United States v. Aetna Casualty Insurance Company

921 F.2d 741, 36 Cont. Cas. Fed. 75,992, 1990 U.S. App. LEXIS 21307
Court of Appeals for the Eighth Circuit·Decided December 10, 1990·No. 89-5127·Published·Cited by 1 cases

Opinion

921 F.2d 741

36 Cont.Cas.Fed. (CCH) 75,992

UNITED STATES of America for the Use and Benefit of RAMSDELL
CONSTRUCTION, Appellee,
v.
AETNA CASUALTY INSURANCE COMPANY; Lamro, Inc., Appellants,
Schultz & Sons Construction Company.

Nos. 89-5127, 89-5149.

United States Court of Appeals,
Eighth Circuit.

Submitted July 13, 1990.
Decided Dec. 10, 1990.

John Holm, Rapid City, S.D., for appellants.

John LaFleur, Rapid City, S.D., for appellee.

Before ARNOLD, JOHN R. GIBSON, and WOLLMAN, Circuit Judges.

JOHN R. GIBSON, Circuit Judge.

Ramsdell Construction sued Lamro, Inc., prime contractor on a road project on the Pine Ridge Indian Reservation, and its bonding company, Aetna Casualty Insurance Company, under the Miller Act, 40 U.S.C. Sec. 270a et seq. (1988), claiming that Lamro had not paid Ramsdell for work and equipment supplied on the project. Lamro counterclaimed for overpayments made to Ramsdell. The district court entered judgment for Ramsdell and against Aetna and Lamro for $34,135.16, plus prejudgment interest of $11,551.12 and dismissed Lamro's counterclaim. United States ex rel. Ramsdell Const. v. Aetna Cas. Ins. Co., No. CIV87-5134 (D.S.D. Feb. 8, 1989), slip op. at 18. All parties have appealed. We affirm the district court's order, except that we remand to the district court to enter a specific finding of fact on one aspect of Lamro's counterclaim.

Lamro was the primary contractor under a contract with the Bureau of Indian Affairs for a twelve-mile road project south of Scenic, South Dakota, known as the Rockyford Project. The district court found Lamro had no construction capabilities, but existed by virtue of its status as a Native American owned and managed business, which qualified it for preferential treatment under Oglala Sioux Tribal Ordinance No. 84-08. Slip op. at 2. Its practice is to bid on contracts subject to the Ordinance and then to enter subcontracts with other companies to do the construction work. Id.

Accordingly, Lamro entered two contracts with Ramsdell dated May 1, 1986, relating to the Rockyford Project. One contract explicitly required Ramsdell to perform Line Item 311(4) of the general contract, which consisted of removing and stockpiling the existing surface of the roadway. The district court held that the second contract, though styled "Equipment Rental Agreement," obliged Ramsdell to accomplish various other bid items on the project, except paying labor and culvert costs for those items, which Lamro would do directly. The district court found that the purpose of this oblique method of contracting was to meet requirements of the Bureau of Indian Affairs and the tribal employment rights ordinance requiring a qualifying company (Lamro) to do the work, though Lamro had no construction capabilities of its own. Slip op. at 2, 4-6.

There were problems on the project. First, there was a major design error in the project, and work was suspended from August 7 to August 19, 1986 while the error was corrected. During this time, Ramsdell had equipment idle at the job site. The specifications for the project provided for compensation in such an event. Lamro made a claim for the standby equipment costs to the Bureau of Indian Affairs and received at least partial compensation for the standby time.

Secondly, well into the project, Ramsdell began to have difficulty accomplishing the work in a timely manner due to equipment breakdowns and capital shortages. As the project's contract deadline loomed near, Lamro gave up on Ramsdell and hired two firms, Schultz & Sons Construction and Rapid Construction, to complete the construction.

Lamro and Ramsdell entered into a new contract dated September 22, 1986, which obliged Ramsdell to complete work under Line Item 304(7) of the general contract. Ramsdell's task under this subcontract was to replace recycled gravel on the road subbase, but Lamro was obliged to pay the labor and fuel expenses.

Importantly, the September 22, 1986 contract contained an addendum that in turn contained an "Agreement and Release" dated October 1, 1986. The Agreement and Release purported to release the parties from all existing claims against each other arising out of the May 1, 1986 "Equipment Rental Agreement," except for payment due Ramsdell for the part of the contract already completed but not yet paid for.

Besides Ramsdell's claims arising out of the two sets of contracts (May 1 and October 1, 1986) directly between Lamro and Ramsdell, there is also a claim arising out of dealings between Ramsdell and Schultz.1

Schultz and Ramsdell entered a contract having to do with "soft spot work." This was work additional to that covered by the original Rockyford Project contract, made necessary by the appearance of "soft spots" on the job site that resulted from water accumulation. The Bureau of Indian Affairs agreed to pay additional compensation to correct this problem, and Lamro contracted with Schultz to perform the work. Schultz, in turn, contracted with Ramsdell to provide labor, equipment and supplies for the work. Ramsdell completed its work on the soft spots on December 16, 1986. The total amount due Ramsdell for soft spot work was $34,135.16. Schultz did not pay Ramsdell, so Ramsdell hand delivered a Miller Act notice of its claim to Lamro, dated March 11, 1987.

Ramsdell sued Lamro for the amounts due for its equipment standing idle from August 7-19, 1986 and for the amount due it for its work on the soft spots under its contract with Schultz. Lamro counterclaimed for overpayments under the May 1, 1986 "Equipment Rental Agreement" and the May 1 Line Item 311(4) subcontract.

The district court held that Ramsdell had released its claim for standby equipment in the October 1, 1986 Agreement and Release. Slip op. at 15. However, the court held that Ramsdell was entitled to the amounts it claimed for the soft spot work ($34,135.16) and awarded Ramsdell that amount, plus prejudgment interest. Id. at 18. The court did not explicitly discuss Lamro's counterclaims, but simply failed to award Lamro anything on the claims. Lamro interprets the trial court's discussion of the release as a finding that Lamro's claims were released by the October 1 Agreement. Lamro's Brief at 29.

On appeal, Lamro argues that Ramsdell's soft spot claim is not protected under the Miller Act, because Ramsdell did not serve on Lamro the necessary Miller Act notice, see 40 U.S.C. Sec. 270b(a), of its soft spot claim, and because Schultz was not a subcontractor on the job. Lamro also argues that the district court erred in holding that it released its claims for overpayments. Ramsdell also appeals, arguing that it did not release its claim for the standby equipment.

We begin by observing that we decided that Schultz was a subcontractor on the Rockyford Project in the Morris case, 908 F.2d at 379. See Ramsdell, slip op. at 16. The requirements for collateral estoppel are met in this case, see generally Lane v. Peterson, 899 F.2d 737, 741 (8th Cir.), cert.

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. Aetna Casualty Insurance Company, 921 F.2d 741, 36 Cont. Cas. Fed. 75,992, 1990 U.S. App. LEXIS 21307 (8th Cir. 1990).