street Tunnel Conversion Project by March, 1985. See Paragraph XI.A.1; see also Item 96, Exh. C-3 (“Report on Completion of Facilities Plan Flow Reduction 1981” by Camp, Dresser and McKee [1981 CDM Report], pp. 11-13-25). The purpose of this project was to remove all known connections of industrial, commercial, and sanitary wastewater into the Tunnel, and to permit the Tunnel to carry only groundwater. It was believed at the time that this groundwater carried approximately 17 pounds per day of toxic pollutants during dry weather. During wet weather, it was understood that the Tunnel would also carry excess stormwater as well as commercial, industrial, and extraneous overflows that were beyond the hydraulic treatment capacity of the WWTP.

As plaintiffs point out in their papers, it was originally agreed that the Falls Street Tunnel Conversion Project would include the use of “control gates” at the junction of the upper end of the Gorge Interceptor (1981 CDM Report, pp. II — 9) in order to [1016]*1016control the flow from the Falls Street Tunnel to both the Niagara River and the Gorge Interceptor, the latter of which channels wastewater to the Gorge Pump Station and, ultimately, the WWTP. Plaintiffs acknowledge that these gates would normally be remained closed to permit the discharge of groundwater directly into the Niagara River. However, plaintiffs say that it was understood by all parties that if treatment of stormwater and wastewater overflows was required in the future, the control gates could be opened. 1981 CDM Report, 11-23.

Plaintiffs note that the Falls Street Tunnel Conversion Project was eventually implemented without the use of these control gates. Instead, plaintiffs say that “the function to be served by the control gates was accomplished by the City through the provision of two orifices or apertures in the bulkhead that was constructed to separate the Tunnel and Gorge Interceptor.” Item 97, p. 11, citing Item 96, Exh. C-4,117, p. 3; Exh. C-5, 1117, p. 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. City of Niagara Falls
706 F. Supp. 1053 (W.D. New York, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
674 F. Supp. 1013, 26 ERC (BNA) 2140, 1987 U.S. Dist. LEXIS 11523, 1987 WL 23040, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-city-of-niagara-falls-nywd-1987.