United States v. Ashcraft-Wilkinson Co.

18 F.2d 977, 1927 U.S. Dist. LEXIS 1111, 1927 A.M.C. 872
CourtDistrict Court, N.D. Georgia
DecidedApril 28, 1927
DocketNo. 908
StatusPublished
Cited by4 cases

This text of 18 F.2d 977 (United States v. Ashcraft-Wilkinson Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Ashcraft-Wilkinson Co., 18 F.2d 977, 1927 U.S. Dist. LEXIS 1111, 1927 A.M.C. 872 (N.D. Ga. 1927).

Opinion

SIBLEY, District Judge.

This is a libel in personam, brought by the United States, as owner of the steamship Vittorio Emmanuele III, against Asheraft-Wilkinson Company, recipients of the cargo, to collect demur-rage for delay in discharging the ship. I find the material facts to be as follows:

In the fall of 1919, Asheraft-Wilkinson Company contracted to buy of a German syndicate a cargo of fertilizer salts, to be delivered in Savannah, Ga., free of freight, insurance, and other costs. To carry out the sale, J. H. Bachmann, of Bremen, chartered the steamer Vittorio Emmanuele III, under a charter party dated January 27, 1920, exhibited in the libel, and had the fertilizer salts duly loaded upon her. Bills of lading for the cargo were issued by the master about February 10, 1920, by which he engaged to deliver the cargo at Savannah, under certain terms and conditions, unto the order of National City Bank of New York, freight to be paid by consignee at the stated rate, “all other conditions and exemptions as per charter party dated Bremen, January 27, 1920.” The ship arrived at Savannah on March 2, 1920, passed quarantine and customs, and moored alongside another vessel, and while so moored, and about 1:50 p. m., gave notice of readiness to deliver. The shipowners had Tresdale, Plant & La Fonta representing them at Savannah, and the charterers had arranged with Straehan Shipping Company to represent them and the cargo.

Because of disturbed communications with Germany subsequent to the war, the bills of lading, with copy of charter party and insurance papers, had not reached Asheraft-Wilkinson Company. These papers, in-fact, were not indorsed over to them by Na[978]*978tional City Bank until March 10th or 11th, and were first seen by them about March 13th. The arrival of the ship, however, was communicated to them at once by Straehan Shipping Company, and Ashcraft-Wilkinson Company arranged with Central of Georgia Railroad Company to receive delivery, for them. Ashcraft-Wilkinson Company did not employ or pay Straehan Shipping Company to act for them, and recognized them only as representatives of the sellers of the fertilizers making delivery, though they kept in touch, through them, with the progress of the discharge of the ship, and approved finally all that Straehan Shipping Company had done thereabout. Notice of the berth to be occupied by the ship was given her apparently on the afternoon of March 2d, and at 8 a. m. on March 3d she was alongside the wharf, actually ready to discharge, and discharge was then begun. Smith and Kelly, the only stevedoring firm at Savannah at the time, were employed on the ship, working supposedly from 8 a. m. to 6 p. m., with one hour for dinner, as was customary at the port.

The vessel had five hatches, each equipped with two winches, but it was found impossible, owing to insufficient supply of steam to them, to work more than three hatches at a time, and the stevedores actually employed but two gangs much of the time, and only three at any time. Because the winches worked slowly, the number of' men in these gangs was reduced one-third. The different winches, moreover, broke down repeatedly, so that much delay occurred in shifting gangs to other hatches and in suspension of work for winch repairs. No full and reliable record exists of the aetual loss of time, but the stevedores’ daily record shows a very poor delivery from most of the hatches on most of the days, and the evidence suggests indifference of the master and stevedores. Other delays were occasioned by the failure of the Central of Georgia Railroad Company at times to promptly handle cars away from the wharf. The ship and the stevedores did not refuse, on demand, to work at night, nor did they tender any such work; but Straehan Shipping Company did, on March 8th, attempt to get the Central of Georgia Railroad Company to receive cargo at night, and it declined to do so. The discharge was completed at 1:50 p. m. March 13, 1920. On March 4th work was interrupted by rain, and that is to be counted as a half day only. Saturday, March 7th, was, by custom of the port, a half holiday, and to be counted as only a half working day. Sunday, March 8th, was not a working day, and is to be excluded.

Though the master had a copy of the charter party, its contents were actually unknown to Ashcraft-Wilkinson Company until the dispute about the demurrage arose. Before the World War fertilizer cargos had usually moved under charter parties of the same general form as that used here, but providing a rate of‘discharge of only 300 tons daily, and a rate of demurrage of only 8 pence sterling per ton net register, instead of 550 tons discharge, with a rate of $1 per ton net register. The ship Vittorio Emmanuels III was the first, or among the first, ships to bring such a cargo into Savannah after the war, and Ashcraft-Wilkinson Company supposed the provisions as to discharge •that were formerly used would apply, and made no inquiry thereabout. They paid the freight, deducting it from the purchase price due sellers on the bills of lading, but refused to pay demurrage. Effort was made by the United States to collect demurrage on a libel against the cargo, but it was held that the lien had been lost by delivery. After fruitless negotiations, this libel in personam was filed March 3, 1923.

The main questions to be decided are: (1) Are respondents liable in personam for demurrage without an express agreement to be bound? (2) If so, are they bound by the provisions of the charter party touching it, and are those provisions enforceable or a mere penalty? (3) If liable, for what time and in what amount?

1. No express promise to pay demur-rage on the part of Ashcraft-Wilkinson Company is alleged or proved. In "a letter to Straehan Shipping Company on March 12th, they expressed a willingness to pay fair demurrage; but this is not shown to have been communicated to any representative of the ship, nor to have resulted in any contract thereabout. But an agreement to pay proper demurrage, should any be incurred in discharging, is to be implied on the part of the recipients of the cargo. The shipowner, is entitled to protection against the unreasonable detention of the ship, and in this case, as was usual, had stipulated against it, and exacted in the charter party a lien on the cargo for demurrage, as well as for freight. Under it he could have held the cargo, or any part of it, until the charges were paid, or a satisfactory agreement made for payment. The charterer, by the cesser clause, was not personally liable to the ship after loading the cargo. The ship, in delivering the" cargo, would lose the benefit of this lien, and the [979]*979consignee would receive the benefit of its release.

The fairness, nothing else appearing, of implying an engagement to pay the charges, when delivery is taken in silence, but with knowledge of the situation as outlined, is as evident as when one accepts the valuable goods or services of another without express agreement touching payment. In the present case, Ashcraft-Wilkinson Company were not bound to take the cargo at all until it was delivered free of charges on the wharf, not having, on the arrival of the ship, become a party to the shipment by accepting indorsement of the bills of lading. Since they had bought the goods delivered in Savannah free of freight, insurance, and other charges, they might have refused to have anything to do with them until so delivered. But this right, as against the charterer, would not affect the rights of the ship, for it was no party to the sale of the fertilizers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maddern v. Austin
S.D. California, 2022
Trans-Asiatic Oil Ltd., S.A. v. Apex Oil Company
804 F.2d 773 (First Circuit, 1986)
United States v. Jamison
56 F.2d 627 (S.D. New York, 1930)
United States v. American Sugar Refining Co.
28 F.2d 140 (S.D. New York, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
18 F.2d 977, 1927 U.S. Dist. LEXIS 1111, 1927 A.M.C. 872, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-ashcraft-wilkinson-co-gand-1927.