United States of America v. SEA Construction LLC
Opinion
1 2
3 4 5 6 7 UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON 8 AT SEATTLE
9 10 UNITED STATES OF AMERICA, CASE NO. C18-1698JLR et al., 11 ORDER DENYING STIPULATED Plaintiffs, MOTION TO CONTINUE TRIAL 12 v.
13 SEA CONSTRUCTION, LLC et al., 14 Defendants. 15 This matter comes before the court on the parties’ stipulated motion to continue 16 the trial date, along with 11 other pretrial deadlines. (See Mot. (Dkt. # 18) at 2-3.) The 17 parties state that “Defendants’ primary counsel on this matter, Sarah Cox, recently 18 learned that she has a serious medical condition that requires surgery and will force her to 19 miss work for a significant portion of the remaining discovery schedule, including 20 specifically during the time when the parties would be conducting depositions and 21 otherwise finalizing discovery. (Id. at 1-2.) Accordingly, the parties propose an 22 1 amended case schedule that postpones most pretrial deadlines by roughly two months. 2 (See id. at 2-3.) The parties contend that they meet Federal Civil of Civil Procedure Rule
3 16(b)(4)’s good cause standard based on Ms. Cox’s health issues. (See id. at 3. (citing 4 Wake Forest Acquisitions, L.P. v. Vanderbilt Commercial Lending, Inc., No. 2:15-CV- 5 02167 KJM DB, 2018 WL 1586362 (E.D. Cal. 2018)).) 6 The court issues scheduling orders setting trial and related dates to provide a 7 reasonable schedule for the resolution of disputes. Pursuant to Federal Rule of Civil 8 Procedure 16(b)(4), “[a] schedule may only be modified for good cause and with the
9 judge’s consent.” Fed. R. Civ. P. 16(b)(4). “Good cause” for purposes of Rule 16 10 focuses on the diligence of the party seeking to modify the pretrial scheduling order. 11 Johnson v. Mammoth Recreations, Inc., 975 F.2d 604, 607-08 (9th Cir. 1992). Parties 12 must “diligently attempt to adhere to that schedule throughout the subsequent course of 13 the litigation.” Jackson v. Laureate, Inc., 186 F.R.D. 605, 607 (E.D. Cal. 1999); see also
14 Marcum v. Zimmer, 163 F.R.D. 250, 254 (S.D. W. Va. 1995). In part, the “good cause” 15 standard requires the parties to demonstrate that “noncompliance with a Rule 16 deadline 16 occurred or will occur, notwithstanding [the parties’] diligent efforts to comply, because 17 of the development of matters which could not have been reasonably foreseen or 18 anticipated at the time of the Rule 16 scheduling conference . . . .” Jackson, 186 F.R.D.
19 at 608. Further, the court’s scheduling order states that the dates are “firm” and that 20 “[t]he court will alter these dates only upon good cause shown.” (Sched. Order (Dkt. 21 # 16) at 2.) 22 // 1 The court is sympathetic to Ms. Cox’s health condition. However, the court 2 cannot conclude that the parties have met Rule 16(b)(4)’s good cause standard. First, Ms.
3 Cox does not submit a declaration specifying when she learned she would be unable to 4 work for several months.1 Additionally, the court notes that James Howard appeared as 5 defense counsel at the same time as Ms. Cox in February 2019. (See 1st Not. (Dkt. # 9); 6 2d Not. (Dkt. # 11).) The parties do not explain why Ms. Cox’s absence “will render it 7 impossible for the parties to comply with the current case schedule” while Mr. Howard 8 remains active in this case. (See Mot. at 3.) Accordingly, the court DENIES the parties’
9 stipulated motion (Dkt. # 18). As the parties may be aware, there are currently multiple 10 judicial vacancies in the Western District of Washington, which render the court’s 11 calendar less flexible. Nevertheless, if the parties would like to move their trial date to 12 the end of the court’s trial calendar, they may so stipulate and notify the court. If the 13 parties so stipulate, the court will issue a new case schedule for all remaining pretrial
14 deadlines based on a new trial date at the end of the court’s trial calendar. The parties 15 should be aware that the court is presently setting trials in approximately March 2021. 16 Dated this 22nd day of November, 2019. 17 A 18 United States District Judge
1 Ms. Cox signed the stipulated motion but did not submit a corresponding declaration. 21 (See Mot. at 4; see generally Dkt.) The court notes that the parties submitted their stipulation two days before the expert disclosure deadline and the deadline to amend pleadings. (See Mot. at 22 4; Sched. Order at 1.)
Free access — add to your briefcase to read the full text and ask questions with AI
United States of America v. SEA Construction LLC (United States of America v. SEA Construction LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.