United States Steel Corp. v. S. D. Highway Commission

237 N.W.2d 175, 89 S.D. 679, 1975 S.D. LEXIS 192
CourtSouth Dakota Supreme Court
DecidedDecember 31, 1975
DocketFile 11530
StatusPublished
Cited by2 cases

This text of 237 N.W.2d 175 (United States Steel Corp. v. S. D. Highway Commission) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Steel Corp. v. S. D. Highway Commission, 237 N.W.2d 175, 89 S.D. 679, 1975 S.D. LEXIS 192 (S.D. 1975).

Opinion

MILLER, Circuit Judge.

This action was commenced in January 1969, specifically under Ch. 110, S.L.1964 (now SDCL 31-2-34 through 31-2-39), seeking recovery for additional work and materials arising out of the temporary suspension of work under a contract that had been entered into in February 1963, for the construction of the superstructure on the Platte-Winner Bridge. Plaintiff received *681 notice to proceed with construction on November 5, 1963, but on January 14, 1964, it was advised by the state highway engineer to suspend the work, apparently because of cracks in the pilings in the substructure of the bridge, which substructure was construct-' ed by third-party defendants. The suspension continued until March 23, 1965, and plaintiff resumed work on the superstructure of the bridge on April 1, 1965.

In the initial trial to the court, judgment in the amount of $170,000 was awarded to the plaintiff. That judgment was entered on November 30, 1970. On December 28, 1970, such judgment was vacated on motion of third-party defendants because the trials between plaintiff and defendants and defendants and third-party defendants had been separated without notice to third-party defendants.

On November 21, 1972, this court entered its decision in G. H. Lindekugel & Sons, Inc. v. South Dakota St. Hwy. C., 87 S.D. 32, 202 N.W.2d 125, construing SDCL 31-2-34 through 31-2-39.. There this court held that SDCL 31-2-34 through 31-2-39 was a procedural remedy and not an appropriation statute that would allow payment of a judgment for breach of contract against the State of South Dakota. See South Dakota Constitution, Art. XI, § 9.

Presumably, because of the decision in Lindekugel, plaintiff amended its complaint to allege that the liability of the state for the additional work and materials caused by suspension of work' on the bridge by the state highway engineer was specifically provided for in paragraph 4.5(c) of the construction contract and, as a result, a legislative appropriation for the contract would allow recovery.

Defendant, joined by third-party defendants, moved the trial court for summary judgment alleging that as a matter of law paragraph 4.5(c) of the contract did not allow for recovery against the state. The trial court by memorandum decision indicated that the motion for summary judgment would be granted. Following further hearings on a statute of limitations issue, summary judgment was filed and entered. It is that summary judgment from which plaintiff appeals.

*682 In bringing this appeal, plaintiff has assigned as error the following:

1. That the trial court erred in granting summary judgment, arguing that there are genuine issues of material fact still to be determined.

2. That the trial court erred in determining that as a matter of law such contract provision (4.5(c) ) does not permit recovery and, further, in determining that defendants were entitled to judgment as a matter of law.

3. That the trial -court erred in determining that SDCL 31-2-34 through 31-2-39, formerly Ch. 110) S.L.1964, did not constitute an appropriation statute for the payment of plaintiff’s claim.

In Wilson v. Great Northern Railway Company, 1968, 83 S.D. 207, 157 N.W.2d 19, this court set down the guiding principles on the use of summary judgment. It is only appropriate that they be reiterated here.

“(1) The evidence must be viewed most favorable to the nonmoving party; (2) The burden of proof is upon the movant to show clearly that there is no genuine issue of material fact and that he is entitled to judgment as a matter of law; (3) Though the purpose of the rule is to secure a just, speedy and inexpensive determination of the action, it was never intended to be used as a substitute for a court triál or for a trial by jury where any genuine issue of material fact exists. (4) A surmise that a party will not prevail upon trial is not sufficient basis to grant the motion on issues which are not shown to be sham, frivolous or so unsubstantial that it is obvious it would be futile to try them. (5) Summary judgment is an extreme remedy and should be awarded only when the truth is clear and reasonable doubts touching the existence of a genuine issue as to material fact should be resolved against the movant. (6) Where, however, no genuine issue of fact exists it is looked upon with favor and is particularly adaptable to expose sham cláims and defenses.”

*683 Keeping these guiding principles in mind, we now address the first of plaintiff’s assignments of error. This court finds that there are no genuine issues of material fact yet to be determined. It is not the specific claims for additional work and materials nor the fact that the work on the bridge was indeed suspended which defendants have disputed in this case. The only real issue which remains between the parties is the issue of defendant’s liability for these claimed additional expenses. This was an issue of law to be determined by the trial court.

Plaintiffs second assignment of error questions the trial court’s finding that, as a matter of law, the contract provision, paragraph 4.5(c), 1 does not permit recovery. *684 In reviewing the record on this issue, this court agrees with the analysis and conclusions of the trial court in its memorandum decision, wherein it stated:

“THE ISSUE: Whether or not the contract imposes a legal obligation upon the State to pay for ‘additional work’ as claimed by Plaintiff..
No claim is made by the Plaintiff under the ‘extra work’ provisions found in Section 9.4 of the Contract. Plaintiff contends that a suspension of work in fact occurred, and that payment for its claim is provided for in that sentence in 4.5(c) which reads:
*685 ‘The necessary replacement of materials and all additional work caused by such Suspension shall be paid for by the State at the Contract unit prices or by force account where no contract item exists for such work and for materials.’
“Defendant contends Plaintiff is taking the foregoing provision out of context in order to reach the conclusion it does. Defendant contends Section 4.5, which is entitled ‘Maintenance of Traffic’, applies solely to the maintenance of traffic through the construction site or project, and that Plaintiff’s various claims obviously have no connection with this type claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
237 N.W.2d 175, 89 S.D. 679, 1975 S.D. LEXIS 192, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-steel-corp-v-s-d-highway-commission-sd-1975.