United States v. Bethlehem Steel Co.

302 F. Supp. 600, 1969 U.S. Dist. LEXIS 10693
CourtDistrict Court, D. Maryland
DecidedJuly 31, 1969
DocketAdm. No. 4599
StatusPublished
Cited by1 cases

This text of 302 F. Supp. 600 (United States v. Bethlehem Steel Co.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Bethlehem Steel Co., 302 F. Supp. 600, 1969 U.S. Dist. LEXIS 10693 (D. Md. 1969).

Opinion

THOMSEN, Chief Judge.

The judicial history and background of this case may be found in opinions reported in 235 F.Supp. 569 (D.Md.1964), 374 F.2d 656 (4 Cir. 1967), 389 U.S. 575, 88 S.Ct. 689, 19 L.Ed.2d 775 (1968), and 409 F.2d 961 (4 Cir. 1969), the first and third sub nom. United States v. Bethlehem Steel Co. et al., the second and fourth sub nom. United States v. Moran Towing & Transp. Co., et al.

In its recent decision, 409 F.2d 961, the Fourth Circuit vacated the earlier findings and remanded the case for further proceedings consistent with the majority opinion there reported and the Supreme Court’s remand — in essence, directing this Court to receive such additional evidence as either side might wish to offer, and to make findings of fact and conclusions of law on the issues of negligence and proximate cause upon the existing record and such new evidence.

Pursuant thereto, this Court has held an additional hearing, at which both the government and Bethlehem offered evidence, and counsel have presented their arguments. The government conceded that it had proved no case against Moran, and judgment will be entered for that defendant.

All of the previous findings of fact have been reexamined. The present findings are based upon the agreed facts, the transcript of testimony and the exhibits offered at the previous trial, and the testimony and exhibits offered at the recent hearing. In making the findings set out below, the Court has considered the credibility of the several witnesses, in accordance with accepted principles.

The dry dock was built in 1917 by Crandall Engineering Company. It was of wooden construction 360 feet long, had a capacity of 9,400 tons, and was composed of six trussed sections connected by steel pins. Each section was shaped thus — ■ 0=0 —with its sidewalls rising at right angles from its pontoon, and the outside of each sidewall running down to the bottom of the pontoon. The pontoon of each section had a centerline bulkhead and a transverse bulkhead, forming four compartments in each pontoon.

Bethlehem purchased the dock in 1930, and it was then towed from Charleston, S. C„ to Bethlehem’s Key Highway Yard in Baltimore. Each section of the dock was towed separately.

The six sections comprising the dry dock at the time of the casualty are referred to as Nos. 1, 2, 3, 4, 5, and 7. An additional section had been inserted between the No. 5 and No. 7 sections in 1950, but was removed before the tow. In some of the testimony and exhibits the No. 7 section is referred to as No. 6. The No. 6 section which was added and removed before the tow has no importance in this case. No. 1 was the nearest section to the shore when the dock was in operation. No. 7 was the foremost section during the trip down the river and the bay on October 17-18, 1962, with which we are concerned in this case; No. 1 was the foremost section on the trip back up the bay.

The dry dock itself was last dry-docked for inspection and maintenance in 1949. [602]*602The seams were either rewedged or the existing wedges were driven up. The pontoon timbers were found to be in excellent condition and no renewals were required. Thereafter, the dry dock was in substantially continuous use by Bethlehem until October 4, 1962. During 1949 and 1950 Bethlehem equipped each of the six sections with wooden sponsons or blisters to add stability.

Inspections were made in 1956 and 1961 to determine the lifting capacity of the dock. In 1956 each of the pontoons, including the interior portion, was inspected. The 1956 report stated that the structural timber framing and planking was sound and in good condition. In 1961 the inspectors entered only the pontoons of the N(o. 1, No. 3 and No. 6 sections. Excessive leaking was found in the No. 1 pontoon, which was repaired. Otherwise, the framing and planking in the pontoons which were inspected were found to be sound and in good condition.

During 1962 Bethlehem decided to replace the 9,400 ton dock at the Key Highway Yard with a 20,000 ton dock from New York. Having no use for the 9,400 ton dock and being unwilling to sell it to a competitor, Bethlehem considered how to dispose of it. Bethlehem contemplated beaching the dry dock and burning it, but the landowners it contacted were unwilling to have their properties used for that purpose. An inquiry was addressed to the Maryland Port Authority, which declined to approve sinking the dock anywhere in the Chesapeake Bay, but, after suggesting the possibility of beaching and burning it, mentioned that it might be sunk at sea. Bethlehem decided that the cheapest way to dispose of the 9,400 ton dock would be to have it towed as a unit out of Baltimore Harbor, down the Chesapeake Bay, through the Capes, and out to sea, so that it could be sunk beyond the 1,000 fathom curve.

Bethlehem contracted with Moran to tow the dry dock to a point beyond the 1,000 fathom curve, at a total cost to Bethlehem of some $10,000. Moran undertook the contract upon Bethlehem’s assurance that the dry dock was fit for the tow and on the condition that Bethlehem would indemnify Moran against any liability arising out of the unseaworthiness of the tow.

Moran and Bethlehem arranged that the operation would be begun on or about October 17, 1962, provided weather conditions in the Bay were favorable.

Prior to the tow, Bethlehem removed all keel and bilge blocks and other equipment, and disconnected the 24 pumps on the dry dock, each of which had a capacity of 4,000 gallons per minute, but which were inoperable without shore power. Four openings, each approximately one foot square, were cut in the deck of each pontoon, one in each of the water-tight compartments, for the insertion of portable pump suction hose. Bethlehem placed aboard the dry dock three portable gasoline pumps, each of which had a capacity of 250 gallons per minute.

During the period between the last use of the 9,400 ton dock on October 4 and October 11, while the dock remained moored at the Key Highway Yard, Bethlehem conducted a test of the leaking in the pontoons, but found no leakage beyond the customary leakage or seepage, which could be handled by one pump. No one went into the pontoons to examine the condition of the boards and the wedges,1 and to determine whether or not there were any conditions which might cause trouble during a towing operation. Particularly, no one remembered that a 12 inch by 12 inch opening in each pontoon (which had originally provided a pumping outlet shown on blue prints then available) had been plugged by two wooden blocks, which were covered by non-watertight sheathing on the outside and by mud and silt on the inside, without other support. No one checked to see whether those blocks were firmly in [603]*603place, able to withstand the particular stresses, tensions and strains involved in a towing operation.

No one examined the sides or bottom of the pontoons below the waterline.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Chesapeake & Delaware Shipyard, Inc.
369 F. Supp. 714 (D. Maryland, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
302 F. Supp. 600, 1969 U.S. Dist. LEXIS 10693, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-bethlehem-steel-co-mdd-1969.