United States v. Central Pac. R.

25 F. Cas. 354, 4 Sawy. 341, 1877 U.S. App. LEXIS 2041
CourtU.S. Circuit Court for the District of California
DecidedOctober 15, 1877
StatusPublished

This text of 25 F. Cas. 354 (United States v. Central Pac. R.) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Central Pac. R., 25 F. Cas. 354, 4 Sawy. 341, 1877 U.S. App. LEXIS 2041 (circtdca 1877).

Opinion

SAWYER, Circuit Judge

(after stating the facts). Upon the facts of the case as found and' stated, two questions have been raised and fully argued: (1) At what point of time was the road so fully completed as to make it obligatory upon the defendant to apply five per centum of the net earnings of the road to the payment of the bonds issued by [359]*359the government, and the interest thereon? (2) What constitutes net earnings-within the meaning of the act?

Upon the first question the government insists that the road was completed, and the obligation to set aside five per centum of the net earnings arose on July 15, 1869, the date of the provisional acceptance of the last section; while the defendant maintains that the road was not completed as a whole until October 1, 1874, the date at which the whole road was accepted by the president as having been fully completed.

The act of congress, and the acceptance by the defendant constitute a contract between the parties by the terms of which the defendant was required to build and complete such a road as is prescribed in the act—a road “supplied with all necessary drains, culverts, viaducts, crossings, sidings, bridges, turnouts, watering-places, depots, equipments, furniture, and all other appurtenances of a first-class railroad;” in other words, in all respects a first-class railroad, with all appropriate equipments and appurtenances. Such a road the defendant was bound to build and fully complete, and until so built and completed as a whole, it was not entitled to be discharged from the obligations of the contract to complete the road, or to receive the full consideration which the government, on its part, undertook to give. So, also, in addition to constructing the road, another obligation was imposed on defendant; for the act provides that “after the said road is completed, until said bonds (bonds issued by the government) and interest are paid, at least five per centum of the net earnings of said.road shall also be annually applied to the payment thereof.” And this is the clause under which this action is brought. It is plain that the point of time at which the defendant becomes liable to thus apply five per centum of the net earnings, is the point of time when it has fully completed the construction of the road as a whole, as an entirety, so that its contract is fully discharged so far as the construction is concerned, and the defendant has thereby become entitled to receive all the consideration therefor which the government undertook to give —the point of time when it becomes entitled to all the lands granted and all the bonds and other subsidies promised. The clause is “after said road is completed”—not a part or section, but said road. When the road is completed for the purpose of' casting the obligation upon defendant of applying five per centum of the net earnings of the road to the payment of the government bonds and interest, it is also completed for the purpose of entitling it to have the road accepted, and of exonerating it from any further liabilities for construction, and for the purpose of entitling it to receive all the lands and other aid given by the government. The construction of the statute as to the time when the road is completed, must be the same when it operates in favor of the defendant as when it operates in favor of the government. If the road was completed on July 15, 1869, so as tp make it the duty of the defendant to apply five per centum of its net earnings to the payment of the subsidy bonds and interest, it was completed for the purpose of exonerating the defendant from expending further sums in the construction of- the road, and for the purpose of entitling it to all the lands granted.

But the statute authorized the president, upon the report of commissioners appointed by him, to determine when the road should be deemed completed. Upon the completion of a section of forty, afterward twenty miles of road, the president of the United States was authorized by section 4 of the act “to appoint three commissioners to examine the same, and report to him in relation thereto; and if it shall appear to him that forty consecutive miles of said railroad and telegraph line have been completed.” etc., “patents shall issue conveying the right and title to said lands to said company,” etc. The commissioners were to report “to him”—the president—for his information, and if “it shail appear to him” that the section is completed, then the defendant is to be entitled to the corresponding part of the subsidy. This provision clearly devolves the duty upon the president of determining when the road is completed. This was so held by Mr. Attorney-General Evarts, in an elaborate opinion given to the president for his guidance in 1868, and I think correctly. 12 Op. Attys. Gen. 477. And this determination of the president I think conclusive, at least, upon the government. If so, it settles the question, for there can be no dispute as to what the action of the president and of the secretary of the interior, acting under his directions, actually was. The acceptance of sections from time to time, as constructed, was manifestly provisional—all the later ones being expressly so in terms upon their face. The whole action of the government is in harmony with this view, and utterly inconsistent with any other, as will be seen by a brief recapitulation of the facts, which speak for themselves. So early as September' 25. 1S68, the president appointed a commission of civil engineers to examine the entire road so far as then provisionally accepted, and to report wherein it was not completed up to the standard required by the statute. This commission made a thorough examination, and on May 20, 1869, which is subsequent to laying the connecting rail uniting the two roads, made a minute and exhaustive report, showing that it would require $4,493,3S0 to bring the five hundred and fifty-one miles of the provisionally completed road examined by them up to the required standard. Without waiting for the action of the commission, the secretary of the interior, on March 22, 1869. for the purpose of withholding the lands as security for the completion of the [360]*360road according to the statute, issued an order suspending the issue of all patents to lands due on completion of the road. At this time hut a small portion of the lands belonging to the sections provisionally completed had been patented to the defendant, so that this order, in fact, withheld nearly all the lands to which the defendant was entitled, provided the road was so far completed.

In April, also, congress authorized the appointment of another commission of eminent citizens to re-examine the road and report deficiencies, and in express terms authorized the president, as further security for the completion of the road, to withhold subsidy bonds, or require the delivery of first mortgage bonds, or the return of subsidy bonds already received, 'sufficient to insure a full performance of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Central Pacific Railroad
99 U.S. 449 (Supreme Court, 1879)

Cite This Page — Counsel Stack

Bluebook (online)
25 F. Cas. 354, 4 Sawy. 341, 1877 U.S. App. LEXIS 2041, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-central-pac-r-circtdca-1877.