United States of America for the Use and Benefit of H & S Industries, Inc., as Assignee of Cass County Stone Corp. v. F. D. Rich Co., Inc., and Transamerica Insurance Co., United States of America for the Use and Benefit of H & S Industries, Inc., as Assignee of Cass County Stone Corp. v. F. D. Rich Co., Inc., F. D. Rich Co., Inc. v. United States Fidelity & Guaranty

525 F.2d 760
CourtCourt of Appeals for the Seventh Circuit
DecidedNovember 17, 1975
Docket74--1670
StatusPublished
Cited by10 cases

This text of 525 F.2d 760 (United States of America for the Use and Benefit of H & S Industries, Inc., as Assignee of Cass County Stone Corp. v. F. D. Rich Co., Inc., and Transamerica Insurance Co., United States of America for the Use and Benefit of H & S Industries, Inc., as Assignee of Cass County Stone Corp. v. F. D. Rich Co., Inc., F. D. Rich Co., Inc. v. United States Fidelity & Guaranty) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America for the Use and Benefit of H & S Industries, Inc., as Assignee of Cass County Stone Corp. v. F. D. Rich Co., Inc., and Transamerica Insurance Co., United States of America for the Use and Benefit of H & S Industries, Inc., as Assignee of Cass County Stone Corp. v. F. D. Rich Co., Inc., F. D. Rich Co., Inc. v. United States Fidelity & Guaranty, 525 F.2d 760 (7th Cir. 1975).

Opinion

525 F.2d 760

UNITED STATES of America for the Use and Benefit of H & S
INDUSTRIES, INC., as Assignee of Cass County Stone
Corp., et al., Plaintiffs-Appellants,
v.
F. D. RICH CO., INC., and Transamerica Insurance Co.,
Defendants-Appellees.
UNITED STATES of America for the Use and Benefit of H & S
INDUSTRIES, INC., as Assignee of Cass County Stone
Corp., et al., Plaintiffs-Appellees,
v.
F. D. RICH CO., INC., Defendant-Appellant.
F. D. RICH CO., INC., Plaintiff-Appellee,
v.
UNITED STATES FIDELITY & GUARANTY, Defendant-Appellant.

Nos. 74--1670, 74--1687 and 74--1700.

United States Court of Appeals,
Seventh Circuit.

Argued April 3, 1975.
Decided Oct. 16, 1975.
Rehearings and Rehearings En Banc
Denied Nov. 17, 1975.

George E. Buckingham, Goshen, Ind., Robert L. Miller, South Bend, Ind., for H & S Ind.

Thomas M. Shoaff and N. Reed Silliman, Fort Wayne, Ind., for F. D. Rich Co.

James W. Riley, Jr., Indianapolis, Ind., for U. S. Fidelity & Guaranty.

Before CUMMINGS and PELL, Circuit Judges, and PERRY, Senior District Judge.*

PELL, Circuit Judge.

The United States of America contracted with the F. D. Rich Co., Inc., (Rich) as general contractor to build a 200 family housing project at Bunker Hill (now Grissom) Air Force Base near Kokomo, Indiana. Transamerica Insurance Co. was surety of Rich for the benefit of the United States. Cass County Stone Corp. (Cass) was a subcontractor of Rich who was, inter alia, to clear and grade the site to specifications, install a storm drainage system, and prepare the ground in the form of building pads on which a foundation and a concrete slab would be poured by others. United States Fidelity and Guaranty Company (USF&G) was surety of Cass for the benefit of Rich. H & S Industries, Inc., (H & S) is the assignee of Cass of all Cass's claims against Rich.1

The housing project could scarcely be characterized as other than a disaster for all concerned parties. It was scheduled to be completed by July 4, 1970, but was not accepted by the government until July 27, 1973. Rich experienced a loss of over a million dollars even though the contract price was only $3,360,000. Cass abandoned the project before completing its work, alleging nonpayment of amounts due from Rich, and later filed suit against Rich for these amounts and other damages. Rich counterclaimed for damages alleging breach of the subcontract by Cass.

After a lengthy bench trial, the district court issued a thirty-one page (unpublished) memorandum carefully setting forth its findings and conclusions. It found that Cass failed to complete its work on the building pads until 292 days after the date Rich scheduled their completion. It found Rich's schedule was within its authority as provided in the contract and that the time provided was within industry standards. The court further found that the delay resulted in 292 days delay to the entire project because the building pads were on the critical path of the project; viz., no work could be done by other trades on the buildings until the ground was compacted so that concrete slabs could be poured on which the buildings would be built. The court found:

'(Cass) did not prosecute its work under the subcontract diligently and did not maintain sufficient men and equipment forces to prosecute the various segments of its work simultaneously under the subcontract irrespective of the extra work and materials required by the contractor as recited above. The subcontractor was under financed to meet its obligations under the subcontract. When one segment of its work proceeded, the other lagged, and when a shift was made to any new area of its obligations under the subcontract, it caused the preceding areas of work to dissipate or cease entirely. The subcontractor failed to complete any of its work items within the time required by the original contract schedule of which the subcontractor was fully informed at all pertinent times.'

Nevertheless the court found that Rich caused one-half (146 days) of this delay by failing to place rock on the subgrade for the road through the project to provide temporary access during construction. Placing this rock on the road would also have enabled water to drain from the construction site. A major problem throughout the construction period was pooling of water.

In accordance with these findings, damages were awarded against Cass and its surety for causing 146 days delay to Rich. Damages were also awarded against Cass for certain payments made to Cass and to Cass subcontractors who had not been paid, for payments made to Cass subcontractors to complete subcontract work, and for deficiencies charged by the government against Rich. Cass was allowed to set off the cost of repairing damages by Rich to Cass's work and payment for work requested by Rich which was in addition to the work indicated in the subcontract. The details of these awards are set out in the first column of figures of Schedule A appended to this opinion.

Following entry of judgment and amendment to that judgment, USF&G and H & S for the benefit of Cass appealed; Rich cross-appealed.

I. Propriety of Cross-Appeal

Cass, by motion, requested Rich's cross-appeal be dismissed on the grounds that Rich had accepted benefits of the judgment in its favor. Following entry of the judgment, counsel for each party signed an agreement entitled 'Waiver of Costs and Limited Waiver of Interest.' Cass now alleges that the attorney who signed the agreement was not authorized to do so and that this attorney no longer represents Cass. The attorney who signed the agreement had been Cass's attorney at trial. We need not decide whether this attorney had actual or apparent authority to bind Cass or whether his lack of authority affects the validity of the agreement as it applies to Rich because of our interpretation of the agreement.

The parties first dispute whether federal law or Indiana law should be applied to determine Rich's right of appeal. Cass argues that Indiana law should be applied relying generally on Erie R.R. Co. v. Tompkins, 304 U.S. 64, 58 S.Ct. 817, 82 L.Ed. 1188 (1938). Also in Moser v. Buskirk, 452 F.2d 147 (7th Cir. 1971), this court accepted and commented favorably on a stipulation of counsel in a diversity case which followed Indiana law and indicated that acceptance of benefits of a judgment precludes an appeal. There is no indication in Moser that the question of which law to apply was argued or considered. It is by no means certain that this is the law of Indiana today.2

In Dorin v. Equitable Life Assurance Society, 382 F.2d 73 (7th Cir.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
525 F.2d 760, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-h-s-industries-inc-ca7-1975.