United States v. Arkansas Power & Light Co.

207 F.2d 943, 1953 WL 81384
CourtCourt of Appeals for the Eighth Circuit
DecidedDecember 24, 1953
Docket14660
StatusPublished
Cited by5 cases

This text of 207 F.2d 943 (United States v. Arkansas Power & Light Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Arkansas Power & Light Co., 207 F.2d 943, 1953 WL 81384 (8th Cir. 1953).

Opinion

SANBORN, Circuit Judge.

This is an appeal from a judgment of dismissal, upon the merits, of the Government’s complaint in an action to recover damages from the defendant (ap-pellee) for breach of contract.

The case was here before. 165 F.2d 354. The first appeal was taken by the Government from an order dismissing its complaint upon the ground that the action had been prematurely brought, since the Arkansas Public Service Commission had not approved the contract in suit. We reversed and remanded the case for further proceedings.

The original complaint, filed April 4, 1946, alleged the nonperformance by the defendant of the provisions of paragraph numbered 28 of a written contract between the parties, dated February 20, 1945, which contract provided for the sale and delivery to the defendant of electrical energy generated by the Government’s Norfork Dam Project in Arkansas. Paragraph 28 reads as follows:

“28. In recognition of the established policy of the Government and in order to *944 effectuate the terms of Executive Orders No. 9366 and 9373 [U.S.Code Cong.Service 1943, pp. 5.66, 5.72], and make available, immediately, to war plants and establishments, public bodies and cooperatives, and other persons, in that order of preference so far as practicable, the benefits resulting from the construction and operation of the Norfork Dam Project, and in consideration of the Government making available to the Company [defendant] a substantial part of the power and energy generated at the Norfork Dam Project, the Company agrees:

“(a) That it will reduce, effective sixty (60) days after the execution of this agreement (and will continue the reduction thereafter for the duration of this agreement) its present rate of charges for electric service to the United States, its agencies, and industries or activities financed in whole or in part by the United States (excepting REA Cooperatives) so as to effectuate a total reduction to such customers of at least $150,000 annually.

“(b) That it will, within sixty (60) days after the execution of this agreement, put into effect and maintain during the term of this agreement a revised rate schedule applicable to all rural electric cooperatives served by the Company which will result in a net average rate for each month to each Rural Electric Cooperative taking service under such schedule and having a monthly load factor of 35% or larger of six (6) mills or less per kilowatt-hour.”

The complaint further alleged that “the defendant wholly failed to complete performance of the said contract in accordance with Article [paragraph] 28 (a) and (b) by filing rate schedules with the Public Service Commission of the State of Arkansas, and securing its approval thereof, reflecting the annual savings of $150,000 per year on government loads and rate schedules applicable to all Rural Electric Cooperatives served by the defendant which would result in a net average rate for each month to each Rural Electric Cooperative taking service under such schedule and having a monthly load factor of thirty-five per cent or larger of six (6) mills or less per kilowatt-hour, and still refuses to complete performance of said contract in such respects, * *

The original complaint asserted that, by reason of the nonperformance of the defendant’s obligations to file and secure the approval of reduced rate schedules under paragraph 28(a) and (b), the defendant for the year beginning April 21, 1945, became liable to the Government for damages in the sum of $155,-000. The Government in the original complaint and first amended complaint asked for specific performance and damages.

The position of the defendant, as reflected by its answer and cross-complaint, was, in effect that it had in the fall of 1944 effected the rate reductions called for by paragraph 28 of the contract, by filing schedules of revised rates with the Arkansas Department of Public Utilities [succeeded by the Arkansas Public Service Commission on February 12, 1945], which schedules were approved by the Department of Public Utilities on October 31, 1944, to become effective November 27, 1944; that the written contract signed on or about February 20, 1945, and dated that day, was to evidence an agreement reached by the parties in the summer of 1944; that the parties had intended to date the written contract prior to the general rate reductions approved by the Arkansas Department of Public Utilities on October 31, 1944, and that the dating of the written contract February 20, 1945, was the result of a mutual mistake of the parties, and that the defendant was entitled to have the contract reformed in that regard.

The order of dismissal from which the first appeal was taken by the Government was entered December 12, 1946. Our opinion reversing the order and remanding the case was filed January 7, 1948. 165 F.2d 354.

*945 After the remand of the case to the District Court for further proceedings and on April 2, 1948, the Government filed a second amended complaint in which it asserted that the contract in suit had terminated on June 30, 1947. In that complaint the prayer for specific performance was dropped, but damages for nonperformance were sought in the sum of $340,155.55, that being the amount by which the Government contends the defendant, in conformity with paragraph 28 (a) and (b) of the contract, should have secured a reduction in its rates to governmental customers during the period April 21, 1945, to June 30, 1947.

The evidence of the Government was to the general effect that the rate reduction made in the fall of 1944 did not include the rate reductions to governmental customers and rural electric cooperatives called for by the contract, and that there was no agreement or understanding on the part of the Government that the rate reductions contemplated by paragraph 28(a) and (b) would be, or were, made prior to the execution of the written contract which required the approval of the Secretary of the Interior, who had not formally approved or authorized its execution until February 2, 1945.

The evidence of the defendant tended to show that an understanding had been reached by the parties in the summer of 1944, which was reduced to writing and became the contract in suit; that it was understood that a general rate reduction being contemplated by the Arkansas Department of Public Utilities and the defendant, to become effective in the fall of 1944, should reflect the rate reductions to governmental customers and rural electric cooperatives provided for in the understanding reached with the representative of the Government; that the schedules which brought about the general rate reductions ordered and later approved by the Arkansas Department of Public Utilities in the fall of 1944 included the reductions in rates agreed upon; that no further rate reductions were contemplated; and that, when the written contract was signed in February 1945, the President of the defendant, who executed the contract on its behalf, thought he was “signing something that had already been performed.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norman v. Missouri Pacific Railroad
414 F.2d 73 (Eighth Circuit, 1969)
Angelo Vakas v. Philip Manuel
316 F.2d 369 (D.C. Circuit, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
207 F.2d 943, 1953 WL 81384, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-arkansas-power-light-co-ca8-1953.