United States v. American Surety Co.

34 F. Supp. 386, 1940 U.S. Dist. LEXIS 2818
CourtDistrict Court, E.D. New York
DecidedJuly 22, 1940
DocketNo. 7674
StatusPublished

This text of 34 F. Supp. 386 (United States v. American Surety Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. American Surety Co., 34 F. Supp. 386, 1940 U.S. Dist. LEXIS 2818 (E.D.N.Y. 1940).

Opinion

GALSTON, District Judge.

This is an action brought pursuant to the Miller Act, U.S.C. Title 40, Sec. 270b, 40 U.S.C.A. § 270b (formerly known as the Hurd Act) by a sub-contractor to recover an alleged balance due it from the general contractor.

The suit was begun by the Foster Wheeler Corporation against the American Surety Company. From the complaint it appears that on November 27, 1936, the Atlantic Basin Iron Works entered into a contract with the United States for furnishing and installing new boilers, renewal of tank tops, and general above water repairs for the United States Army Transport Republic. Pursuant to that contract the Atlantic Basin Iron Works furnished a payment bond with a surety for the protection of a person supplying labor and material in the prosecution of the contract. The bond was executed by the defendant, American Surety Company of New York, in the usuál form in such cases made and provided. The general contractor thereupon contracted with the plaintiff for boilers, materials .and labor which it is alleged were duly supplied by the plaintiff. The agreed price for the boilers and services was $96,-128.49; the contractor paid on account thereof the sum of $90,513.20, leaving unpaid $5,616.29.

By its answer, making denial of material allegations, the defendant Surety Company raised the general issues. Thereafter the Atlantic' Basin Iron Works intervened as a defendant, and by an amended answer set up a counterclaim alleging that the boilers and appurtenances supplied by the plaintiff were not in accordance with the specifications; and that the Atlantic Basin Iron Works was compelled to make repairs [387]*387after notice to the plaintiff at a cost of $11,365.48, afld accordingly seeks judgment in that amount against the Foster Wheeler Corporation.

The United States of America, as third party defendant, alleges that all the work and labor performed on or about October 12, 1937, in repairing the boilers on board the United States Army Transport Republic, was by virtue of the contract between the parties required to be done without any additional cost or expense; and as a counterclaim owing to the failure of the defendant, Atlantic Basin Iron Works, to repair or replace the defects in the brick work which developed within the year’s guarantee, seeks a recovery against the defendant and the third party plaintiff in the sum of $8,135.77.

The issue can be narrowly stated. On the one hand the plaintiff contends that it complied fully with the terms of the contract; on the other, the United States contends that within one year from the date of completion of the contract the furnaces failed; that in consequence the general contractor, having guaranteed the equipment furnished against defective materials and workmanship, was under obligation to replace by supply of new part or otherwise remedy the defect without cost to the United States Government; and the Atlantic Basin Iron Works in turn looks to the Foster Wheeler Corporation, under the terms of the contract between those two corporations, for failure to comply with the terms of the contract between them.

Moreover, the position of the Foster Wheeler Corporation is that the collapse of the furnaces was owing not to any fault on its part, but on the contrary to improper operation of the boilers by the crew of the United States Army Transport Republic.

In the stipulation signed by the parties it appears that the only items in the Government’s specifications claimed by the defendants not to have been performed duly by the Foster Wheeler Corporation relate to

(a) The type, trade name and specifications of the fire brick and refractory furnished and installed;

(b) The means employed for tying in place the furnace walls;

(c) The type, tradename, etc., of tie brick used for tying in place the furnace walls;

(d) The design and specifications of the tie bolts used for tying in place the furnace walls; and

(e) The number of tie bolts used for tying in place the furnace walls.

The stipulation recites that the foregoing items are covered by the following extracts of the specification.

(1) Government Contract W 626 q m-22097.

“Suitable tie brick with high temperature alloy steel tie bolts shall be supplied for supporting front and back walls.”

“All fire brick and fire tile shall conform to class SH 75 of Federal Specifications Board, specifications for fire clay brick No. HH-B-671a, and in addition thereto, shall pass the Navy simulated service test with a work factor rating of not less than 1.7.”

(2) Foster Wheeler Specification.

“The furnace walls will be tied in place with a suitable number of high temperature alloy steel tie bolts and special tie brick.”

“All refractory will be Garfield ‘Corstex’ and conform to Class SII 75 of Federal Specifications Board, specifications for fire clay brick No. HH-B 671 n and also shall pass the Navy simulated service test with a work factor of not less than 1.7.”

It is agreed that the four boilers were manufactured, furnished and installed by and under the supervision of the Foster Wheeler Corporation and that the work was completed and accepted by the Government on May 20, 1937. It appears that between that time and July 25, 1937, the Republic made one round trip from Brooklyn to Honolulu without incident; that on August 4, 1937, the Republic proceeded on another voyage to Honolulu, but on the return, when about two days out of Panama, the rear furnace wall of boiler No. 3 collapsed. Repairs of that boiler were made at the Canal Zone. On arrival from Panama at Brooklyn, on October 10, 1937, the rear furnace wall of boiler No. 1 collapsed. An examination at the time revealed also bulging in the rear walls of boilers Nos. 2 and 4.

The Foster Wheeler Corporation was requested to make the necessary repairs; and on refusal, the repairs were made by the Mack Company and paid for by the Atlantic Basin Iron Works. Thereafter the vessel made two voyages to Honolulu and return, following which, in March, 1938, an inspection of the four boilers revealed that to make the vessel seaworthy further re[388]*388pairs were necessary. The refusal of the Atlantic Basin Iron Works to re-brick the furnaces forced the United States to have repairs made in boilers Nos. 1, 2 and 4, and subsequently to re-brick boiler No. 3.

Our first inquiry must be to determine whether the fire brick and fire tile supplied by the plaintiff conformed to the specification. The proceedings at the meeting of the Board of Inquiry appointed by the superintendent of Army Transport Service to investigate the failure of the furnaces disclosed that the brick removed from boilers Nos. 1, 2 and 4 in March, 1938, included bricks bearing the trademarks Corstex, Mexko, Mullitex, Armor, and various miscellaneous broken brick. This variety included brick used in the original installation and brick used in the repairs of October, 1937. The Mack Engineering Supply Company had furnished the brick for the October, 1937, repairs. Their bill shows that only Mexko bricks were supplied by them.

A report of the National Bureau of Standards, on a test of samples of fire clay brick, made April 12, 1938, discloses that Mexko brick and Mullitex brick conform to Government specifications, but that neither the Corstex brand of fire clay brick nor Arch 3441 supplied, comply with the p c e requirement specified for the high heat duty class (formerly in the SH-75) of fire clay brick.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 270b
40 U.S.C. § 270b

Cite This Page — Counsel Stack

Bluebook (online)
34 F. Supp. 386, 1940 U.S. Dist. LEXIS 2818, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-american-surety-co-nyed-1940.