United States of America, for the use and benefit of Seedorff Masonry, Inc. v. Archer Western Construction, LLC

CourtDistrict Court, D. Nebraska
DecidedSeptember 23, 2019
Docket8:18-cv-00021
StatusUnknown

This text of United States of America, for the use and benefit of Seedorff Masonry, Inc. v. Archer Western Construction, LLC (United States of America, for the use and benefit of Seedorff Masonry, Inc. v. Archer Western Construction, LLC) is published on Counsel Stack Legal Research, covering District Court, D. Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America, for the use and benefit of Seedorff Masonry, Inc. v. Archer Western Construction, LLC, (D. Neb. 2019).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEBRASKA

UNITED STATES OF AMERICA, FOR THE USE AND BENEFIT OF SEEDORFF MASONRY, INC., 8:18CV21

Plaintiff, MEMORANDUM v. AND ORDER

ARCHER WESTERN CONSTRUCTION, LLC, and TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA,

Defendants.

This matter is before the Court on plaintiff Seedorff Masonry, Inc.’s (“Seedorff”)1 Motion to Exclude (Filing No. 54) the testimony of defendants Archer Western Construction, LLC (“Archer”) and Travelers Casualty and Surety Company of America’s (“Travelers” and collectively, “defendants”) expert Randy A. Rapin (“Rapin”). For the reasons stated below, that motion is denied. I. BACKGROUND2 On September 3, 2014, Archer entered into a general contract with the United States Department of Veteran Affairs (“VA”) to construct the VA’s new national cemetery in Omaha, Nebraska (the “project”). Archer subcontracted with Seedorff to complete the project’s masonry work. To do that, Seedorff obtained, supplied, and installed limestone for the project.

1This action arises under the Miller Act, 40 U.S.C. § 3131 et seq., which requires Seedorff bring this action “in the name of the United States,” id. § 3133(b)(3)(A). 2This Court’s Memorandum and Order dated August 20, 2019, denying Seedorff’s request for partial summary judgment gives a more detailed rendition of this case’s facts. All did not go well. Beginning in 2016 and continuing through 2017, Archer notified Seedorff the limestone Seedorff supplied did not comply with the project’s specifications. The VA rejected the limestone. Although Seedorff maintained the limestone met the project’s requirements, Archer withheld some payments to Seedorff. After exhaustive discussion between Seedorff, Archer, and the VA, the VA relented and issued a formal letter accepting the limestone “as is” on December 7, 2017. Seedorff sued (Filing No. 1) the defendants on January 22, 2018, alleging Archer owes Seedorff $1,368,474 for its work on the project.3 Archer filed a counterclaim (Filing No. 15), seeking at least $760,000 in damages for costs allegedly caused by Seedorff’s delays and travel expenses Archer incurred negotiating with the VA about the limestone on Seedorff’s behalf. To support their position, the defendants retained Rapin as an expert to determine whether Seedorff delayed the project. Rapin issued a report (Filing No. 55-1), which describes Rapin as a senior consultant at J.S. Held, LLC, a construction-services and consulting company. Rapin claims “specialized education and experience in the areas of construction cost and cost analysis, project scheduling, schedule analysis, project controls and project management.” In his report, Rapin opined, among other things, Seedorff delayed the project and required Archer to expend additional resources. On March 18, 2019, the defendants served Seedorff their expert designation of Rapin with his report. The Amended Final Progression Order (Filing No. 46) set the deadline to file motions to exclude expert testimony as July 17, 2019, but the Court extended (Filing No. 50) that deadline to August 23, 2019. With a bench trial scheduled for October 15, 2019, Seedorff now moves to exclude Rapin’s testimony arguing Rapin’s

