United States v. Breymann
This text of 228 F. 808 (United States v. Breymann) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
The contract referred to was for dredging in Boston Harbor; and the work under it extended over a period of seven years. Until one-half the work was completed, Breymann was paid each month for only 90 per cent, of the work done during the preceding month, the United States reserving 10 per cent, against the final completion of the contract. (Specifications, clause 30.) After such completion, a final inspection and survey was made, and it was discovered, according to the allegations of the declaration, that Breymann had over-dredged to a very large amount and — construing the declaration according to the plaintiffs contention — had been paid for such over-dredging. By the terms of the contract overdredging was not to he paid for. The payments made to Breymann for it largely exceeded the amount reserved by the United States; and he was called upon to repay such a sum as, with the reserved amount, would equal the payments which had been made to him for overdredging. Upon his refusal to do so, this action was brought upon the bond.
As the obligation under the bond is, in substance, that Breymann should perform his contract, the plaintiff must establish that Brey-mann’s refusal to refund overpayments was a breach of the contract [810]*810That the United States may have a claim against him in the nature of an action for money had and received to recover payments made by it under a mistake of fact is not sufficient to entitle it to maintain action upon the bond. There is no clause in the contract by which Brey-mann expressly agreed to repay overpajunents, or to repay such sum, if any, as might be found due from him upon tire final accounting un- ■ der the contract, which, upon this point, says only:
“Deductions for dredging to a depth in excess of thirty-six (36) feet except as provided in paragraph 38, will be made at the rate of 1.2 cubic yards as measured in scows for every cubic yard estimated in situ from survey after dredging/
No fraud or misconduct on Breymann’s part in obtaining overpay-ments is alleged. Indeed, it is not charged that Breymann knew he was receiving money to which he was not entitled, nor is it stated that, in order to obtain the payments, Breymann made any assertion or representation that the material for which he was being paid had been taken from above the 36-foot line.
The contentions on the part of the United States are: (1) That Breymann had no right to go below 36 feet and broke the contract by doing so, that the overpayments were a natural result of that breach, and that the defendants, sureties on his bond, are therefore liable under it for the overpayments, as damages sustained by the United States through Breymann’s breach of contract; and (2) that the right of the United States to deduct for overdredging expressly given in the contract implies an actual agreement by the contractor to repay sums received by him for over dr edging.
Disregarding its provisions as to ledges, which do not figure in this controversy, the contract obliged Breymann to dredge to a depth of 35 ‘feet, entitled him to be paid for material dredged to a depth of 36 feet, and provided that for material taken from below that depth he should not be paid. * There is no clause' forbidding Breymann from dredging below 36 feet; and I do not think that any such prohibition can fairly be read into the contract. The over dredging did not, therefore, constitute a breach of the contract, and the contention based upon that assumption fails.
The contract itself was drawn by the United States; it is exact and stringent in its provisions. It expressly gave the United States “the right to recover from the” contractor in certain events. (Contract, clause 4.) The absence of such a provision in reference to possible overpayments is not without significance. The plaintiff had inspectors on the work. (Spec. Cl. 49.) It could, before making payment, have determined whether there had been overdredging. It did not do so, supposing, no doubt, that the reserved sums would be sufficient to meet any deductions on that account. It is one thing to guarantee performance of a contract by a contractor; it is quite a different thing to guarantee that he will refund money paid to him by mistake, years after the receipt of such money and the completion of the work. I do not think that the right to deduct reserved in the contract can, as against sureties on the bond to secure performance of the contract, fairly be enlarged into an agreement by the contractor to repay. His [811]*811failure to do so did not, therefore, constitute a breach either of his contract or of the bond.
Demurrer sustained, with leave to the plaintiff to amend for the purpose of assigning breaches of the bond, and so separating the claims made in the declaration that a proper order as to each can be made on the demurrer.
Free access — add to your briefcase to read the full text and ask questions with AI
Cite This Page — Counsel Stack
228 F. 808, 1915 U.S. Dist. LEXIS 1027, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-breymann-mad-1915.