United States Sugar Refinery v. Providence Steam & Gas Pipe Co.

62 F. 375, 10 C.C.A. 422, 1894 U.S. App. LEXIS 2306
CourtCourt of Appeals for the Seventh Circuit
DecidedMarch 10, 1894
DocketNo. 61
StatusPublished
Cited by1 cases

This text of 62 F. 375 (United States Sugar Refinery v. Providence Steam & Gas Pipe Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Sugar Refinery v. Providence Steam & Gas Pipe Co., 62 F. 375, 10 C.C.A. 422, 1894 U.S. App. LEXIS 2306 (7th Cir. 1894).

Opinion

JENKINS, District Judge.

By the contract of February 19, 1890, the defendant in error undertook to equip the plant of the plaintiff in error with the Grinnell Automatic Sprinklers, furnishing the necessary piping and labor. It was to be the wet-pipe system. The contract provided that “the sizes of pipe will conform to'the schedule required by your underwriters.” The work was guarantied to be water-tight, and satisfactory in every respect. It was completed in the early summer of 1890. On January 14, 1891, the Providence Company agreed to change the sprinkler system from the wet to the dry system, furnishing the necessaries “to make the same a most complete job, and which shall be satisfactory to your underwriters.” The contract further provided, “If it shall be found that the pipes as now erected are not tight enough, you [the Sugar Befinery Company] to pay any cost we [the Providence Company] may be put to to make them so, which shall be a nominal figure in any event.” The change was effected and completed by May 5, 1891. Upon the building so equipped, insurance was procured [377]*377between November, 1890, and August, 1891, in some 68 companies, to the amount of at least. §>876,000. Prior to November, 189L, and until some three months after suit brought, there was no controversy between the parties with respect to the character of the work. Payment was postponed until July, 1891, and then refused upon the sole ground that during the progress of the work a servant of the Providence Company was accidentally killed, and t he Sugar Eefinery Company feared it might he held liable in damages for his death, and the parties could not agree with respect to the form of the bond of indemnity demanded. On the 7th of November, 1891, the Sugar Edinery complained of inability to get the water out of the pipes, in preparation for cold weather, and de nounced the whole system as one necessary to be removed. Under i he general issue the plaintiff in error gave notice that it would prove an indebtedness of the defendant in error growing out of the contract, because, among other things:

"The sizes oí the pipe did not and does not conform in size to the schedule adopted by the leading' insurance companies throughout tho country, as agreed and warranted, and that the system and sizes of pipe did not conform to the schedule required by its underwriters, meaning thereby the underwriters of '..He various insurance companies to which the defendant might apply for insurance, and meaning' thereby the well-known requirement,s of the various insurance companies, as agreed and warranted, whereby the sprinkler system became aiid was of no use or value to defendant; and by reason of the unfitness of said sprinkler system, as aforesaid, the same afterwards, to wit, on,” etc., ‘'became wholly useless to the defendant, and a burden and damage to defendant’s various buildings and property, whereby the same must be removed, at great cost and expense to defendant, and to the damage of defendant's building and properly, and the entire work of equipping said building with a sprinkler system which will meet the requirements of said contracts and agreements must be commenced and done over again, to the great loss, delay, and damage of said defendant; and various portions of said piping in said system, owing to said imperfect workmanship, have heretofore frozen and burst, and water has collected in various places, causing- defendant great loss and damage by reason of said water so collecting and freezing and bursting, in the endeavor to repair said damage and prevent further loss, whereby tbe defendant was damaged to the amount of fifteen thousand dollars.”

The alleged error at the trial mainly relied upon is in the exclusion of the question propounded to the witness West, as follows:

“Let me ask you, Mr. West, aside from the question of leakage, and all expense, if any, required to remedy leakage, from your examination of the system, and your knowledge of its present condition as testified to, what would it, cost to properly fix that system so that the water can be property drained from the system, with as few elbows and dips as possible, with sizes of pipe to conform to this list, to wit: Three-quarter inch pipe, one head allowed; one inch pipe, three heads allowed; one and a quarter inch pipe, five heads allowed; one and a half inch pipe, nine beads allowed; two inch pipe, seven heads allowed; two and a half inch pipe, twenty-seven heads allowed; three inch pipe, forty-six heads allowed; three and a half inch pipe, seventy-eight heads allowed; four inch pipe, one hundred and fifteen heads allowed; live inch pipe, one hundred and seventy-live heads allowed, — and the further requirement that in buildings where the floor area requires more than one hundred and seventy-five heads, or a five inch riser, the equipment must be divided into two systems with two risers. What would be the expense to make that system, as you found it, conform to those requirements, aside from all expense attached to the leakage?”

[378]*378Prior to the propounding of this question, the counsel for the plaintiff in error had submitted the question of the cost to make the system, as the witness found it, conform to the requirements of a particular schedule, known as the “Chicago Fire Underwriters’ Schedule for Requirements of Sprinklers.” Upon objection the court ruled the question to be improper, but that the witness might describe the system as he found it. The witness had then proceeded to say that he found certain of the pipes tipped toward the extreme end, and upon some of the floors of the building found more sprinklers than required by the Chicago underwriters on certain sized pipe, and thereupon the question stated ~was propounded to the witness.

It is apparent to the court, from the desultory conversation which ensued between counsel upon both sides and the court, following this question, that all parties were led away from any view of the purpose of the question as now claimed by counsel. The discussion went to the question whether the Sugar Refinery Company, having obtained all the insurance required upon the plant equipped with this fire extinguisher, could defeat the right of action because in some respects the plant did not comply with the schedule prepared by some company. The court announced that the defendant below might prove the existence of anything that would justify the cancellation of the policies. But this seems not to have been satisfactory to the defendant’s counsel, who, upon being questioned by the court if he wished to show that the insurance companies did not stand by these schedules, replied that either the contract, when it says the “requirements,” means something, or it does not, and thereupon the objection was sustained. A reference to the contract shows that the stipulation was that the “sizes of pipe will conform to the schedule required by your underwriters.” Another stipulation in the contract-is this: “The entire work is to be done subject to the approval of your underwriter’s, and to be accepted by them, which we guaranty will be done.” A provision in the second contract is to the effect that the work “shall be satisfactory to your underwriters.”

We think the objection to the question wás properly sustained, because:

First. If it was desired to show that the sizes of pipe did not conform to the underwriters’ schedule, the question should have been limited to that subject, and should not have embraced the other conditions in the question.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hunt v. Kile
98 F. 49 (Seventh Circuit, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
62 F. 375, 10 C.C.A. 422, 1894 U.S. App. LEXIS 2306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-sugar-refinery-v-providence-steam-gas-pipe-co-ca7-1894.