United States of America, for the Use and Benefit of Stewart & Stevenson Services, Incorporated v. MCI Constructors, Incorporated the Federal Insurance Company, United States of America, for the Use and Benefit of Stewart & Stevenson Services, Incorporated v. MCI Constructors, Incorporated the Federal Insurance Company

898 F.2d 149, 1990 U.S. App. LEXIS 2577
CourtCourt of Appeals for the Fourth Circuit
DecidedFebruary 26, 1990
Docket89-1452
StatusUnpublished

This text of 898 F.2d 149 (United States of America, for the Use and Benefit of Stewart & Stevenson Services, Incorporated v. MCI Constructors, Incorporated the Federal Insurance Company, United States of America, for the Use and Benefit of Stewart & Stevenson Services, Incorporated v. MCI Constructors, Incorporated the Federal Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America, for the Use and Benefit of Stewart & Stevenson Services, Incorporated v. MCI Constructors, Incorporated the Federal Insurance Company, United States of America, for the Use and Benefit of Stewart & Stevenson Services, Incorporated v. MCI Constructors, Incorporated the Federal Insurance Company, 898 F.2d 149, 1990 U.S. App. LEXIS 2577 (4th Cir. 1990).

Opinion

898 F.2d 149
Unpublished Disposition

NOTICE: Fourth Circuit I.O.P. 36.6 states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Fourth Circuit.
UNITED STATES of America, for the Use and Benefit of STEWART
& STEVENSON SERVICES, INCORPORATED, Plaintiff-Appellee,
v.
MCI CONSTRUCTORS, INCORPORATED; the Federal Insurance
Company, Defendants-Appellants.
UNITED STATES of America, for the Use and Benefit of STEWART
& STEVENSON SERVICES, INCORPORATED, Plaintiff-Appellant,
v.
MCI CONSTRUCTORS, INCORPORATED; the Federal Insurance
Company, Defendants-Appellees.

Nos. 89-1452, 89-1458.

United States Court of Appeals, Fourth Circuit.

Argued: Jan. 8, 1990.
Decided: Feb. 26, 1990.

Appeals from the United States District Court for the Eastern District of Virginia, at Alexandria. James C. Cacheris, District Court Judge. (88-1138-A)

Thomas Bruce Newall, Watt, Tieder, Killian & Hoffar, McLean, Virginia, for appellants.

Thomas M. Brownell, Shaw, Pittman, Potts & Trowbridge, McLean, Virginia, for appellee.

E.D.Va.

AFFIRMED.

Before ERVIN, Chief Judge, MURNAGHAN, Circuit Judge, and J. FREDERICK MOTZ, United States District Judge for the District of Maryland, sitting by designation.

PER CURIAM:

Stewart & Stevenson Services, Inc. ("SSSI") brought this action under the Miller Act, 40 U.S.C. Sec. 270b, against MCI Constructors, Inc. ("MCI") and Federal Insurance Company ("Federal"), seeking payment for labor and materials furnished pursuant to an agreement between SSSI and MCI. Following a bench trial, the district court entered judgment in favor of SSSI, and awarded SSSI damages in the amount of $132,807.29 plus interest. MCI and Federal now appeal that decision, contending that most of the costs incurred by SSSI were directly attributable to its own negligence. SSSI cross-appeals that part of the trial court's decision holding that SSSI was not entitled to recover complete payment from MCI for its work on operating and maintenance manuals in the absence of an express agreement between the parties authorizing such work. Because the decision of the court below is not clearly erroneous, it is hereby affirmed.

I.

