United States v. Baker

50 F.2d 22, 1931 U.S. App. LEXIS 4397
Court of Appeals for the Ninth Circuit·Decided May 18, 1931·No. No. 6250·Published

Opinion

SAWTELLE, Circuit Judge.

This is an appeal by the United States of America from a judgment entered against them in favor of appellees in the sum of $3,874.98, with interest from date until paid, in an action brought by appellees to recover moneys they claimed to be due them from appellant for additional work, labor, and material rendered and furnished by appellees to appellant under or in connection with a written contract between them entered into on September 23, 1927, which provided, among other things, for the construction of approximately 17,867 linear feet of masonry guard rail, or guard rail wall, between stations 0-j-00 and 359-f-00 on route 1-A, Yosemite National Park, Cal., for which the contractors were to be paid on the basis of $12.75 per cubic yard. The amount of said judgment was made up of two items: First, in the sum of $1,128.32, represented extra cost of furnishing 1,640 linear feet of granite, but the government does not hear complam of the allowance of said sum as a part of the judgment; second, in the sum of $2,746.66, represented the amount of extra cost of a change which, as the complaint alleged and the court found, was made by the government in the plans for the construction of said guard rail as originally provided for in the written contraei Upon the allowance by the trial court of the amount represented by said second item, the main controversy on this appeal arises.

To the allegations of appellees’ complaint appellant interposed an answer consisting of a general denial of each and all of said allegations. On the trial, at the close of appel-lees’ evidence, counsel for appellant, stating that the defense did not care to offer any evidence, moved for judgment on all of the issues in favor of the government; the principal ground being that a prima facie ease had not been proved. The court denied said motion, and, upon motion of appellees’ counsel therefor, rendered its order for judgment for appellant on special findings. Touching the controverted second item, the trial court found as follows:

“IV. That plaintiffs were required to ■construct 3,829 linear feet of additional wall not contemplated in the written contract aforesaid.
“That it was contemplated hy the terms and provisions of the said written contract that said guard rail wall was to be carried, below the surface of the pavement, to an average depth of one foot for the entire length of the wall. That after the commencing of said work, a change in the depth of this wall was ordered by defendant’s authorized representative, making its average depth approximately six inches beneath the surface of the pavement for the entire length of the wall. That this change in the plans materially increased the costs per cubic yard of constructing said masonry guard rail, as masonry which was substituted in the upper part of the wall for masonry laid in the footings of the wall was more expensive to construct, a. * * ip^at plaintiffs are entitled to additional compensation therefor in the sum of $2,746.66.”

The principal errors assigned by appellant are that the trial court erred in making said finding No. IV and in not finding that the guard rail or wall, as built, was carried in every instance to the depth contemplated by the written agreement and that no change, by operation of law or otherwise, in plans or specifications thereof in reference to the required depth of said wall, was made by appellant or any of its agents, and that the trial court erred in making its conclusion of law that appellees are entitled to interest on the principal amount of the judgment.

From the record it appears that the written contract referred to was entered into upon the acceptance by the government of a bid theretofore submitted by appellees in compliance with the government’s invitation for bids. The terms of appellees’ bid proposed to furnish all labor and materials and perform all work required for constructing said masonry guard rail “in strict accordance with the specifications, schedules and drawings, for the consideration of the unit prices shown in the Bid Schedule.” Accompanying said bid was a “bid proposal” covering four items, one of which was as follows: “No. 69.” “Approximate Quantity, 3,400 Cu. Yds. Masonry Guard Rail at $12.75 per eu. yd., $43,500.” Said contract provided, among other things, in article 1, that the contractor should furnish all labor and materials and perform all work required for the construction of said masonry guard rail, between the stations previously specified herein, “in strict accordance with the specifications, schedules and di*awings, all of which are made a part hereof and designated as follows : Plans of the work consisting of * * * two sheets of typical section for masonry guard rail. * * * Specifications for Forest Road Construction, F. R. 50, Revised 1927. Special Provisions, Unit prices carried by the bid.”

In said “Special Provisions” it was among other things provided, in substancé, that said [24]*24guard rail should be constructed, at places where directed by the engineer, who in the specifications for Forest Road construction was designated as the authorized representative of the contracting officer signing the contract on behalf of the government, “in conformity with the designs for type No. 1, See. A, as shown on the sheet of typical sections excepting at places where directed by the Engineer the alternate type composed of an upper section of approved stones laid in mortar and a foundation section of Class B concrete constructed in accordance with the alternate design for type No. 1, Sec. B, may be required. * * * The total length to be constructed is approximately 17,867 lin. ■J^. * • *»

One of the two sheets of typical sections above referred to, and which are attached to the contract, is designated “Type 1 — See. A. Typical Masonry Guard Rail,” and depicts the foot of said guard rail as extending below the contiguous ground surface “To Solid Footing.” The other sheet, designated “Type 1 — See. B. Typical Masonry Guard Rail (Alternate Design Using Concrete Base),” delineates the foot of such rail as extending below the contiguous ground surface to contact with a base, designated “Class ‘B’ Concrete,” resting upon a portion of the subsurface which is designated “To Solid Footing.” On neither of said typical section sheets is there shown the depth to which it was contemplated the guard rail was to extend below the surface. On the trial plaintiffs admitted that such depth is not shown and cannot be determined from the sheet entitled “Type 1 — Sec. A.” The guard rail was built and completed throughout in conformity with said “Type 1 — See. A,” and appellees do not claim that any change of plan occurred by reason of any direction or requirement of the engineer that any portion of the guard rail be constructed in accordance with the “alternate design Type 1 — See. B.” While the above-quoted portion of the special provisions specifies the approximate linear footage that was contemplated by the government at the time the contract was entered into, it is clear from provisions of the contract, hereinafter referred to, which reserved to the government the right to increase the quantities of the work to be performed, or to increase the length of the project, that the specification in the contract of the approximate linear footage was not final, but was subject to increase, at the option or election of the government. As regards any amount of cubic yardage that might be involved in the performance of the contract work, the contract did not specify the total amount of such yardage, approximate or otherwise, which it was contemplated the guard rail would contain.

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. Baker, 50 F.2d 22, 1931 U.S. App. LEXIS 4397 (9th Cir. 1931).

50 F.2d 22 (United States v. Baker) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Harvey v. United States
113 U.S. 243 (Supreme Court, 1885)
United States Ex Rel. Angarica v. Bayard
127 U.S. 251 (Supreme Court, 1888)
United States v. North Carolina
136 U.S. 211 (Supreme Court, 1890)
United States v. Rogers
255 U.S. 163 (Supreme Court, 1921)
Seaboard Air Line Railway Co. v. United States
261 U.S. 299 (Supreme Court, 1923)
Boston Sand and Gravel Co. v. United States
278 U.S. 41 (Supreme Court, 1928)