3In certain federal construction contracts, the Miller Act requires general contractors to obtain a bond to protect the payment of subcontractors. See 40 U.S.C. § 3131(b). Here, Archer procured a bond from Travelers, and Seedorff alleges Travelers is responsible for the bond payment. report does not meet the requirements of either Federal Rule of Evidence 702 or Federal Rule of Civil Procedure 26(a)(2)(B). II. DISCUSSION A. Rule 702 Rule 702 “is one of admissibility rather than exclusion.” Lauzon v. Senco Prods., Inc., 270 F.3d 681, 686 (8th Cir. 2001) (quoting Arcoren v. United States, 929 F.2d 1235, 1239 (8th Cir. 1991)). A qualified expert’s opinion is admissible under Rule 702 if (1) it is “based on sufficient facts or data,” (2) it is “the product of reliable principles and methods,” and (3) the expert “reliably applied the principles and methods.” The expert’s “scientific, technical, or specialized knowledge” must also assist the factfinder in understanding the evidence or determining a fact issue. Id. Here, Seedorff challenges both the facts and methodology underlying Rapin’s opinion. In considering the underlying facts for Rapin’s opinion, the Court notes “[g]enerally, ‘the factual basis . . . goes to the credibility of the testimony, not the admissibility, and it is up to the opposing party to examine the factual basis for the opinion in cross-examination.’” David E. Watson, P.C. v. United States, 668 F.3d 1008, 1014 (8th Cir. 2012) (quoting Nebraska Plastics, Inc. v. Holland Colors Am. Inc., 408 F.3d 410, 416 (8th Cir. 2005)). The Court must exclude an expert opinion only if it is “so fundamentally unsupported” it cannot assist the factfinder. Id. (quoting Nebraska Plastics, 408 F.3d at 416). Seedorff contends Rapin considered the wrong “contract completion date” and “actual completion date” for Seedorff’s work on the project, and Rapin could not “make a reliable conclusion” with those mistakes. Further, Seedorff asserts the project schedules on which Rapin relied combined work performed by Seedorff with work performed by other subcontractors into “single activity ID codes,” making it “impossible for [Rapin] or any other expert to link any construction delays to Seedorff.” The defendants respond Seedorff is mistaken. They argue Seedorff has “conflate[d] the [project’s] as-planned completion date—that is, the date [Archer] was to complete the entire Project . . .—with Seedorff’s as-planned completion date—the date that Seedorff was to complete its Subcontract work.” And the defendants contend Seedorff’s assertion about the project schedules lack support. The Court finds the parties’ disagreements over the underlying facts in this case do not warrant wholly excluding Rapin’s testimony. See Synergetics, Inc. v. Hurst, 477 F.3d 949, 956 (8th Cir. 2007). Instead, Seedorff can address any deficiencies in the basis for Rapin’s opinion at the bench trial through cross-examination. See David E. Watson, 668 F.3d at 1014. Turning to Rapin’s methodology, the Court performs a gatekeeping function and preliminarily decides whether an expert’s methodology is reliable. See Daubert v. Merrell Dow Pharm., Inc., 509 U.S. 579, 594-97 (1993). “The main purpose of Daubert exclusion is to protect juries from being swayed by dubious scientific testimony.” In re Zurn Pex Plumbing Prods. Liab. Litig., 644 F.3d 604, 613 (8th Cir. 2011). However, in bench trials where the judge is the factfinder, “[t]here is ‘less need’ for this ‘gatekeeping function.’” United States v. McDaniel, 925 F.3d 381

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
In Re Zurn Pex Plumbing Products Liability
644 F.3d 604 (Eighth Circuit, 2011)
Timothy Duane Arcoren v. United States
929 F.2d 1235 (Eighth Circuit, 1991)
Jane Doe v. V. Leroy Young
664 F.3d 727 (Eighth Circuit, 2011)
David E. Watson, Pc v. United States
668 F.3d 1008 (Eighth Circuit, 2012)
Fred Lauzon v. Senco Products, Inc.
270 F.3d 681 (Eighth Circuit, 2001)
Wegener v. Johnson
527 F.3d 687 (Eighth Circuit, 2008)
Patricia Jackson v. Allstate Insurance Company
785 F.3d 1193 (Eighth Circuit, 2015)
United States v. Terreall McDaniel
925 F.3d 381 (Eighth Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
United States of America, for the use and benefit of Seedorff Masonry, Inc. v. Archer Western Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-seedorff-masonry-inc-ned-2019.