United States v. Board of Education

126 F. Supp. 338, 1954 U.S. Dist. LEXIS 2473
CourtDistrict Court, D. North Dakota
DecidedDecember 8, 1954
DocketCiv. No. 2770
StatusPublished
Cited by6 cases

This text of 126 F. Supp. 338 (United States v. Board of Education) is published on Counsel Stack Legal Research, covering District Court, D. North Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Board of Education, 126 F. Supp. 338, 1954 U.S. Dist. LEXIS 2473 (D.N.D. 1954).

Opinion

VOGEL, Circuit Judge.

This action was brought by the United States to recover the sum of $1,330 advanced to the defendant by the Federal Works Agency pursuant to 50 U.S. C.A.Appendix, § 1671 for the purpose of planning an addition to the Richholt Grade School in Bismarck, North Dakota. After receiving the advance, the defendant, in August, 1945, contracted with Ritterbush Brothers, Architects, for the preparation of plans for the contemplated school addition. At the same time, the defendant held an election at which a bond issue in the amount of $75,-000 was approved.

Ritterbush Brothers proceeded in accordance with the agreement with the defendant and the plans were prepared in 1945. Nothing further was done until March 8,1949, when the defendant called for bids on the proposed plans. All bids received were rejected on April 16, 1949, as being greatly in excess of the amount approved for the project. The lowest bid covering construction of the building so planned approximated $258,-000.

Immediately after the rejection of the bids covering the construction proposed by the first set of plans, the defendant re-employed Ritterbush Brothers to prepare a new set of plans referred to herein as the second set of plans. Bids covering construction of a building proposed in the second set of plans were called for, bids were accepted on July 12, 1949, contracts were awarded' and the building was constructed. Ritterbush Brothers were paid $5,127 by the defendant for the preparation of the second set of plans. Previously, in 1945, they had received from the defendant as partial payment for the first set of plans $1,330, the amount advanced by the United States. The balance of their charges has not as yet been paid to them by the defendant, although the defendant admits liability therefor.

The statute under which the advance from the plaintiff to defendant was made, 50 U.S.C.A.Appendix, § 1671, provided in subsection (c) that such advances

“shall be repaid by such agency if and when the construction of the public works so planned is undertaken.”

The plaintiff’s theory is that construction of “the public works so planned” [340]*340was undertaken when construction under ■the second set of plans was commenced, whereas the defendant contends that “the public works so planned” for which the advance was made was abandoned when the bids on the first set of plans were rejected, and that the addition to the Richholt School as built under the second set of plans was an entirely new or different project. Thus, the question for determination is whether the phrase “the public works so planned”, as used in the statute, is broad enough in scope to include the building constructed by the .defendant under the second set of plans. No cases arising under the statute involved have been cited by counsel or have been found and accordingly the Court is without precedent in attempting to determine the issue. Counsel for both parties have nevertheless ably presented their views on the question.

The Congressional purpose in enacting 50 U.S.C.A.Appendix, § 1671 was stated in subsection (a) as being:

“ * * * to encourage States and other non-Federal public agencies to make advance provision for the construction of public works” and
“ * * * to aid in financing the cost of architectural, engineering, and economic investigations and studies, surveys, designs, plans, working drawings, specifications, procedures, and other action preliminary to the construction of such public works * * *.”

The defendant’s argument centers around the idea that an entirely new set of plans was used as the basis of the building and that no benefit or very little benefit was derived from the first set of plans by the architects in preparing the second set. It argues that “work as planned” cannot simply mean an addition to the Riehholt School but can mean only the building which would result from a contractor following a set of plans and specifications prepared by an architect. It claims that the benefit, if any, carrying over from the first set of plans was a normal concomitant in , an . architect’s business, since' material gathered in planning one school may normally be used in another school plan. Defendant’s main line .of defense is that the “public works so planned” was abandoned on April 16, 1949, when all bids on the first set of plans were rejected and that since the building constructed was from an entirely new set of plans, it is not obligated to repay the advance.

The defendant also argues that plaintiff’s complaint alleges only “that on or about October 12, 1949, the defendant commenced construction of a building substantially similar to the one for the planning of which was paid with the advance received from the United States, and said building has now been completed.” (Emphasis supplied.) It argues that the complaint does not allege that defendant built the public works so planned nor the specific public works so planned. Defendant’s counsel was of the opinion that the complaint did not state a cause of action under the statute and moved for a dismissal. At the time the motion was made, the Court reserved its ruling. That motion will now be denied.

In support of its contention that the building constructed from the second set of plans is not “the public works so planned”, the defendant relies upon the uneontradicted testimony of Robert A. Ritterbush, one of the architects who prepared both sets of plans. This case was tried to the Court some time ago and counsel have not furnished a transcript of the testimony. Accordingly, the Court must rely upon its own memory as stimulated by its notes.

Ritterbush, who was, of course, testifying as an expert, stated in substance that the building represented by the first set of plans was not built; that the building represented by the second set of plans was built; that the second set of plans did not call for the same construction as the first set; that he was unable to use the computations of the first set of plans in preparing the second set; and that in preparing the second set of plans he had to start all over again. He stated in substance that the only simi[341]*341larity between the first and second sets of plans was that both provided for brick buildings, similar concrete mix, and, of course, that they were both school buildings. He testified that he did not use any of the preliminary work obtained in preparing the second set of plans, although he admitted that he referred to the first set of plans and to other sets of school building plans in his office when he prepared the second set.

It is obvious that the building constructed from the second set of plans is not the same building as provided for in the first set of plans. The lowest bid on the first set of plans represented a construction cost of approximately $258,000. The bids which were accepted on the second set of plans totalled $113,933. The rejected bids on the first set of plans were made in April, 1949. The accepted bids on plan No. 2 were made in July of the same year, so it seems obvious that the building constructed is not the same building as provided for in the first set of plans.

To the Court’s mind, however, that is not determinative. The statute under which this litigation arises provides for loans or advances “to aid in financing the cost of architectural, engineering, and economic investigations and studies, surveys, designs, plans, working drawings, specifications, procedures, and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. CITY OF LEESVILLE, LOUISIANA
389 F. Supp. 943 (W.D. Louisiana, 1975)
United States v. City of Rossville
249 F. Supp. 701 (N.D. Georgia, 1966)
United States v. City of Willis, Texas
164 F. Supp. 324 (S.D. Texas, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
126 F. Supp. 338, 1954 U.S. Dist. LEXIS 2473, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-board-of-education-ndd-1954.