United States v. 327 Acres of Land

320 F. Supp. 844, 14 A.L.R. Fed. 799, 1971 U.S. Dist. LEXIS 15212
CourtDistrict Court, N.D. Georgia
DecidedJanuary 4, 1971
DocketCiv. A. No. 2056
StatusPublished
Cited by4 cases

This text of 320 F. Supp. 844 (United States v. 327 Acres of Land) is published on Counsel Stack Legal Research, covering District Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. 327 Acres of Land, 320 F. Supp. 844, 14 A.L.R. Fed. 799, 1971 U.S. Dist. LEXIS 15212 (N.D. Ga. 1971).

Opinion

SIDNEY O. SMITH, Jr., Chief Judge.

This is a proceeding in eminent domain to ascertain just and adequate compensation for certain tracts of land condemned by the government in connection with the Carter’s Dam Project in northwest Georgia. At pre-trial, it appeared that this particular case embraced a preliminary issue whether the particular taking was within the “scope of the project.” Accordingly, a non-jury hearing was conducted by the court in accordance with United States v. Reynolds, 397 U.S. 14, 90 S.Ct. 803, 25 L.Ed.2d 12 (1970) and Wardy v. United States, 402 F.2d 762 (5th Cir. 1968).

FINDINGS OF FACT

The project in question, The Carters Dam and Reservoir, “is a combination flood control and hydroelectric power project. As an additional feature, the Reservoir to be created will provide opportunities for development of recreational facilities.”

Development of the Alabama-Coosa River Basis was conceived in the mind’s eye of the Corps of Engineers as far back as 1930. At the time a three-dam system generating some 30,000 KW, was suggested. By 1941, feasibility studies had modified the proposal to a two-dam system, with the power capacity to remain under study, and Congressional authorization to proceed was requested. (G #2, House Document 414, 77th Congress). The project itself was approved in 1945 consistent with budgetary requirements. (G #3, Public Law 14, 79th Congress). There followed an extensive planning period. In 1958, the Federal Power Commission recommended use of a pumped storage reversible type generating unit to increase the hydroelectric output to 104,000 KW. This recommendation was “taken under study,” but apparently rejected by the Corps of Engi[846]*846neers at the time. In 1961, the Site Selection Report opted for single-dam conventional generating units producing 96,000 KW and Carters Dam (Plan 1) was recommended. (G #4). At the time the reversible type units, a technological development of the fifties, were still being recommended by the Federal Power Commission. Land acquisition was begun on February 16, 1962, for the dam and power plant sites and completed in 1962. Meanwhile, the Corps of Engineers continued to revise its hydroelectric plans and in September, 1963, raised the generating output to 104,000 KW, still with conventional units. Subsequently, in the fall of 1963, the Federal Power Commission proposals were placed under additional study and it was recommended that three 52,000 KW conventional units be installed. However, the idea of a regulation pool and reversible units was again rejected. See G #5, Raymond study).

In April, 1964, the public meetings in the area were held. At that time it was envisioned that some 1,225 acres, already acquired, was needed for the dam site and adjacent public use and operational area, and some 6,224 acres would be needed for the reservoir and public access areas, plus 170 acres of easement area. (See D #1, Information' pamphlet distributed at the meetings). Land acquisition for the reservoir area was begun on January 1, 1964, and completed in 1965. There was no mention of any need for additional acreage for an impoundment area.

In 1964, the Federal Power Commission renewed its efforts to secure approval of increased power generation and the utilization of reversible units. Following a series of meetings during 1964, the Corps of Engineers for the first time, on July 25, 1964, accepted the Federal Power Commission recommendation of two 125,000 KW reversible units, with possible allowance for two additional units for a total of 450,000 KW. (See G #3 supplement to Design Memorandum No. 5).

The acceptance of this plan changed the overall requirements in that the reversible-units necessitated the construction of a reregulation dam below the main dam where water is to be impounded to be pumped back into the main reservoir by the reversible units, thereby effectually doubling the generating capacity of the plant. In September, 1964, it was determined that considerable additional land for the impoundment area would be needed and in August, 1965, the land acquisition for this purpose was authorized. (See G #9, Design Mem. No. 12). However, due to a delay in determination of the exact elevation needed for the reregulation impoundment area until August, 1967, no land acquisitions commenced until after that time. It was substantially completed by the end of 1969.

The regulation dam and impoundment area required the taking of 1,075 acres outright and 25 acres of easements. Its location is southwest and downstream adjacent to the main dam and reservoir.1

Under such circumstances, does this last taking come within the “scope of the project” or not?

CONCLUSIONS OF LAW

The so-called Miller2 rule is easily stated. As reiterated by United States v. Reynolds, 397 U.S. 14, 90 S.Ct. 803, 25 L.Ed.2d 12 (1970), it provides:

“If a distinct tract is condemned, in whole or in part, other lands in the neighborhood may increase in market value due to the proximity of the public improvement erected on the land taken. Should the Government, at a later date, determine to take these other lands, it must pay their market [847]*847value as enhanced by this factor of proximity. If, however, the public project from the beginning included the taking of certain tracts but only one of them is taken in the first instance, the owner of the other tracts should not be allowed an increased value for his lands which are ultimately to be taken any more than the. owner of the tract first condemned is entitled to be allowed an increased market value because adjacent lands not immediately taken' increased in value due to the projected improvement.
“The question then is whether the respondents’ lands were probably within the scope of the project from the time the Government was committed to it. If they were not, but were merely adjacent lands, the subsequent enlargement of the project to include them ought not to deprive the respondents of the value added in the meantime by the proximity of the improvement. If, on the other hand, they were, the Government ought not to pay any increase in value arising from the known fact that the lands probably would be condemned. The owners ought not to gain by speculating on probable increase in value due to the Government’s activities.”

While this rule is easily understood in the abstract, it is difficult to apply in specifics. The court knows of no case which delineates uniform factors or standards to be applied to measure “the scope of the project.” As stated in Reynolds:

“As with any test that deals in probabilities, its application to any particular set of facts requires discriminating judgment. The rule does not require a showing that the land ultimately taken was actually specified in the original plans for the project. It need only be shown that during the course of the planning or original con•struction it became evident that land so situated would probably be needed for the public use.”

Applications of the Miller rule in the context of before-the-fact hearings prior to trials for compensation are not numerous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
320 F. Supp. 844, 14 A.L.R. Fed. 799, 1971 U.S. Dist. LEXIS 15212, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-327-acres-of-land-gand-1971.