United States v. Alpine Land and Reservoir Co.

27 F. Supp. 2d 1230, 1998 WL 808191
CourtDistrict Court, D. Nevada
DecidedSeptember 3, 1998
DocketCIV. D-184-HDM
StatusPublished
Cited by11 cases

This text of 27 F. Supp. 2d 1230 (United States v. Alpine Land and Reservoir Co.) is published on Counsel Stack Legal Research, covering District Court, D. Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Alpine Land and Reservoir Co., 27 F. Supp. 2d 1230, 1998 WL 808191 (D. Nev. 1998).

Opinion

ORDER

McKIBBEN, District Judge.

On December 22, 1997, the Nevada State Engineer issued its Ruling On Remand # 4591. The United States and the Pyramid Lake Paiute Tribe (“Tribe”) appeal that ruling.

The history of this litigation is detailed in United States v. Alpine Land & Reservoir Co., 503 F.Supp. 877 (D.Nev.1980), aff'd. as modified, 697 F.2d 851 (9th Cir.1983) (“Alpine I”), United States v. Alpine Land & Reservoir Co., 878 F.2d 1217 (9th Cir.1989)(“Alpine II”)and United States v. Alpine Land & Reservoir Co., 983 F.2d 1487 (9th Cir.1992) (“Alpine III”). In Alpine III, the Ninth Circuit remanded this action to the district court to make the following determinations, on a parcel-by-parcel basis, with respect to each transfer application at issue: (1) whether the water rights appurtenant to the transferor properties at issue have been perfected; (2) whether the holders of the water rights sought to be transferred abandoned the water rights appurtenant to the transferor properties; and (3) whether the specific water rights sought to be transferred have been forfeited, if the specific water rights vested or were initiated after March 22, 1913. The Ninth Circuit left it to this court’s discretion whether to conduct the factual determinations itself or to appoint the State Engineer or a federal Water Master.

On April 13, 1995, this court issued the following order:

This action is remanded forthwith to the Nevada State Engineer to consider all applications and make determinations on the issues of perfection, abandonment and forfeiture. Should the State Engineer decide additional evidence is required, he shall afford the parties the opportunity to present such evidence. The State Engineer shall then certify the record to this court to decide whether or not the findings of the State Engineer are based on the relevant facts and applicable law.

Thereafter, the Engineer issued a briefing schedule and a timetable for the exchange of evidentiary materials between the parties. On August 30, 1996, the Engineer issued *1235 Interim Ruling No. 4411, in which the Engineer concluded: 1) the Tribe was not precluded by the doctrine of res judicata from being heard on the issues of lack of perfection, abandonment and forfeiture; 2) the Engineer had the authority to consider the issues of lack of perfection, abandonment and forfeiture; 3) the Engineer would act on the applications before him as ordered by the court; 4) Nevada law does not shift the burden of proving lack of abandonment to the applicants upon the protestant’s showing of an extended period of nonuse; and 5) NRS § 533.324, which became effective subsequent to the decision in Alpine III, precluded the need for perfection of the water rights that are the subject of the transfer applications prior to the transfer of said rights.

On September 23, 1996, the Tribe filed a motion for partial reconsideration regarding the Engineer’s ruling on perfection. In Ruling # 4591, the Engineer affirmed his conclusion that the court in Alpine II misinterpreted Nevada law when it held that all water rights in Nevada must be perfected prior to transfer. However, the Engineer further concluded that all unperfected water rights are not available to be transferred. The Engineer determined that if the Tribe proves a water right was not perfected prior to the filing of one of the transfer applications, the issue becomes whether that particular water right is still within the diligence phase of development. If the answer is yes, the un-perfected water right can be moved; however, if the water right is not within the diligence phase, the unperfected water right is not available for the transfer, as it does not comport with the common law doctrines of due diligence and relation back.

Evidentiary hearings were held in 1996 and 1997. On December 22, 1997, the Engineer issued its Ruling on Remand #4591, which considered fourteen (14) applications, consisting of fifty-six (56) transferor parcels. 1 In addition to the Engineer’s factual findings on a pareel-by-parcel basis, the ruling consisted of twelve (12) general findings of fact and four (4) general conclusions of law. Where applicable, the Engineer adopted and incorporated these general findings and conclusions when considering the issues of perfection, abandonment and forfeiture on a parcel-by-parcel basis.

Specifically, the Engineer determined that for thirty-eight (38) parcels, no water had been applied to beneficial use for periods ranging from five (5) years to thirty-six (36) years prior to the filing of the application to transfer the water right. For eight (8) other parcels, the Engineer found that the Tribe had proved that some portion of the land had not been irrigated for a substantial number of years, but that the Tribe had- failed to present evidence of the exact location of the unirrigated land. On the remaining parcels, the Engineer found the Tribe had failed to prove nonuse of the water by clear and convincing evidence.

The Engineer also made findings regarding the land use of the transferor parcels. For a majority of the thirty-eight (38) existing places of use where the Engineer found *1236 no water had been applied to beneficial use and the eight (8) parcels where the Engineer found partial nonuse, the Engineer determined that the evidence before him clearly showed that they were comprised of paved highways and roads, natural vegetation, bare land, residential areas and canals and drains.

With respect to the issues of perfection, forfeiture and abandonment, the Engineer found that the water right on one (1) parcel had not been perfected, the water rights on two (2) parcels could not be transferred, and that no water rights sought to be transferred had been abandoned or forfeited. The three parcels which the Engineer concluded could not be transferred belong to Application 47840 (Mills), parcels 5, 11 and 12. As to parcel 5, the Engineer stated “the water right was never perfected on this parcel from the time of the contract in 1951 through the filing of the change application in 1984, a period of 33 years. The State Engineer further finds in the absence of evidence to the contrary a lapse of 33 years does not demonstrate due diligence in placing the water to beneficial use; therefore, there is no water right that can be related back under the doctrine of relation back and there is no water right available to be transferred from this parcel.” With respect to parcels 11 and 12, the Engineer could not determine what the contract dates were. The Engineer concluded, therefore, that there was insufficient information to determine the Tribe’s claims of lack of perfection, forfeiture or abandonment or to allow the transfer of the water rights.

On January 16, 1998, the United States filed its Petition for Review and Notice of Appeal of Ruling # 4591. 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
27 F. Supp. 2d 1230, 1998 WL 808191, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-alpine-land-and-reservoir-co-nvd-1998.