MCI was the prime contractor on a General Services Administration project to supply and install seven gas turbine generator sets ("Gen-Sets") as part of a back-up power system at the Central Intelligence Agency Headquarters facility in Langley, Virginia. Federal was MCI's surety for the project. MCI procured the required Gen-Sets from Williams & Lane Energy Systems Corporation ("Williams & Lane"). The Gen-Sets consisted of generators manufactured by Kato Generators, Inc., and turbines produced by the Allison Gas Turbine Division of the General Motors Corporation ("Allison"). Williams & Lane was also hired to start up the Gen-Sets after they had been received and installed at the project site by MCI. After the seven Gen-Sets had been delivered to the site and four of them started by Williams & Lane, the subcontractor abandoned its work and defaulted on its obligations to MCI. Consequently, on January 6, 1987, MCI entered into a time and materials agreement with SSSI (the "Contract"). Under the Contract, SSSI agreed to complete the start-up of the three remaining Gen-Sets, and MCI promised to reimburse SSSI for the actual costs of all labor and materials, based on specified rates, that were provided to MCI by SSSI. SSSI estimated that its expenses for the project would total approximately $70,000.

When SSSI technicians attempted to start up Gen-Set No. 7 in January of 1987, they observed that the turbine blades were rubbing heavily against the compressor housing. The Allison turbine assembly, or compressor unit, that was installed in Gen-Set No. 7 is also identified by its serial number, ASP-1099. Because ASP-1099 was new, it was still covered by the manufacturer's warranty. The warranty extended only to the cost of repairs, however, and did not cover the associated expenses of removing, transporting and reinstalling the turbine unit. After consulting with Allison and MCI, SSSI removed the defective turbine from Gen-Set No. 7, and shipped it to National Airmotive Corporation ("NAC") in Oakland, California, for repairs. NAC is one of only two authorized Allison warranty repair facilities in the United States. In March of 1987, NAC ostensibly repaired the turbine, tested the blade assembly for rubbing, determined that the compressor unit was fixed, and returned the unit to SSSI in Virginia. In June of 1987, SSSI reinstalled the turbine in Gen-Set No. 7, and attempted to start up the unit. Despite the work and tests performed by NAC, SSSI technicians still observed abnormal compressor rubbing on coastdown, which occurs when the Gen-Set has been running and fuel is cut off to the power unit. Thereafter, the turbine was again removed and sent to NAC. NAC tested the turbine upon receipt, could find no problems with the unit, and returned it to SSSI. SSSI, however, continued to observe excessive rubbing on coastdown following the reinstallation of the turbine in July of 1987. NAC sent its own technician to the job site in August of 1987. The NAC technician confirmed the existence of severe compressor rubbing, and ordered the turbine sent back to NAC for additional repairs. Because its representative ordered the repairs, NAC paid for the cost of transporting the turbine assembly to its facility in Oakland on this occasion. Despite the additional repairs by NAC, SSSI still experienced rubbing problems once the unit was returned to Virginia, and SSSI was forced to send the turbine back to NAC for a fourth and final time in September of 1987.

Perplexed by ASP-1099's persistent rubbing problems, NAC wrote SSSI on October 21, 1987, to inform SSSI that, henceforth, NAC would no longer repair the turbine without charge unless SSSI could prove that the rubbing was caused directly by NAC's workmanship. NAC had come to believe that something external to the compressor unit was probably causing the rubbing. Consequently, NAC suggested that SSSI install the problematic turbine assembly in another Gen-Set in order to determine whether NAC's supposition was correct. Before SSSI had the opportunity to install ASP-1099 in another Gen-Set, however, MCI informed SSSI that it would make no further payments to SSSI until the turbine problems were resolved. It should be noted that SSSI submitted a daily accounting of all materials and labor furnished and charged to MCI under the Contract. These "Daily Customer Acknowledgment" forms were completed and signed by the SSSI technicians performing the start-up work, and counter-signed and approved by an MCI representative, usually the project manager. The Contract provided that MCI would reimburse SSSI for its expenses on a bi-monthly basis.

After MCI notified SSSI of its decision to cease its payments, SSSI discontinued all work under the Contract, and MCI was forced to hire a third company, American Power Services ("American"), to reinstall ASP-1099. Following NAC's recommendation, American placed ASP-1099 in one of the other Gen-Sets, and installed the turbine assembly from that other Gen-Set into Gen-Set No. 7.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
898 F.2d 149, 1990 U.S. App. LEXIS 2577, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-stewart-stevenson-ca4-1990.