United States v. Bailey

467 F. Supp. 925, 12 ERC 1955, 12 ERC (BNA) 1955, 1979 U.S. Dist. LEXIS 13765
CourtDistrict Court, E.D. Arkansas
DecidedMarch 14, 1979
DocketLR-C-77-240
StatusPublished
Cited by5 cases

This text of 467 F. Supp. 925 (United States v. Bailey) is published on Counsel Stack Legal Research, covering District Court, E.D. Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Bailey, 467 F. Supp. 925, 12 ERC 1955, 12 ERC (BNA) 1955, 1979 U.S. Dist. LEXIS 13765 (E.D. Ark. 1979).

Opinion

MEMORANDUM OPINION

EISELE, Chief Judge.

This case was brought by the United States seeking injunctive relief against the owners of a marina on the Arkansas River at Little Rock, who were alleged to have constructed and maintained a breakwater dike in the navigable waters of the United States in violation of the Corps of Engineers permit, pursuant to 33 U.S.C. § 403, under which the construction of the dike was authorized. For the reasons set forth below, the United States is denied all relief sought and the case is dismissed.

The gravamen of plaintiff’s action is defendants’ failure to restrict the height of their dike to elevation 235 feet above mean sea level, that height being noted on the permit as the height of the proposed dike. The government contends that strict adherence to permit conditions is necessary to guard against the deleterious effects of cumulative but relatively insignificant incursions on these interests in navigable waters that the Corps of Engineers is charged with protecting. Defendants basically reply that the “height restriction” in the permit was never understood as such and that the Corps of Engineers, having tacitly, if not explicitly, “approved” the structure when it was built (at a height over 235 feet), is estopped to assert, after several years, non-compliance with the permit, especially because the “offending” part of the dike has no substantial or cognizable *926 effect on any of the Corps’ legitimate concerns with the navigable waters.

Defendants at the outset of this case contended that the Corps was without jurisdiction to require a permit, and impose conditions thereby, for the construction and maintenance of the marina dike because the foundation of the dike was alleged to have been built above the “ordinary high water mark” on certain accretions near the river’s edge. Defendants maintain that the scope of the Corps’ authority to require permits under section 403 for such construction activity corresponds to the scope of the United States’ navigational servitude, and that therefore the relevant inquiry in this case, jurisdictionally, would be the location of the ordinary or mean high water mark of the Arkansas River at the location in question. See generally United States v. Rands, 389 U.S. 121, 123, 88 S.Ct. 265, 19 L.Ed.2d 329 (1967).

Section 403 provides in pertinent part: “The creation of any obstruction not affirmatively authorized by Congress, to the navigable capacity of any of the waters of the United States is prohibited; and it shall not be lawful to build or commence the building of any . breakwater, bulkhead, jetty, or other structures in any . . . navigable river . . . outside established harbor lines, or where no harbor lines have been established, except on plans recommended by the Chief of Engineers and authorized by the Secretary of the Army; and it shall not be lawful to fill . . . the channel of any navigable water of the United States, unless the work has been recommended by the Chief of Engineers and authorized by the Secretary of the Army prior to beginning the same.”

The Court concludes that the scope of the Corps of Engineers’ authority under section 403 to regulate certain physical activities is not limited to those activities occurring or existing below the ordinary high water mark. In this case, the artificial raising of the ordinary water level of the Arkansas River by means of a series of locks and dams means that, naturally enough, the normal waters of the river cover much land that, with the river in its “natural” state, would be above the otherwise ordinary high water mark. Leaving this fact aside, however, the better reasoning is that, in any event, the Corps’ authority under the second and third clauses of section 403 extends to the permitting of any of the named activities 1 the operational effect of which is, generally speaking, to create obstructions to navigable capacity, regardless of whether the physical location of the activity, in the main, is above the ordinary high water mark. See United States v. Perma Paving Co., 332 F.2d 754, 757 (2d Cir. 1964); United States v. Cannon, 363 F.Supp. 1045, 1051 (D.Del.1973); Sierra Club v. Morton, 400 F.Supp. 610, 628-30 (N.D.Cal.1975); United States v. Sexton Cove Estates, Inc., 526 F.2d 1293, 1298-1300 (5th Cir. 1976). Cf. Leslie Salt Co. v. Froehlke, 578 F.2d 742, 750 (9th Cir. 1978). 2 The Court need not decide whether a conclusion that a particular activity above the high water mark does not create any obstruction to the navigable capacity of the river in turn divests the Corps of its permitting authority over that activity, since the reasonable conclusion that such an activity could, if not properly regulated, have an effect on the navigable capacity provides a sufficient basis upon which to assert permitting authority under *927 section 403. 3 In this case, the Corps reasonably concluded that the dike in question could have such an effect.

Whatever the proper factors may be to allow the Corps to conclude that a particular permit condition is necessary to safeguard against impermissible “obstructions to navigable capability,” the Court is convinced that those factors are not present in this case, that the Corps is indeed estopped to assert a height violation of the permit in question, and that the Corps acted arbitrarily, capriciously, and abused its discretion in denying to defendants an after-the-fact permit or a modification of the extant permit incorporating the present height of the dike.

The essential findings of fact in this case are as follows:

1. The Baileys decided in late 1965 or early 1966 to construct dikes to form an embayment for the purpose of establishing their marina. They knew that the Arkansas River navigation project would raise the elevation of the river sometime in the fall of 1968. It was therefore the defendant’s intention to complete their dike construction just before the elevation of the river was raised.

2. The dike has two portions, one extending from the bank perpendicularly into the river and the other extending from the end of the first part, paralleling the river bank. The dike was constructed for the most part upon accretions which had been established for several years.

3. The defendants applied for and received a permit in September, 1966, for the construction of the dike. At the time, the Corps of Engineers was encouraging the establishment of such facilities, and the formal requirements for submissions in support of applications were very few. The defendants did not employ experts to assist them in preparing their submissions and drawings.

4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. CPS Chemical Co., Inc.
779 F. Supp. 437 (E.D. Arkansas, 1991)
Dempsey v. Director, Federal Emergency Management Agency
549 F. Supp. 1334 (E.D. Arkansas, 1982)
United States v. Martin
517 F. Supp. 211 (D. South Carolina, 1981)
Hart and Miller Islands Area Environmental Group, Inc., a Maryland Corporation Honorable Clarence Long, M.C. Honorable Norman R. Stone Maryland Wildlife Federation, Inc., a Maryland Corporation John Henderson Howard Sappington George Wohlleben Robert Scott Margaret Caldwell Charles Justice v. The Corps of Engineers of the United States Army Honorable Clifford L. Alexander, Secretary of the Army Lt. General John W. Morris, Chief of Engineers of the United States Army Col. G. K. Withers, District Engineer, Baltimore District, United States Army Corps of Engineers, and State of Maryland, Ex Rel., Francis B. Burch, Attorney General, and Steamship Trade Association of Baltimore, Inc., Intervening Hart and Miller Islands Area Environmental Group, Inc., a Maryland Corporation Honorable Clarence Long, M.C. Honorable Norman R. Stone Maryland Wildlife Federation, Inc., a Maryland Corporation John Henderson Howard Sappington George Wohlleben Robert Scott Margaret Caldwell Charles Justice v. The Corps of Engineers of the United States Army Honorable Clifford L. Alexander, Secretary of the Army Lt. General John W. Morris, Chief of Engineers of the United States Army Col. G. K. Withers, District Engineer, Baltimore District, United States Army Corps of Engineers, and State of Maryland, Ex Rel., Francis B. Burch, Attorney General, Intervening and Steamship Trade Association of Baltimore, Inc., Hart and Miller Islands Area Environmental Group, Inc., a Maryland Corporation Honorable Clarence Long, M.C. Honorable Norman R. Stone Maryland Wildlife Federation, Inc., a Maryland Corporation John Henderson Howard Sappington George Wohlleben Robert Scott Margaret Caldwell Charles Justice v. The Corps of Engineers of the United States Army Honorable Clifford L. Alexander, Secretary of the Army Lt. General John W. Morris, Chief of Engineers of the United States Army Col. G. K. Withers, District Engineer, Baltimore District, United States Army Corps of Engineers, and State of Maryland, Ex Rel., Francis B. Burch, Attorney General, Steamship Trade Association of Baltimore, Inc., Intervening
621 F.2d 1281 (Fourth Circuit, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
467 F. Supp. 925, 12 ERC 1955, 12 ERC (BNA) 1955, 1979 U.S. Dist. LEXIS 13765, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-bailey-ared-1979.